Flow Charts
Clause 20.4 Has either party referred* the matter in dispute to the DAB, copy to other party?
yes
Clause 20.4 Has DAB given notice of his decision* to both parties within 84 days of receipt of reference?
yes
Clause20.4 Has either party, within 28 days of DAB's decision, given notice to other party, of dissatisfaction
Clause 20.5 Arbitration may commence after 56 days (Clause 20.6 Sets down the rules applying to the arbitration process)
Notes:
Party means the Employer or the Contractor * Reference/Decision must state that it is issued pursuant to Clasue 20.4
yes
no Clause 20.1 2nd Paragraph No EOT may be given and Employer discharged from liability
no Clause 20.1 Amount of claim may be limited if failure has prevented or prejuduced proper investigation but Contractor may still be entitled to EOT
yes
no
yes
Engineer to act
yes
no
no Unspecified
yes 50% of retention released Note: Schedule of Payment approach Clause 14.4, may be written into the
no
no unspecified
yes
yes yes Clause 14.13 Engineer issues Final Payment Certificate to Employer, copy to Contractor within 28 days Clause 14.7 Employer pays FPC within 56 days yes no Clause 14.8 Contractor entitled to interest at rate stated in Appendix
Clause 14.11 Contractor submits Final Statement Clause 14.12 Contractor submits written discharge
Note: Upon the issue of the Taking-Over Certificate, one half of the Retention Money shall certified by the Engineer for payment to the Contractor Upon the expiration of the Defects Notification Period, the other half of the Retention Money shall certified by the Engineer for payment to the Contractor unless there is outstanding work pursuant to Clauses 11 and 14.9. Copyright Cardno MBK International Pty Ltd