Professional Documents
Culture Documents
1. Project Introduction
2. Problem Definition
3. Design Basis
4. Pipeline Mechanical Design
5. Pipeline Outline Installation Analysis
6. Repair Methodology
7. Cost Estimate and Schedule
8. Valve Skid Design
9. EIA Review
10. HAZID & HAZOP Action Items
11. Prof. Andrew Palmer’s Review
12. Closeout Report
13. Discussion and Close Out
Project Introduction
KP 133.5
KP 110.5
FEED OBJECTIVES
Repair Method
Cost
Flange
Barred 5D Gate Shut-down
Connections/ Hot Taps STOPPLE
Tees Bend Valve Time Hardware Construction Total
KaMos Gaskets
Cost Cost Cost
CM – Reduced 6
Nil 4 Nil Nil Nil 4 – 6 Wks US$3.3 US$30M US$33.3
Downtime (4 in-place)
Zero
8 2 x 28”
Downtime 6 4 2 4 Nil US$9.6M US$40M US$49.6
(6 in-place) 2 x 16”
Method
Note:
2. CM – Conventional Method
3. The hardware cost stated above includes 10% for transportation cost.
Comparison Between Both Methods
Reduced Downtime Method Zero Downtime Method
Advantages • No flange connections along the • Zero Shut-down time and any delay
pipeline in construction will not disrupt flow
• Involves less construction and to the consumers
diving work • Restoration of full design pressure
before completion of repair
• Equipment procured offers flexibility
to switch to reduced down time
method
Disadvantages • Stoppage of gas supply to • 6 flange connections
consumers for 4 to 6 weeks • Involves more construction / diving
• Delay in construction work will result work
in more stoppage of gas supply to • 6 In-place hot-tap clamps
consumers
• After commissioning sales gas will
have some water till complete
dryness is achieved
• Equipment procured does not offer
flexibility to switch to zero down time
method
• 4 In-place hot-tap clamps
Material Cost US$3.3M US$9.6M
Construction Cost US$30.0M US$40.0M
Comparisons of Risks
Reduced Downtime Method Zero Downtime Method
1. Gas Freeing the abandoned pipeline 1. Gas Freeing the abandoned pipeline
Pipelay Subsea
Cal Dive
Saipem
Global
Acergy
Technip Subsea 7
Valve Skid Design
Valve Skid Design
Valve Skid Design
Valve Skid Design
EIA Action Plan
EIA Action Plan
EIA Action Plan
HAZID & HAZOP Action Items
7. Overall Schematic Done EPC Contractor to perform final HAZOP and HAZID and update
overall schematic.
Project Status – Engineering
Installation Methodologies
4. HAZID and HAZOP Done EPC Contractor to perform HAZID and HAZOP based on the
execution plan and procedures developed by EPC Contractor
Project Status – Engineering
2. Structural Analysis - SACS Done EPC Contractor to re-check installation analysis and design
Model
installation aids based on the final skid design and equipment /
vessel proposed for installation.
3. Drawings Done
EPC Contractor to develop detailed fabrication drawings.
Project Status – Engineering
Material Specifications
S/N Activities Status Further Actions
1. Flanges, Bolts, Nuts, Gaskets Done -
and Fittings
4. Subsea Mechanical Connectors Done EPC Contractor to attend all FAT testing for both mechanical
& Hot Tap Assembly connectors and hot tap assemblies
EPC Contractor to perform mock testing before the actual
installation works
5. Field Welding and NDT Done EPC Contractor to prepare welding and NDT procedures
6. Construction Materials Not Done All non-long lead and construction materials to be procured by
EPC Contractor
Project Status – Engineering
Installation Specifications
2. Survey and Monitoring Done EPC Contractor to develop detail survey and monitoring
procedures.
3. Pipeline Cleaning, Gauging, Done EPC Contractor develop detail pre-commissioning procedures.
Pigging and Hydrotest Final HAZOP and HAZID need to be performed
Project Status – Engineering
Drawings