You are on page 1of 39

WELCOME

ALL FACULTY MEMBERS & ALL PARTICIPANTS OF INTEGRATED COURSE-10109

ACKNOWLEDGEMENT

WE LIKE TO PAY OUR GRATITUDE TO SH. A. K. GOEL DIRECTOR IRICEN WHO IS LEADING &GIVING PERFECT INVIRONMENT FOR OVERALL DEVELOPEMENT AND LEARNING AT IRICEN. WE EXPRESS OUR SINCERE THANKS TO SH. V. B. SOOD PROF/BR FOR HIS VALUABLE GUIDANCE IN PREPARING THIS PROJECT. WE ALSO EXTEND OUR SPECIAL THANKS TO SH. NEERAJ KHARE COURSE DIRECTOR FOR HIS VALUABLE GUIDANCE AND PERSONEL ATTENTION IN EACH AND EVERY ASPECT THROUGHOUT THE COURSE. WE EXPRESS OUR SINCERE THANKS TO ALL THE FACULTY OF IRICEN FOR THEIR VALUABLE LECTURES WHICH HAVE HELPED US IN UPGRADING OUR KNOWLEDGE IN ALL THE AREAS.

BALANCED CANTILEVER CONSTRUCTION OF PSC BRIDGE

CAST-IN- SITU CONTINUOUS UNIT

INTEGRATED COURSE 10109

PRESENTED BY :
SHIV KUMAR AXEN/CONST./REWARI/NR A.D.AGNIHOTRI AXEN/CONST./GONDA/NER A.K.BARSAIYAN ADEN/BR/BHOPAL/WCR GUIDED BY: SH. V.B.SOOD PROFESSOR BRIDGE

INTRODUCTION

BALANCED CANTILEVER CONSTRUCTION IMPLIES CONSTRUCTION OF CANTILEVER SEGMENTS FROM A PIER IN A BALANCED FASHION ON EACH SIDE UNTIL THE MID SPAN IS REACHED AND A CLOSURE KNOWN AS STITCH SEGMENT IS MADE WITH OTHER HALF SPAN CANTILEVER CONSTRUCTED FROM THE PRECEDING PIER. THE PROCESS

THE FORM WORK IS SUSPENDED FROM THE END OF THE LAST SEGMENT. THE NEW SEGMENT IS CAST AND ONCE THE CONCRETE HAS DEVELOPED A PREDETERMINED STRENGTH, THE SECTION IS POST TENSIONED TO THE REST OF THE BRIDGE. THE SAME ERECTION PROCESS IS REPEATED TILL THE STRUCTURE IS COMPLETED.

CONSTRUCTION SEQUENCE

Stitch Segment 3 Mtr Long Segment End Span

Pier Head

Pier Head

Pier 1

P2

P3

P4

FUNDAMENTALS OF DESIGN

Building a bridge deck by succession of segments where each segment carries the weight of the next segment Each segment is integrated with the previous one as soon as it is strong enough. Each segment becomes self supporting and also becomes a base for a new segment.

The stability of cantilever is secured at each step by pre-stressing cables provided in the upper fiber - In order to avoid asymmetric overturning moments, the construction is done symmetrically on the pier on both the sides.

NECESSITY OF CAST-IN-SITU CONSTRUCTION


WHEN

ACCESS BELOW THE BRIDGE IS EXPENSIVE OR PRACTICALLY IMPOSSIBLE DUE TO BUSY ROAD, RIVER, CANAL, DEEP VALLEY OR RAILWAY TRACK ETC. LONGER SPAN (WHERE LAUNCHING IS VERY COSTLY).

Construction over busy road

SEGMENTAL CONSTRUCTION OVER RAILWAY TRACK

DMRC Cast in place balanced cantilever

SEGMENTAL CONSTRUCTION IN PROGRESS OVER A RIVER/ SEA

CONSTRUCTION MACHINERY
1. BATCHING PLANT. 2. TRANSIT MIXERS. 3. CONCRETE PUMP. 4. WELDING GENERATOR. 5. CONCRETE VIBRATORS. 6. CONCRETE NEEDLES.(6O&25MM DIA). 7. COMPRESSOR. 8. TYRE MOUNTED CRANE. 9. HAND WINCH. 10. CHAIN PULLEY BLOCK. 11. PIPE WRENCH. 12. CLC GANTRIES (80T)-4NOS. 13. GROUT PUMP.

Concrete Pump

Bridge builder

CRITICAL CONSTRUCTION MATERIALS


1. POT-PTFE BEARINGS 2. ANCHORAGES-19K15,AND GRIPS. 3. BEARING PLATES. 4. HT STRANDS (IS-14268 CLASS-2) 5. GI SHEATHING PIPES-ID 110MM. 6. CEMENT OPC 53 GRADE 7. REINFORCEMENT STEEL IS-1786 8. ADMIXTURE IS-9103

OPERATION SEQUENCES
1. SURVEY WORK: CENTER LINE MARKING FOR FOUNDATION OF TRESTLES WILL BE DONE WITH THE HELP OF THEODOLITE/ TOTAL STATION. 2.CONSTRUCTION OF PIER HEAD: (a). TRESTLE FABRICATION AND ERECTION FOR CONSTRUCTION OF PIER HEAD. (b). DESIGN AND FIXING OF BEARINGS.

OPERATION SEQUENCE

OPERATION SEQUENCES

Cont.

(c). SUPER STRUCTURE STABILIZING ARRANGEMENTS: THE ADDITIONAL TRESTLE AND SAND JACKS OF 350 TONNE CAPACITY ARE PLACED AT REQUIRED LOCATIONS. (d). CALCULATION OF CO-ORDINATES FOR HORIZONTAL CURVE AND DECK LEVEL FOR VERTICAL CURVE. (e). SOFFIT, WEB EXTERNAL AND DECK SHUTTERING. (f). SOFFIT, WEB AND DECK REINFORCEMENT.

OPERATION SEQUENCES CONTD.


(g). CABLE PROFILING. (h) EMBEDDED FIXTURES. (i). END STOPPER SHUTTERING. (j). CONCRETING WITH CONCRETE PUMP. (k). CURING IS DONE FOR 14 DAYS. (l). HYDRO TESTING OF SHEATHING PIPE AT 0.3 MPa PRESSURE. (m). PRESTRESSING AND GROUTING: STRESSING STARTS ONLY IF CONCRETE ATTAINS THE DESIRED COMPRESSIVE STRENGTH.

OPERATION SEQUENCES CONTD.


3.CONSTRUCTION OF CANTILEVER: (a). FABRICATION AND ERECTION OF CLC GANTRIES (BRIDGE BUILDERS)(2+2=4SETS). (b). PRE-CAMBER CALCULATION. (c). GANTRY ALIGNMENT AND LEVEL. (d). SOFFIT SHUTTERING. (e). EXTERNAL SHUTTERING. (f). REINFORCEMENT, SHEATHING PIPE AND CABLE PROFILING.

OPERATION SEQUENCES CONTD.


(g). INTERNAL SHUTTERING OF CLC GANTRY IS MOVED ON MONO RAILS AND FIXED TO THE LOCATION AS PER DRG. (h). END STOPPER SHUTTERING. (i). APPLYING ADHESIVE (NITO BOND ETC.) ON FACE OF OLD CONCRETE. (j). CONCRETING OF 3M LONG SEGMENTS ON EITHER SIDE OF PIER HEAD SIMULTANEOUSLY OR ONE BY ONE USING CONCRETE PUMP. (k). CURING.

OPERATION SEQUENCES CONTD.


(l). PRE STRESSING AND GROUTING. (m). RELEASING OF CLC GANTRY FORM WORK. (n). MOVEMENT OF CLC GANTRY (BRIDGE BUILDER.) FOR SHIFTING TO NEXT UNIT. (o). LEVELLING AND ALIGNMENT OF CLC GANTRIES. (p). SIMILAR PROCEDURE TO BE ADOPTED FOR OTHER SEGMENTS.

Cast in place balanced cantilever

OPERATION SEQUENCES CONTD.


4.CONSTRUCTION OF END SPAN.

CASTING OF END SPAN IS DONE AFTER THE CANTILEVER CONSTRUCTION. ACTIVITIES INVOLVED REMAINS THE SAME AS EXPLAINED FOR PIER HEAD CONSTRUCTION. AFTER CASTING OF CLC SPAN, THE REMAINING PORTION OF LENGTH 2.50M SEGMENT IS TO BE STITCHED.

5.CASTING OF STITCH SEGMENT

SAFETY PRECAUTIONS
1. LOAD TEST OF CRANE SHOULD BE DONE BY THIRD PARTY. 2. WORKING PLATFORM AND SAFETY NETS WILL BE PROVIDED. 3. SAFE ACCESS BY MEANS OF LADDER WILL BE PROVIDED FROM GROUND TO DECK TOP. 4. THE MACALLOY BAR IS DESIGNED FOR FOS =3. 5. ALL ELECTRICAL CONNECTIONS SHOULD BE PROPER. 6. TEMPORARY HAND RAIL WILL BE FITTED FOR DECK SLAB CASTING. 7. FALL ARRESTER SHOULD BE PROVIDED. 8. HEIGHT GAUGES AND CAUTION BOARDS SHOULD BE FIXED FOR ROAD USERS. 9. PROPER PERSONAL EQUIPMENTS (PPE) LIKE SAFETY HELMETS, SAFETY SHOES, SAFETY BELTS AND SAFETY NETS SHALL BE USED.

HEIGHT GAUGE FOR ROAD USERS

SAFETY NET

DOCUMENTATION AND RECORDS


1. POUR CARD. 2. BAR BENDING SCHEDULE. 3. REINFORCEMENT INSPECTION CHECK LIST. 4. INSPECTION CHECK LIST BEFORE APPROVAL OF CONCRETE. 5. CHECK LIST FOR SHEATHING, ANCHORAGES, AND EMBEDDED FIXTURES. 6. STRESSING CHART AND PRE STRESSING REPORT. 7. GROUTING REPORT. 8. SAFETY CHECK LIST FOR CLC WORK.

ADVANTAGES
1.THIS METHOD HAS GREAT ADVANTAGES OVER THE OTHER FORMS OF CONSTRUCTION IN URBAN AREA WHERE TEMPORARY SHORING WOULD DISRUPT TRAFFIC SERVICES BELOW. 2.SUITABLE OVER WATERWAYS WHERE FALSE WORK WOULD NOT ONLY BE EXPENSIVE BUT ALSO A HAZARD. 3.USEFULL WHERE SPAN LENGTH IS MORE BUT LAUNCHING OF GIRDER IS NOT POSSIBLE.

BRIDGE OVER WIDE RIVER

ADVANTAGES CONTD.
4. ONLY A SMALL PORTION OF THE SUPER STRUCTURE ADJACENT TO THE PIER /ABUTMENT WILL REQUIRE USE OF FALSE WORK. 5. PROCESS IS SAFE AND ECONOMICAL. 6. ADOPTABILITY TO CURVATURE AND SUPER ELEVATION. 7. USEFUL FOR ODD SIZES, SINGLE SPAN ETC AS FALSE WORK IS LESS.

LONGER SPAN OVER RLY TRACKS

DISADVANTAGES
1. CAST-IN-SITU SEGMENTAL CONSTRUCTION IS A RELATIVELY SLOW CONSTRUCTION METHOD IN COMPARISON TO PRE CAST SEGMENTAL CONSTRUCTION. 2. THE WORK IS PERFORMED IN SITU i.e EXPOSED TO WEATHER CONDITIONS. 3. THE TIME DEPENDENT DEFORMATION OF CONCRETE BECOME VERY IMPORTANT AS A RESULT OF EARLY LOADING OF THE YOUNG CONCRETE. 4. HIGH PRECISION IS REQUIRED.

THANKS

You might also like