1 Project Profile : Lifting of 20 tmc of water from foreshore of PJP and Ookachettivagu Project Pondage : G. O. Ms. No. 166, I & CAD, Dt: 30-102003 for Rs. 1426.30 Crores : 13 Nos. : Rs. 1417.92Crs.
2 3 4
5
6
2004-05 : Rs. 108.68 Crs. (Incl. Sangambanda BR) 2005-06 : Rs. 238.50 Crs. TOTAL : Rs. 347.18 Crs. 7 8 Utilisation Ayacut New Ayacut : 20 TMC : 2,03,000 Acres
Stabilization
: 4,000 Acres
Lift Height
No. of Pumps Total pumps capacity 11 Total Power required
: 61 M
: 6 Nos. : 48 MW : 96 MW
Acquired :
Requisitioned : 13 Est. Cost for LA Est. Cost for R & R Mobilisation Advance :
14
15
22.10 Crs.
Rs.14.99
Description
Awarded
CATEGORY-II
Excavation of High level right main canal, distributary system including construction of CM & CD works from Sangambanda BR to feed ayacut of 18400 Acres. Excavation of High level left main canal, distributary system including construction of CM & CD works etc. to feed an ayacut of 35,800 Ac. Under Sangambanda BR Investigation, design, estimation and excavation of canal distributary system including construction of CM & CD works from Yenukunta BR, Waddewata (V), Kottakota (M), Mahabubnagar (D) to feed about 14,000 Acres upto Rangasamudram BR. Excavation of canal distributary system including constrction of CM & CD works from Ranga Samudram to feed an ayacut of 21,000 Acres Investigation, design, estimation and execution for converting the existing Rangasamudram tank, near Sri Rangapuram (V) Pebbair (M), Mahabubnagar district as balancing reservoir under Bhima Lift Irrigation Project (Lift-II) Investigation, design, estimation and execution for convesting the existing Shankarasamudram tank, near Knaipally (V) Kothakota (M), Mahabubnagar district as balancing reservoir under Bhima Lift Irrigation Project (Lift-II) M/s. R.M.M. & BRC (JV)
13
57.97
14
68.94
15
51.270
16
70.800
17
41.540
18
42.100
CATEGORY-II
Description
Awarded
M/s. G.H. Reddy & Associate K.K.R & Co (JV) M/s. KNR-SLEC (JV)
19
Shankara Samudram Balancing Reservoir Right Main canal. (i) Formation of Earth Dam with FRL +352m (ii) Construction of spillway, (iii) Construction of Head Regulator to let out into left and right main canals. Budpur Balancing Reservoir Investigation, Designs and excavation of left main canal, distributary system including construction of CM & CD works from budpur Balancing reservoir, Budpur (V), Atmakur (M), Mahabubnagar (D) to feed about 32,000 Acres
Investigation, Designs and excavation of right main canal, distributary system including construction of CM & CD works from budpur Balancing reservoir, Budpur (V), Atmakur (M), Mahabubnagar (D) to feed about 32,000 Acres
20
36.98
21
60.39
22
26.73
27
Investigation, Design, excavation of left main canal, distributary system including construction of CM & CD works from Sankarsamudam Balancing Reservoir . LIFT-I : Design, manufacture, supplying & erection of pumps, motors, electro mechanical works, including tunnel, cistern and pump house etc. Design and execution of Stage-I and stage-II pumping stations of LIFT-II at Thirumalayapalli & Kothakota (M), Mahabubnagar (D) on EPC basis. TOTAL
149.40
OC
383.349
OC
391.55
1417.919
Investigation completed
Designs Execution (Main canal) Qty. of earth work done No. of Machinery
1No.)
: Completed
: 9.2 KM approved against 24 KM : 15 KM length in progress against total length of 24.00KM : 6.00Lakh Cum against 37.32 Lakh Cum. : Deployed = 15Nos (Excavators =2 Nos.,Tipper-8Nos., T Roller-
Land Acquisition acres Expenditure Mob. Adv. Paid Mob. Adv. Recovered
: Required 1000 Acres, Requisition : 260 acres, Acquired 81 : Rs. 14.90 Crs. against Rs. 57.97 Crs., : Rs. 2.90 Crs. : Rs. 2.90 Crs.
Date of completion
:24-02-2007
Investigation Designs
Investigation Design
Execution (main canal) : 13 KM length in progress against total length of 30.25 KM Qty. of earth work done : 5,70,000 Cum against 20,00,000 Cum No. of Machinery
=2No.)
Land Acquisition
218.71Acs.
Investigation (HPs)
Execution
81.00 KM
Expenditure
Land Acquisition
Investigation
: Completed
Designs (Earth Bund & Weir) : 80% approved Execution Qty. of earth work done : Started : Cut off trench excavated for a length of 1.50 KM
Expenditure
Land Acquisition Nil
: Rs. 2.08 Crs. (Mob. Adv. Only) against Rs. 41.50 Crs.
: Required 2452.30Acres, Requi.: 2526.11Acrs Acquired
Investigation
Designs (Earth bund & Weir) : 80% of designs approved. Execution for : Yet to start (Water in the Tank & objections of Kanepally (V) want of inclusion of village in R & R Package. : Rs. 2.11 Crs. (Mob. Adv. only) against Rs. 42.10 Crs.
Expenditure
Land Acquisition
Agreement Date
Period of Completion
: 19-02-2005
: 24 Months (Milestones : 8)
Investigation
Execution
Qty. of earth work done : 5.5 Lakh Cum against 6 Lakh Cum. Qty. of concrete work done: 2500 cum against 30,000 cum Structure Expenditure Mob. Adv. Paid Mob. Adv. Recovered : 25 Nos. executed against 110 Nos. : Rs. 16.68 Crs. against 36.79Crores : Rs. 3.68 Crs. : Rs. 0.70 Crs.
Land Acquisition
: Completed (6.10 KM) : Approved : Qty. of earth work 5.64 Lakh cum completed. : Rs. 15.43 Crs. (Inc. Mob. Adv. Rs. 3.43 Crs.) against Rs. 36.98Crs.
Designs (HPs & Structures) : Length 28.65 Km approved against 37.825Kms. Execution (Canal) Structures Machinery deployed Land Acquisition Acs. : 28.10 KM length in progress against total length of 37.825KM
: 13 Nos. executed against 79 Nos.
: 10Nos. (Tippers-4Nos, Poclains-4Nos, DRR-1No,Dozer-1No.) : Required 1386 Acres, Requisitioned: 316Acs Acquired 98
Expenditure Crs.
: Rs. 18.04 Crs. (inc. mob. Adv. Rs. 6.04 Crs.) against Rs. 60.39
Period of Completion
: 24 Months (8 milestones)
Mahabubnagar (D) to feed about 32,000 Acres Investigation : Completed (15.025 KM)
Design (HPs)
Execution (Canal)
: Approved
: 14.50 KM length in progress against total length of 15.025KM
Qty. of earth work done : 2.86 Lakh cum against 2.95 Lakh cum Qty. of concrete work done: 5200 cum
Structures
Expenditure Crs. Mod. Adv. Recovered
Machinery deployed
Land Acquisition
Balancing Reservoir .
AGREEMENT DATE :
9/2005
Name of the Contractor : M/s Patel Engineering Ltd. Agreement Amount : Rs. 383.349Crores
Agreement Date
Period of Completion
: 07-03-2005
: 30 Months (10 milestones)
Designs (Tunnel, Pump House, Surge pool, Cistern) : 2.70 KM approved against 3.0705 Execution
house)
Qty. of earth work done : 5.50 Lakh Cum against 7.82 Lakh Cum.
No. of Machinery
Land Acquisition Acs.
: Rs. 52.16 Crs. against Rs. 383.34 Crs. (Mob. Adv paid Rs.
Name of the Contractor : M/s NEC NCC MAYTAS (JV Agreement Amount Agreement Date Period of Completion : Rs. 391.55 Crores : 14-03-2005 : 30 Months
Designs (Tunnel, Pump House, Surge pool, Cistern) : Approved Execution : Excavation 0.383Km in progress (approach channel, tunnel, surge pool & Pump house)
Qty. of earth work done : 1,70,000 Cum against 5 Lakh Cum. No. of Machinery Land Acquisition Expenditure Mob. Adv. Paid Mob. Adv. Recovered : Deployed = 18 Nos (Excavators = 4 Nos., Dumpers = 12 Nos.,
Dozers = 2 Nos. etc)
: Required 135 Acres, Requisitioned 67 Acs. Acquired Nil : Rs. 71.58 Crs. against Rs. 391.55 Crs. : Rs. 19.58 Crores. : Rs. 6.00 Crores.