Solid Motors
GS1 Motor
No Concern
HES
MS3 MS2 MS1
751
743 733 736
1.83-2.17
1.57-1.80 1.63-1.87 1.31-1.70
8.00.2
8.00.2 7.80.2 7.80.2
8.039
8.075 7.893 7.735
NES
737
28-08-2009
1.68-1.91
7.80.2
7.634
No Concern
No Concern
Motor cases Propellant system Nozzle, Igniters & Initiators - No major deviations.
No Concern
Metallic Structures
Assessment on structures
Structure Core Base Shroud Assembly Aft End Closure Assembly Inter Stage 1/2M Assembly Inter Stage 2/3L Assembly Thrust Frame Assembly Inter Stage 1/2U Assembly Upper Stub Adaptor Identification BS 009 BS 008 BS 011 BS 09 BS 07 BS 08 BS 11 Issues Nil Status Green Green Green Green Green Green Green
Nil
Nil Nil Nil Nil Nil
MF/2313/07/02 & (238/0198/1) (XVF/757/9) MF/2313/07/03 & (238/0197/1) (XVF/757/12) MF/2313/07/04 & (238/0197/2) (XVF/757/14) MF/2313/07/05 & (238/0197/3) (XVF/757/20)
VE/5556/08/01 to 08 (XVF/ 664/02 to 08 &15)
Nil
Green
Nil
Green
No Concern
Assessment on structures
L40 Structures
Hardware SONC S4 BS-21 S3 TAAL-04 S2 BS-22 S1 TAAL-05 Issues Nil Status Green
ITS SBS
FIN Thermal Shroud Protection Plate
TAAL-04 SV-04
BS-29 TAAL-12 TAAL-15
TAAL-05 BS-22
BS-23 TAAL-13 TAAL-08
TAAL-06 TAAL-02
BS-30 TAAL-14 TAAL-07
SV-02 TAAL-03
BS-31 TAAL-15 TAAL-16
Nil Nil
Nil Nil Nil Nil
Green Green
Green Green Green Green
No Concern
Composite Subsystems
Composite Sub Systems L40 Throat GS2 Throat L40 Thermal Boot CC Vanes (CMSE Make) Pay Load Adaptor
Identification No
No Concern
VOQ test on two samples of flight batch, for extending the life completed successfully. Life extended to December 2011.
No Concern
Mechanical Integration
No Concern
Control Systems
L40 / GS2 EGC
Corrective actions
Clearance fit ensured by rework of the rotor. Relief provided at the shaft shoulder.
Qualification of 3 sets of bearings through gas motor & system level tests.
Run away condition test (9300rpm) in hot air at 300 deg C. Acceptance tests carried out on 8 sets of flight gas motors L110 Injector level hot tests on 2 qualification hardware. Performance normal
No Concern
3. Solenoid Valve
ISSUE: Failure of CADD make Solenoid Valve - Leakage seen during qualification cycling tests. ANALYSIS: Jamming observed between plunger and bobbin due to inadequate clearances . (-1 micron against 21 microns reported by M/s Raghav
aerospace. Spec: 25 to 75 microns).
CORRECTIVE ACTION: LPSC make valves were used for F06. Clearance at the interface in the range of 80 microns. The performance of these valves satisfactory during acceptance tests
SR views: Measurement inadequacy at work centre needs correction. Clearances also to be included in FCD list.
No Concern
Failure of RCI servo valve : The servo valve spool got stuck during component level acceptance tests (during 10 mA flow test ).
ANALYSIS
FA in progress However, for GSLV F06 MOOG servo valve is used. SR views:
FA of RCI servo valve to be completed
SR views: Impact on similar joints of L40 & GS2 EGC system to be studied. FA to be closed.
The performance of the EGC Packages during the tests at lab and at SHAR is normal.
AVIONICS SYSTEMS
Analysis: Traced to abnormal behavior of opamp inside NIM for inputs greater than -10 deg/s. Action: Design modified to clip input to -10 deg/s at the input of op-amp for analog rate channels.
No Concern
No Concern
ANALYSIS:
The reason is noise pick up through PCB tracks of frequency fixing capacitors of AD698 LVDT signal conditioning IC Capacitors repositioned by mounting on top of the IC and the original tracks disconnected for all the four loops.
ACTION:
RVDT Excitation measurement and Linearity tests at SHAR show good performance.
No Concern
No Concern
The torque levels measured are low and less than 5 Nm at 400 HZ and 9.5 Nm at 200Hz. The torque levels are comparable for CSCE Single box and 3 box AMC configurations for the same actuators The torque varies from actuator to actuator measured with the same Electronics and same method.
200 Hz
3 Box (AMC Versi on)
400 Hz
200 Hz
200 Hz
400 Hz
9.5
9.5
11
4.5
The actuator movement is at 200Hz when algorithm is engaged and at 400Hz only during the initial phase and at shutdown.
Verification
of Trajectory & DAP design inputs Assessment of mission requirements documents QA audit of DRT Actions --- Completed
No Concern
Flight Software
Major changes from D3 Implementation of Onboard Level Alignment in Navigation S/W. E2PROM Checksum Computation in Flight mode in Major Cycle periodicity
Passing of Z1 analog rate to navigation for RESINS rate computation (based on GSLV-D3 PFA recommendation)
Interface changes due to addition of GAINS package (in piggy back mode) and PRISM in place of SDAM in the NGC system MRC / AVR Algorithms related to GK Stage (three different regimes of operation) All mandatory Verification & Validation activities completed.
No Concern
Checkout Software
Major Changes Changes for Onboard Level Alignment and GK Stage Automatic Launch Sequence (ALS) Timing Changes New Linux Based Supervisory Checkout Console Verification & Validation Status Requirements and Design Reviews Code Inspection Module Level Testing of ALS Software Changes System Level T&E - Completed
No Concern
- Completed
No Concern
No Concern
No Concern