Professional Documents
Culture Documents
NTPC Limited
Indias Projected Growth is 7-8 % of GDP Projected power requirement by year 2012: Per capita consumption 1000 units per annum Installed capacity over 2,00,000 MW Projected power requirement by year 2032: Per capita consumption about 3000 units per annum Installed capacity about 6,00,000 to 7,00,000 MW
However government of India is targeting double digit growth rate (10%) and hence projections are likely to get revised upwards. The above necessitates : Sustainable Large Capacity Addition Program at higher efficiency Upgrading fleet of Old Power Stations which are inefficient and have poor availability
R&M and Re-powering India has large number of old plants which are inefficient and running below design capacity Operating pressure and temperature of these old plants are lower and there is no reheating in some of the units Fuel available at present is different from what plant were designed for Some of the equipments have degraded Re-powering of these plant can quickly increase the power generation at relatively lower cost to consumer Re-powering can increase the cycle efficiency and hence reduce emission of greenhouse gases and pollutants
APPROACH TO R&M
Depends on Age of the plant, its existing condition and generic problems in its inherited design Operational History & Problems being faced to run the plant Major modifications carried out from the original design condition Type of fuel & its cost To cater to changes in the input / output of the plant coal, water, power evacuation Source of availability of inputs for future Cost of generation Cost of Technology
WHY R&M?
To restore the original rated parameters by one to one replacements Improve performance by introduction of new technology. To upgrade the units to comply with fast changing Environmental / statutory standards / guidelines. To cater to technological obsolescence. Mega R&M Technology Upgrades. This would aim at both leveraging the technological advancements, as well as driving down the Cost Of Generation, while factoring in the emerging business scenario to meet the market determined price for power
Technological Options
Clean Coal Technology To reduce SOX ,NOX & CO2 Emissions Energy extraction from coal 1.PC fired 2.Fluidized bed combustion-Reduces Sox, NOx Emissions 3.Indirect combustion through coal gasification Sub Critical Steam Parameters To Supercritical Parameters Increase in Pressure and temperature to like 250bar and 565 deg C Re-powering Technology For better efficiency, pollution control and less cost besides life extension
Technological Options
Technological Options
TG & AUXILIARIES
Replacement of turbine blades with latest design. Modernization of condensors by change in type and material of tubes, augmenting with tube cleaning mechanism. Modernisation of power cycle equipments with more efficient pumps and improved Regenerative Heaters. Modification of air evacuation system with Vacuum pumps.
Technological Options
Gas Turbine
Inlet Air Cooling system. Online Compressor Washing System Dry Low NOx Burners. Improved metallurgy for improved life of Hot Gas Path Components Improved efficiency Thermal Barrier Coatings of Blades & Vanes. Improved major inspection intervals. Multi Fuel Firing
Technological Options
ELECTRICAL Up gradation of insulation of rotating machines from Class B to Class F. Up gradation of protection systems including diagnostic tools. Replacement of HV , EHV circuit breakers with SF6 / Vacuum breakers for stability and to overcome obsolescence. C&I Modernization of obsolete C&I systems with State- of-ArtTechnology. MISCELLANEOUS Augmentation Of CHP Augmentation Of Water Treatment Plants Introduction of Ash Water Re-circulation System.
EXPECTED BENEFITS
Increase in generation with improved performance Increase in safety, reliability, availability and operational flexibility Recapturing and/ or enhancing of unit capacity Extension of economic useful life by 15-20 years at comparatively lower capital cost Benefit by way of additional life Possibility of reducing cost of generation
Rehabilitation
20
40
years
Mega R&M
Opting for higher steam pressure & temperatures due to the availability of better material suited for these parameters improves heat rate and reliability Therefore, for old plant it may be worthwhile to consider mega R&M schemes to bring these plants up to the contemporary state of the art plants in terms of efficiency and availability Typically, such mega R&M may include up-rating, re-powering, higher process parameters resulting in enhanced efficiency, improved operational safety, reliability, advanced diagnostics etc. Mega R&M typically consists of replacements of major equipment / systems of the plant at marginally higher cost & longer shutdowns of the Units are inherent.
Plans for R&M The importance of R&M was recognised by the Government of India way back in 1984 when PHASEI R&M Programme for 34 thermal power stations in the country was launched by the Central Electricity Authority as a Centrally Sponsored Scheme The Government of India has now accorded high priority to R&M and Life Extension (LE) of old existing power plants. The funds in the form of loan assistance at concessional interest rates are being provided by the Government through Power Finance Corporation (PFC) for R&M works
iii)
iv) v)
Estimated Cost
Total Capacity involved Average PLF of the units before LE programme
vi) vii)
75% 23700 MU
viii)
10,747 MW
PARTICULARS
PARTICULARS
i)
i)
13
ii)
ii)
57
iii)
iii)
Estimated Cost
Estimated Cost
Rs.977 crores
Rs.977 crores
iv)
14270 MW
i)
18
12
ii)
34
31
iii)
Estimated Cost
Rs.6000 Crores
iv)
6,000 MW
7,090 MW
30 25
25 20 15 10 5 0 4
No of units
30 43
10 500MW
360 5000 110 MW and Below 200 & 210 MW 8910 500MW
1000
improved reliability
RESULTS
increased power output reduced power generation cost operation free of restrictions
Challenges in R&M
Limited Agencies for R&M implementation in the country. Prohibitive cost of New Technologies impediment for introduction on wider scale. Unfavorable cost benefit analysis.
CDM Potential in R&M Offers substantial CDM benefits reduction/substitution of coal by: through
NTPC R&M Project under CDM: NTPC has taken up Badarpur R&M project under CDM PIN is already prepared
R&M cost - Rs 1.50 Crs/MW PLF is around 88% as against 19% during takeover in Jun 1995.
R&M cost - Rs 1.17 Crs/MW PLF is around 85% as against 21% at the time of takeover in Jan 2000
110 MW Unit at AECO, Sabarmati has been upgraded to 120 MW by NASL with Turbine HR improvement of approximately 140 Kcal/Kwh. No. of 200/210 MW LMZ Units have been upgraded to 225 MW in other countries with considerable improvement in Heat rate. These are now being planned in India.
Governments Initiatives
Partnership in Excellence
CEA has identified 26 stations which are operating at a PLF of less than 40%. These stations would have a Partnership in Excellence with better performing utilities, so as to achieve an improvement in performance in the shortest possible time. Subsidized funds would be made available for this programme through PFC / REC. The target is to achieve a PLF of 60% in two years time.
Role of NTPC
NTPC has been entrusted the responsibility of 14 stations out of the identified 26. Site office has been opened at all the 14 stations and experts have been posted at all sites. The teams will aim to implement the customized O&M systems and will carry out one cycle of overhauls.
Governments Initiatives
Role of NTPC
NTPC has taken up consultancy services for a few of these stations. NTPC initially took up four power stations for R&M/LE (Total 1332.5 MW). Subsequently another six stations (1512.5 MW) were taken up for R&M / Life Extension (LE) / Recommissioning / Residual Life Assessment (RLA) Funds being provided by PFC / REC
APDP-R&M
Highlights of Achievement
Proj. PLF bef. PLF aft. % imp. in PLF SOC bef. SOC aft. % imp. APC in SOC bef. APC aft. % imp. in APC
23.97
72.66
203.13
28.60
0.80
97.20
22.30
11.43
48.75
36.78
65.41
77.84
5.28
1.88
64.40
12.59
9.88
21.52
45.00
84.00
93.19
3.00
0.70
76.67
12.40
10.23
17.50
In USA and other advanced countries utilities have largely gone for Mega R&M because of the age of their units & rapid changes in their business environment which required them to remain competitive and efficient
Hence, Mega R&M schemes such as up-gradation of process parameters, improved balding in turbines, Re-powering, & even installing machines of higher capacity on the same footprint were adopted
This was mainly achieved due to using low NOx burners in boiler, redesigning of LP turbine and cooling tower modernisation The emission levels of the units was reduced drastically due to use of low NOx burners, installing Flue Gas Desulfurification plant and optimisation of operation of ESP
Flue gas discharge through cooling towers, automatic concrete cutter for existing chimneys
Conclusion
Implementation of the R&M Schemes has benefited the stations by way of Overcoming Technological obsolescence. Low cost capacity addition Extending the life of equipment / components. Complying with Statutory and Environmental Norms Sustaining availability and improved performance There is huge potential in India for R&M activities because of large number of old plants which are inefficient and running below design capacity