1. Erection and alignment of kiln bases and gearbox supports 2. Preassembly of kiln shell heavy sections (tyre sections) 3. Preparation of Kiln bearings, scraping if necessary 4. Erection and alignment of bearings, rollers and thrust device 5. Erection of kiln drive 6. Preassembly of kiln light sections 7. Erection of kiln heavy and light sections, alignment and welding 8. Erection of kiln seals, heat shields, fans, etc.

Erection and alignment of kiln bases and gearbox supports

Alignment of kiln bases

Gear box supports and self aligning yoke

Preassembly of kiln heavy sections

Mark up and weld on one side of retainers

Insert tyre, mark up and weld next side Align tyre to shell and weld on axial retainers All welding are to be inspected by UT and MT

Mounting of tangential suspension

Preparation of kiln bearings

Check with blue marking, and scrape if nesseary

Erection and alignment of bearings, rollers and thrust device

Erection and alignment of bearings and rollers

Erection and alignment of thrust device

Erection of kiln drive

Preassembly of kiln light sections and erection of kiln

Kiln seals, heat shields, fans, etc.