You are on page 1of 32

Programme Evaluation Review Technique (PERT)

PERT (Programme Evaluation Review Technique)


Pessimistic time estimate (tp) Considering that activity facing maximum possible problems & delays Optimistic time delay (to) Considering that activity does not encounter any problem Most likely time (tm) Considering that activity faces moderate delays as normally expected Average time for the activity to be used can be calculated as: T = (tp) + 4 x (tm) + (to) 6 Standard deviation () = (tp) (to) 6 Sift Marketing Pvt Ltd 2 Variance = square of standard deviation = ()2

Normal Distribution curve

Frequency
to
Sift Marketing Pvt Ltd

tp

tm
3

Time

Problem - 1
Activity Optimistic Most Likely time time 1-2 1-6 2-3 2-4 3-5 4-5 6-7 5-8 7-8 3 2 6 2 5 3 3 1 4 6 5 12 5 11 6 9 4 9 Pessimistic time 15 14 30 8 17 15 27 7 28 3. 1. Draw Network Diagram

2.

Find Project Duration


Calculate Standard deviation & variance

Sift Marketing Pvt Ltd

Problem 1 . . . contd
Activity Optimistic Most Likely Pessimistic time time time 1-2 1-6 2-3 2-4 3-5 4-5 6-7 5-8 7-8 3 2 6 2 5 3 3 1 4 6 5 12 5 11 6 9 4 9 15 14 30 8 17 15 27 7 28 Average time 7 6 14 5 11 7 11 4 11.33

Sift Marketing Pvt Ltd

Problem 1 . . . contd
Activity Optimistic Most Likely Pessimistic time time time 1-2 1-6 2-3 2-4 3-5 4-5 6-7 5-8 7-8 3 2 6 2 5 3 3 1 4 6 5 12 5 11 6 9 4 9 15 14 30 8 17 15 27 7 28 Average Standard time deviation 7 6 14 5 11 7 11 4 11.33 2 2 4 1 2 2 4 1 4

Sift Marketing Pvt Ltd

Problem 1 . . . contd
Activity Optimistic Most Likely Pessimistic time time time 1-2 1-6 2-3 2-4 3-5 4-5 6-7 5-8 7-8 3 2 6 2 5 3 3 1 4 6 5 12 5 11 6 9 4 9 15 14 30 8 17 15 27 7 28 Average Standard time deviation 7 6 14 5 11 7 11 4 11.33 2 2 4 1 2 2 4 1 4 Variance 4 4 16 1 4 4 16 1 16

Sift Marketing Pvt Ltd

Problem 1 . . . contd

14 5

11 7

1-2-3-5-8 = 7 + 14 + 11 + 4 = 36 1-2-4-5-8 = 7 + 5 + 7 + 4 = 23

11.33 7

1-6-7-8 = 6 + 11 + 11.33 = 28.33

11

Sift Marketing Pvt Ltd

Problem 1 . . . contd
Activity Optimistic Most Likely Pessimistic time time time 1-2 1-6 2-3 2-4 3-5 4-5 6-7 5-8 7-8 3 2 6 2 5 3 3 1 4 6 5 12 5 11 6 9 4 9 15 14 30 8 17 15 27 7 28 Average Standard time deviation 7 6 14 5 11 7 11 4 11.33 2 2 4 1 2 2 4 1 4 Variance 4 4 16 1 4 4 16 1 16

Sum of variances of critical activities = 4 + 16 + 4 + 1 = 25 Standard deviation = square root of sum of variances = 5
Sift Marketing Pvt Ltd

Problem 2 (Practice)
Activity Preceding Activity a b c

A
B C D E

A B

2
8 3 2 2

4
8 15 14 8

3
8 8 5 2

F
G H 1. 2. 3.
Sift Marketing Pvt Ltd

C
D,E F,G

1
1 6

5
3 14

3
2 10

Draw Network Diagram Find Project Duration Calculate Standard deviation & variance
10

Problem 2 (Practice) - Solution


Activity Preceding Activity A B C D A a = t-o 2 8 3 2 b = t-p 4 8 15 14 c = t-m 3 8 8 5 Average Time (T) 3 8 8.33 6 Standard Deviation 0.33 0 2 2 Variance 0.11 0 4 4

E
F G H

B
C D,E F,G

2
1 1 6

8
5 3 14

2
3 2 10

3
3 2 10

1
0.67 0.33 1.33

1
0.44 0.11 1.78

Sift Marketing Pvt Ltd

11

Problem 2 (Practice) - Solution


D 2 A 3 B E 3 6 5 1-2-5-6-7 = 3+6+2+10 = 21 1-3-5-6-7 = 8+3+2+10 = 23 1-4-6-10 = 8.33+3+10 = 21.22

1
8 C 8.33

F
4 3 6

H
7 10

Sift Marketing Pvt Ltd

12

Problem 2 (Practice) - Solution


Activit y A B C D E F G H Preceding Activity A B C D,E F,G a = t-o 2 8 3 2 2 1 1 6 b = t-p 4 8 15 14 8 5 3 14 c = t-m 3 8 8 5 2 3 2 10 Average Time (T) 3 8 8.33 6 3 3 2 10 Standard Deviation 0.33 0 2 2 1 0.67 0.33 1.33 Variance 0.11 0 4 4 1 0.44 0.11 1.78

Sum of variances of critical activities = 0 + 1 + 0.11 + 1.78 = 2.89 Standard deviation = square root of sum of variances = 1.70
Sift Marketing Pvt Ltd

13

Normal Distribution

x-
Z =
0.5 0.5

Z
0 0.5

Z
1

Sift Marketing Pvt Ltd

14

Problem - 3
Time in weeks
Activity 1-2 1-3 2-4 2-5 3-5 4-5 4-6 5-6 Pessimistic 21 27 8 3.5 10 1.7 9 5 Most likely 7.5 8 8 2 10 1 7.5 3 Optimistic 3 3 8 0.5 10 0.3 3 1

1. Draw the network diagram and identify the paths through it

2. What is the expected project completion time


3. What is the expected project completion time with a confidence of 90%

Sift Marketing Pvt Ltd

15

Problem 3 . . contd
Activity 1-2 1-3 2-4 2-5 3-5 4-5 4-6 5-6 Pessimistic 21 27 8 3.5 10 1.7 9 5 Most likely 7.5 8 8 2 10 1 7.5 3 Optimistic 3 3 8 0.5 10 0.3 3 1 Average 9 10.33 8 2 10 1 7.00 3 Std Deviation 3 4 0 0.5 0 0.23 1 0.67 Variance 9 16 0 0.25 0 0.05 1 0.44

Sift Marketing Pvt Ltd

16

Problem 3 . . contd
1. 2. Draw the network diagram and identify the paths through it What is the expected project completion time 1-2-4-6 = 9 + 8 + 7 = 24 2 8 9 7 2 3 10 5 4 1-2-4-5-6 = 9 + 8 + 1 + 3 = 21 1-2-5-6 = 9 + 2 + 3 = 14 6 3

1
10.33

1-3-5-6 = 10.33 + 10 + 3 = 23.33

Expected Project completion time = 24 weeks


Sift Marketing Pvt Ltd

17

Problem 3 . . contd
3. What is the expected project completion time with a confidence of 90%
Activity 1-2 Pessimistic 21 Most likely 7.5 Optimistic 3 Average 9 Std Deviation 3 Variance 9

1-3
2-4 2-5

27
8 3.5

8
8 2

3
8 0.5

10.33
8 2

4
0 0.5

16
0 0.25

3-5
4-5 4-6 5-6

10
1.7 9 5

10
1 7.5 3

10
0.3 3 1

10
1 7.00 3

0
0.23 1 0.67

0
0.05 1 0.44

Variance = 9 + 0 + 1 = 10
Z = (x - ) /

Std Deviation = 3.16

= 24, = 3.16, Find Z from table and calculate x


Sift Marketing Pvt Ltd

18

Problem 3 . . contd

x-
Z =
0.5 0.5

From table Z = 1.28 for P = 0.3997 Hence, 1.28 = (x - 24) / 3.16

Z
0 0.5 0.4 1

x = 28.05 weeks

With a confidence of 90% expected project completion time = 28.05 weeks

Sift Marketing Pvt Ltd

19

Problem 4 (Practice)
Data: = 25 days, = 1 What is the expected project completion time with confidence of 88% x-
Z =
0.5 0.5

From table Z = 1.17 for P = 0.3790 Hence, 1.17 = (x - 25) / 1

Z
0 0.5 0.38 1

x = 26.17 days

With a confidence of 88% expected project completion time = 26.17 days


Sift Marketing Pvt Ltd

20

Problem - 5
Time in weeks
Activity A Preceding activity a 1 b 3 c 5

B
C D

A A

2
3 5

4
6 6

6
15 7

E
F G

C
D B

5
6 7

7
8 9

9
10 11

E, F,G

1. Draw the network diagram and identify the paths through it 2. What is the expected project completion time 3. Find the probability of completing the project no more than 4 weeks later than expected
Sift Marketing Pvt Ltd

21

Problem 5 . . contd
Time in weeks
Activity A B C D E F G H Preceding activity A A C D B E, F,G a 1 2 3 5 5 6 7 2 b 3 4 6 6 7 8 9 3 c 5 6 15 7 9 10 11 4 T 3 4 7 6 7 8 9 3 0.67 0.67 2 0.33 0.67 0.67 0.67 0.33 Variance 0.44 0.44 4 0.11 0.44 0.44 0.44 0.11

Sift Marketing Pvt Ltd

22

Problem 5 . . contd
1. 2. Draw the network diagram and identify the paths through it What is the expected project completion time C 7 6 D 5 B 4 3 G 9 8 6 H 3 7 F E 7

2 A 3

1-2-4-6-7 = 3 + 7 + 7 + 3 = 20 1-2-5-6-7 = 3 + 6 + 8 + 3 = 20 1-3-6-7 = 4 + 9 + 3 = 16

Expected project completion time = 20 weeks


Sift Marketing Pvt Ltd

23

Problem 5 . . contd
3. Find the probability of completing the project no more than 4 weeks later than expected
Activity
A B

Preceding activity
-

a
1 2

b
3 4

c
5 6

T
3 4

0.67 0.67

Variance
0.44 0.44

C
D E

A
A C

3
5 5

6
6 7

15
7 9

7
6 7

2
0.33 0.67

4
0.11 0.44

F
G H

D
B E, F,G

6
7 2

8
9 3

10
11 4

8
9 3

0.67
0.67 0.33

0.44
0.44 0.11

Variance 1 = 0.44+4+0.44+0.11 = 4.99 ()1 = 2.23


Sift Marketing Pvt Ltd

Variance 2 = 0.44+0.11+0.44+0.11 = 1.11 ()2 = 1.053 ()2 = 20


24

()1 = 20

Problem 5 . . contd
x - 1
Z1 =

1
Z1 = (24 20) / 2.23 Z1 = 1.785

0.5

0.5

Hence

Z1 From Table for Z = 1.78 = 0.4625


0 20 x =24

So, probability of completing the project in not more than 4 weeks later than expected duration = 0.5 + 0.4625 = 0.9625 = 96.25%
Sift Marketing Pvt Ltd

25

Problem 5 . . contd
x - 2
Z2 =

2
Z2 = (24 20) / 1.053 Z2 = 3.80

0.5

0.5

Hence

Z2 From Table for Z = 3.80 = 0.4999


0 20 24

So, probability of completing the project in not more than 4 weeks later than expected duration = 0.5 + 0.4999 = 0.9999 = 99.99%
Sift Marketing Pvt Ltd

26

Problem - 6
Data: Expected project duration = 36 days Standard deviation = 5 Find: a) The probability that project will take more than 41 days b) The probability that project will be completed in 31 days or less time

Sift Marketing Pvt Ltd

27

Problem 6 . . contd
a) The probability that project will take more than 41 days x-
Z = Hence
0.5 0.5

Z = (41 36) / 5 Z=1

Z
0 36 41 1

From Table for Z = 1 = 0.3413

Probability that project will take more than 41 days = 0.5 0.3413 = 0.1587 = 15.87%
Sift Marketing Pvt Ltd

28

Problem 6 . . contd
b) The probability that project will be completed in 31 days or less time x-
Z =

Hence
0.5 0.5

Z = (31 36) / 5 Z=-1

Z
0 31 36 1

From Table for Z = 1 = 0.3413

Probability that project will take more than 31 days = 0.5 0.3413 = 0.1587 = 15.87%
Sift Marketing Pvt Ltd

29

Problem - 7
If in a PERT network the expected duration of critical path is 36 months and sum of variances of the activities on the 2 then what is the probability critical path is 25 (months) 2 that the project will be completed not earlier than 30 months and not later than 42 months

= 36 months
Variance = 25 = 5

Sift Marketing Pvt Ltd

30

Problem - 7 . . contd
Probability that project will be completed not earlier than 30 months x-
Z =

Hence
0.5 0.5

Z = (30 36) / 5 Z = - 1.2

Z
0 30 36 1

From Table for Z = 1.2 = 0.3849

Sift Marketing Pvt Ltd

31

Problem - 7 . . contd
Probability that project will take not more than 42 months x-
Z = Hence
0.5 0.5

Z = (42 36) / 5 Z = 1.2

Z
0 36 42 1

From Table for Z = 1.2 = 0.3849

Probability that project will take not less than 30 months and not more than 42 months = 0.3849 + 0.3849 = 0.7698 = 76.98 %
Sift Marketing Pvt Ltd

32

You might also like