Professional Documents
Culture Documents
Receipt at site
After Receipt at site and before unloading the materials ,the conditions of packing and record of the transportation shall be jointly assessed by owner and contractor and dully recorded.
Storage at site
Storage instructions should be followed strictly as per storage instructions in equipment manual. While shifting materials from storage place to final place for erection, sufficient care is to be taken to avoid damage to the materials. The material shall be opened after reaching the place of erection . In case the material is found damaged during storage and shifting. Inform supplier, erection contractor and Insurance agency.
Storage at site
LA should be stored vertically. CVT should be stored vertically. CT should be stored vertically or if it is horizantal, keep around 30 degree height at top side. WT should be stored vertically. Store all equipments above ground level by making platforms.
ERECTION OF EQUIPMENTS
1. MEASURE FOUNDATION BOLTS DISTANCE &
LEVELING. 2. CHECK THE BASE PLATE HEIGHT WITH EXISTING EQUIPMENT BASE PLATE. 3. CHECK THE LEVELING OF STRUCTURE AT TOP WITH SPIRIT LEVEL AND TIGHT ALL NUTS & BOLTS. 4. ERECT EQUIPMENT PREFERABLY WITH CRANE AS PER MANUFACTURER RECOMMENDATIONS.
ERECTION OF EQUIPMENTS
5. ERECT THE CT PRIMARY POINTS P1 &
P2 AS PER DRAWING. 6. ERECT LAS BY KEEPING VENTS DIRECTION AWAY FROM EQUIPMENTS. 7. ERECT ISOLATOR EARTH SWITCH POSITION AS PER DRAWING.
PRE COMMISSIONING TESTS OF CVT 1.POLARITY TEST. 2. RATIO TEST. 4. IR MEASUREMENT. 5. TANDELTA & CAPACITANCE MEASUREMENT
PRE COMMISSIONING TESTS OF SA 1. THIRD HORMONIC RESISTIVE CURRENT. 2. IR MEASUREMENT OF INDIVIDUAL STACK. 3. OPERATION OF LA COUNTER. 4. TANDELTA & CAPACITANCE MEASUREMENT
PRE COMMISSIONING TESTS OF ISOLATOR 1. MILLIVOLT DROP TEST. 2. IR MEASUREMENT . 3. 50 OPERATIONS TEST.
CONSTRUCTION FEATURES. Circuit Breaker is an on load Switch which can make & break load currents and fault Currents in shortest time.
What it requires ? 1.Support Structure. 2. Operating Drive Assembly. 3.Pole Column. 4.Interrupter. 5.Control Cubicle.
SUPPORT STRUCTURE
Lattice structure or Tripod. It carries the operating drive assembly,pole column and Interrupter . It will stand on the concrete foundations.
POLE COLUMN
It consists
Stacks of support porcelain Insulators to insulate the live parts from the ground. Operating rod(Insulating rod) with guiding rings transmits movement from driving assembly to moving contacts. SF6 gas . Shaft seal assembly seals the SF6 gas.
INTERRUPTER ASSEMBLY
Closing resistor assembly(optional)-400 ohms. Grading capacitors(oil filled) -1200 PF .
TESTS
Pre-commissioning Tests.
PRE-COMMISSIONING TESTS
Pressure Switch settings of SF6 gas&Air/Oil. Air/Oil Pressure drop tests during operation. Air/Oil&SF6 gas Leakage tests in 24hrs. Pole Discrepancy test for open/close. Dew point & Air content tests for SF6 gas. Milli volt drop test in close position. Capacitance&Tan delta test for Grading Capacitor. Operation timings test. Insulation Resistance measurement tests.
OPERATION TIMINGS
Close timings including PIR. Trip 1 timings . Trip 2 timings. Close Trip for both Trip 1 &2. Duty cycle operation times(O-0.3s-CO). Pole discrepancy time during open&close.
3.33Ms 2.5Ms
3.33Ms 2.5Ms
PIR TIME
BHEL make CGL make ABB make NGEF make M&G make TELK make ABB make(HVDC) 12-16ms 8-12ms 8-10ms 8-12ms 8-12ms 8-12ms 8-12ms
5ms(min)
AT RATED PRESSURE
PIR and main contacts overlap time (BHEL,M&G,ABB imported)make CBx). TAN DELTA of grading capacitors Capacitance of grading capacitors Contact resistance of CB Contact resistance of CB terminal Connector
5ms(min)
AT RATED PRESSURE
0.007degrees at 20deg.cel. within +10 of the rated value within 5 150 micro-ohm 10micro-ohm per connector
100m-ohm(min) by 5.0/10.0kvMEGGER
Remarks
During commissioning During O&M Critical During commissioning During O&M During commissioning During O&M During commissioning During O&M During commissioning During O&M Critical
M&G CGL ABB NGEF -15deg.cel. -10deg.cel. -15deg.cel -5deg.cel -15deg.cel -7deg.cel. -5deg.cel
THE END