Professional Documents
Culture Documents
Introduction
This presentation was developed as a teaching aid with the support of the American Institute of Steel Construction. It is primarily intended to be used by Construction Management programs to supplement classes in Construction Methods and Construction Equipment but also provides examples applicable to Estimating, Soils, Statics and Structures. The presentation materials would also be applicable in Architecture and Civil Engineering programs. You will need to enable Macros in PowerPoint to use these functions. Because viruses are sometimes transmitted through Macros, the default security setting for PowerPoint is usually High. This must be changed to Medium before opening the presentation. The security setting can be changed by first closing the presentation. In PowerPoint select Tools|Macro|Security Select Medium. Reopen this presentation and select Enable Macros when prompted by the Security Warning. See the Slide Notes for additional information
2
Crane Types
Rough Terrain
Truck Mounted
All Terrain
Tower
See also [1], 53-66, 78-81
Crawler Lattice
Types of Cranes
Rough Terrain
Designed for unimproved work sites Roadable for short distances Four steering modes Pick and carry capability Three position outriggers
5
Truck Mounted
Can be driven at highway speeds Limited off-road capability Can do multiple jobs in one day Hydraulic booms allow fast setup but the weight (compared to lattice) reduces lifting capability
All Terrain
Combines features of Rough Terrain and Truck Mounted cranes Off-road capable All-wheel steering Highway speeds
Crawler Lattice
High-capacity, longreach lifts Pick and carry operations Multiple attachments provide great flexibility in boom configuration
Tower
Used when space is at a premium Up and over reach Moving counterweight balances load Fixed foundation or Crawler w/attachment
Crane Selection
Selection criteria Crane data sheet examples
Rough Terrain - Grove RT700E Crawler Lattice - Manitowoc Model 777
10
11
Available Space
Can crane fit on jobsite? Can crane maneuver as required on jobsite? Can the boom configuration reach all required placement positions? Can boom avoid existing obstacles while performing required movements?
12
INFO
Available Space
Clicking on the category button will briefly describe the crane's capabilities.
Tower
Hydraulic
Crawler
13
Working Range
Working range diagram shows the cranes reach Load capacity will be significantly reduced at long radii Diagram also shows range of boom angles and attachment geometry
14
INFO LOAD
Load Charts
NOTES: 4. Capacities appearing above the bold line are based on structural strength and tipping should not be relied upon as a capacity limitation.
Load charts provide the authoritative load capacity for all crane configurations at all ranges Load Chart NOTES must be followed 4. Weight of the block, rigging equipment and cable below the boom must be subtracted from load capacity to determine actual payload
15
Crane Availability
As with most types of construction equipment, the theoretically optimal crane for the job based on capability may not be readily available, or a more capable crane that is owned by the steel erector may be more economical Availability will always be an important factor in crane selection
16
Number of Lifts
Fixed costs for crane mobilization will be more significant for smaller jobs requiring fewer days on site A crane that can perform all lifts from a small number of positions (or a single position) on the job site may be highly desirable even if mobilization and operating cost are higher
17
18
19
20
21
RT700E Weights
Crane weight is critical when hauling The counterweight may have to be removed and transported on a separate vehicle
22
INFO
Fixed
Counterweight
Bi-Fold
Steering
Insert s
Gradeability
23
24
LOAD
110 ft.
Rotation
Fixed Swingaway
360 deg
20 ft.
Length 56 ft.
Offset 25
LOAD
35 40 45 50 55 60 65 70
9,360 (78) 9,360 (77) 8,480 (75.5) 7,680 (73.5) 6,990 (71.5) 6,190 (70) 5,890 (68) 5,390 (66)
7,480 (78) 7,070 (77.5) 6,470 (76) 5,970 (74) 5,570 (72) 5,070 (70)
5,880 (78) 5,880 (77.5) 5,480 (76.5) 5,080 (74.5) 4,780 (72.5)
6,300 (78) 6,300 (7.5) 6,000 (76.5) 5,990 (75) 5,980 (73.5) 5,510 (72) 5,010 (70)
NOTES: Radii listed are for a fully extended boom with the boom extension erected. For main boom lengths less than fully extended, the rated loads are determined by boom angle. Use only the column which corresponds to the boom extension length and offset for which the machine is configured. For boom angles not shown, use the rating of the next lower boom angle.
4,840 (78) 4,840 (77.5) 4,440 (76.5) Tipping Structure Governs Governs
26
Displays the load chart for the configuration selected on the previous slide.
LOAD
Boom Insert FS Length FS Offset Outriggers Capacity Rigging Max. Load to Lift
110 ft. 20 ft. 56 ft. 25 50% 2880 pounds 1000 pounds 1880 pounds
27
INFO
Selected Specifications
Boom No. 134 Fixed Jib
Optional: No. 134 basic fixed jib 30' length consisting of 15' jib butt and 15' jib top with 12' jib strut, pendants and backstay.
Fixed Jib
Luffing Jib
Counterweight
29
30
31
32
LOAD
70 ft. Rotation
360 deg
33
LOAD
Luffing Jib
Main Boom Length in Feet
Displays the load chart for the configuration selected on the previous slide.
34
35
Check load capacity at each range identify critical lifts Insure that crane can reach each location with previously placed members in place Consider multiple lift rigging
36
Crane Positions
Level, solid foundation
Provided by controlling contractor, as required by OSHA
Adequate set back from slopes Consider addition of surcharge load to earth pressure on walls Protection of underground utilities/ structures Interference with other construction operations
37
38
40
41
42
43
90-8
Weight of 33-6 W12X45 with attachments is determined from detailers calculations (~1700 lbs) A 19 ton capacity weight ball and wire rope for hoisting weigh 1000 lbs. The crane load chart must be checked to insure that is has adequate capacity for the total load of 2700 lbs The Manitowoc Model 222 with 160 Boom and 40 Jib at 0 Offset can lift 4400 lbs at 150 foot radius The erection sequence must be checked to insure that the crane boom wont strike other members
45
Select a crane location Some details from the actual building were simplified in the model
46
LOAD
Crane Model
Manitowoc Model 777 w/190ft Boom
139 42
Locate Crane
Group
Fourth Floor
X Y
130 -30
47
Cycle Time
C F V F Rt where C Hoisting Cost F Fixed Cost V Variable Cost R Hourly ( Daily) Cost Rate t Hoisting Time ( Hours, Days)
51
Case Study
Consider two options for erecting the Four Story Office Building
A large crawler lattice crane positioned in one location A medium crawler lattice crane placed at two positions A smaller rough terrain crane that must be repositioned several times
52
LOAD
Case
Model 222
Hoist Abort
Radius Boom Angle Swing Angle Max. Lift Load Rigging Weight Net Capacity Approx. Weight Percent of Capacity
53
LOAD
Sequence Number 1
Mobilize Crane
$ 3000
Position Crane
1.0 Hr
Unload Trucks
2.3 Hr
Place Members
16.5 Hr
Demobilize Crane
$ 2000
Hourly Rate
529.00 $68,100
Calculate
Total Cost
Hourly Rate Crane 300.00 Operator 50.00 Oiler 0.00 Foreman 39.00 54 Iron Workers (x4) 35.00
Jobsite Methods/Management
Safety Rigging Crew coordination Crane foundation issues
55
Safety
OSHA requirements for steel erection are covered in Subpart R of Safety and Health Regulations for Construction Two sections are critical for planning crane operations
1926.752 Site layout, site-specific erection plans and construction sequence
OSHA Steel Erection eTool Site Preparation.htm
Accidents
Crane failures can be classified as structural or tipping Tipping can be caused by overload, inadequate foundation, or wind loading Structural failure may be due to overload or lateral load Operator error can cause either failure mode Operations near power lines present additional safety hazards
57
Rigging
Columns Beams Multiple Lift Rigging Statics of rigging
58
Column Rigging
This column is rigged using a device that allows the iron workers to release the rigging from the ground by pulling on the rope
59
Beam Rigging
Beams are usually lifted using a choker wrapped around the beam at the center of gravity Beams may also be hoisted with two cables
60
Statics of Rigging
Lifting a beam or column using a single cable is simply a problem of selecting a cable that can support the weight and attaching it at the center Some situations will require the rigger to calculate
Center of gravity Load in skewed cables Variable sling lengths Spreader bar design
62
LOAD
Statics of Rigging
1500 lbs
11'
14.21'
/\ \/
Spreader Compression 675.0 lbs.
+ C.G.
< >
Crew Coordination
Typical erection crew
Crane operator Oiler (not required on hydraulic cranes) Foreman Four ironworkers 2 ground, 2 connectors
Order of assembly is determined in advance Crane operator may be guided by hand signals or two-way radios when visibility is inadequate
64
LOAD
Crawler 130 Boom Length (ft.) Radius (ft.) Swing Angle Load (kips)
Calculate
0.00
25.77
0.00
Firm
25.77
12 ksf
66
1 1 1.5 Preferred
In 1 good soil
68
1 1.5 Preferred
69
Summary
Proper crane selection and application is essential for a safe and economically competitive steel erection plan The crane must be placed on stable foundations and have adequate range and lift capacity to make the required placements
70
References
[1] AISC (2005) Jobsite Layout, Mobilization, Equipment and Coordination, American Institute of Steel Construction, Inc.. Chicago, IL. [2] AISC (2003) Structural Steel Construction Process - Technical, American Institute of Steel Construction, Inc.. Chicago, IL. [3] AISC (1999) Construction Management of Steel Construction, American Institute of Steel Construction, Inc., Chicago, IL. [4] Shapiro, H.I., J.P. Shapiro and L.K. Shapiro (2000) Cranes and Derricks, McGraw Hill Companies, Inc., New York.
71