Professional Documents
Culture Documents
Construction Management
Dr. Samia Ali
Company
LOGO
www.themegallery.com
Planning
Definition: It is the area that concerned with the various methods of arranging and employing materials, equipments, labours, money, and subcontractors to carry out the day-to-day operations of the project. .
COMPANY LOGO
www.themegallery.com
c
r
COMPANY LOGO
www.themegallery.com
PLANNING TECHNIQUES
Bar Chart Network Techniques. * PERT, Program Evaluation & Review Technique. * CPM, Critical Path Method Technique. Resource Oriented Techniques. * LOB, Line Of Balance Technique. * Time-Location Technique.
COMPANY LOGO
www.themegallery.com
BAR CHART
During world war I, Mr. Gantt. Most directly and understood method for project planning. Limitations: dependencies not clear. Detailed activity not enough.
COMPANY LOGO
www.themegallery.com
BAR CHART
# 1 Foundations 2 Underground 3 services Rough 4 mechanical & Structural steel 5 Exterior walls 6 Roof 7 8 9 1St floor slab 2nd floor slab Operation Demolition Quantity duration Amt. Unit 8 14 6 12 5 12 6 4 6 12 10 8 -13.76 --50 371.6 464.5 76.46 95.57 -325.2 1208 -m3 --ton m2 m2 m3 m3 -m2 m2 3/30 4/6 4/13 4/20 4/27 Week Ending 5/4 5/11 5/18 5/25 6/1 8/6 6/15
Holiday
5/1
Time Now
COMPANY LOGO
www.themegallery.com
BAR CHART
Easy to understand, most widely used. List of activities, start, duration, and finish plotted in a time scale. Level of detail & time scale chosen to suit the users purpose. Good communication method between engineer and foreman.
% completion Activity# 1 2 3 Actual 100 67 40
Dr. Samia Ali
Programmed 100 95 95
COMPANY LOGO
www.themegallery.com
Network techniques
Both were developed independently in parallel CPM critical path method
www.themegallery.com
THE CPM
A TIME MANAGEMENT TOOL THAT:
1- Overcome the difficult time control task. 2- Enable managers to handle large number of activities and complicated relationships in a simple and understandable way. 3- Applies well to all construction work. 4- Based on graphical network model.
COMPANY LOGO
www.themegallery.com
THE CPM
NETWORK :
1-Presents in diagrammatic form all the job activities and their mutual time dependencies.
2- A simple and effective medium for communication complex job inter-dependencies. 3- Serves as a basis for calculation of work schedules.
COMPANY LOGO
www.themegallery.com
THE CPM
A THREE PHASE PROCEDURE :
COMPANY LOGO
www.themegallery.com
THE CPM
ADVANTAGES: 1- shows relationships. 2- more effective planning. 3- pinpoints problem areas. 4- improves communications. 5- resource allocation. 6- study of alternate courses of action. 7- management by exception identifying the critical operations, and permits true MBE.
COMPANY LOGO
www.themegallery.com
THE CPM
Limitations : 1- Not a substitute for thinking or planning. 2- Project manager and his staff must be a part of the planning process. 3- Should not be confined to the preliminary planning stages of the project. 4- It furnishes only information.
COMPANY LOGO
www.themegallery.com
COMPANY LOGO
www.themegallery.com
COMPANY LOGO
www.themegallery.com
Project documents
Activity list Basic resource managing Network diagram Duration & resource estimate Basic critical path calculations Time-cost adjustment
Time-resource adjustment
Schedule plan for implementation
Is current plan ok
update Project complete
COMPANY LOGO
Field reports
www.themegallery.com
Requires: 1- Intimate knowledge of construction method. 2- Ability to visualize discrete work elements. 3- Establish activities mutual inter-independencies. 4- done by experienced people familiar with the type of field work involved. 5- participation of responsible field implementation personal. Consists of three steps: Activity 1- determine job steps activities Logic 2- define activities sequential relationship. Network 3- present planning information on a network diagram
COMPANY LOGO
www.themegallery.com
Activity : a single work step that has a recognizable beginning and end and requires time for its accomplishment. Project subdivision :
1. 2. 3. 4. Area of responsibility general or subcontractor Category of work labour, equipments, materials Structural elements footing, walls, beams Purpose owners bidding, payments , contractors cost accounting & estimate
Level of details : depends upon: - Who will use the network? - What are the users interests ? - Manag. Span of control.
COMPANY LOGO
www.themegallery.com
Be prepared for the task Should have open mind with regard to construction methods. NO arbitrary imposed restrictions on activities. The planner must not only ask the field personnel HOW? They plan to do the job, but must be able to raise questions ask WHY? Things should be done they way proposed. Assume unlimited resources. Restrictions of time and space are not a proper consideration when constructing the initial network.
Dr. Samia Ali COMPANY LOGO
www.themegallery.com
From reviewing plans and specifications. Job logic : - The determined order in which the activities are to be accomplished in the field . - Showing job activities logic produces the net work. - Evolves naturally as the job is discussed and the network diagram progresses. - For every activity in the activity list ask, what does this activity depends upon?
COMPANY LOGO
www.themegallery.com
COMPANY LOGO
www.themegallery.com
LOGIC BATTERNS
The identity of the activity and a considerable amount of other information pertaining are entered into its rectangular box.
20 60
A
20
B
30
a) Independent relationships
b) Dependent relationships
www.themegallery.com
LOGIC PATTERNS
20
A
22
30
40
B
20 30
E
40
c) Merging relationships
C
42
d) Bursting relationships
E
20 30
40
C
Redundant link to be removed
Dr. Samia Ali COMPANY LOGO
www.themegallery.com
LOGIC PATTERNS
A B C A
start
F E
Finish
www.themegallery.com
10
25
A
5
start
E
35
Finish
15
B
20 30
COMPANY LOGO
www.themegallery.com
COMPANY LOGO
www.themegallery.com
COMPANY LOGO
www.themegallery.com
1 2 16 2
Contract award
18
11
2
4 10 2 4 17 2 3 4 5 3
8
9 6 7 3 10 5 8 5
14 2
12 9
19 7
15 2
13 9
COMPANY LOGO
www.themegallery.com
Precedence diagram 1 2
10 14 15 15 20 5
Contract award
10
60 10 40 7 45 50 2 70 9 75 19
85
90 12
1 25 16 30 17 35 18
5
55 3
65
8
80
11 95 13
100 4
COMPANY LOGO
www.themegallery.com
COMPANY LOGO