Professional Documents
Culture Documents
Master Scheduling I
Controls the timing and quantity of production for products or product families Primary interface point for actual customer orders Coordinates forecasted demand and actual orders with production activity Serves as tool for agreement between marketing and operations (but at a different level than SOP)
3
Master Scheduling II
Feeds more detailed material planning Indicates the quantity and timing (i.e., delivery times) for a product or group of products More detailed than SOP
SOP
1 25 12
2 25 35
3 25 13
4 25 40
MPS
5
EIt = Ending Inventory for period t (same as projected on-hand inventory for next period)
Ft = Forecasted demand for period t MPSt = MPS quantity available in period t OBt = orders booked for period t
MPS Formulas:
EI t EI t 1 MPSt max( Ft ,OBt ) ATPt EI t 1 MPSt OBi
i t z 1
Notes: Planning time fence cumulative lead time for product What seems to be the lot-sizing rule here?
8
Orders Booked
Projected On-Hand Inventory
170
230
165
65
140
215
120
65
85
190
45
65
20
190
0
65
Master Schedule
300
300
250
250
i.e. Projected on-hand inventory for week 47: = 65 + 300 150 = 215
Available-to-Promise
On-hand inventory at end of October = Month Week Forecast Demand 45 150 November 46 150 47 150 48 150 49 125 100 December 50 125 51 125 52 125
Orders Booked
Projected On-Hand Inventory Master schedule Available-to-Promise
170
230 300 65
165
65 0
140
215 300 40
120
65 0
85
190 250 120 70
45
65 0
20
190 250 230
0
65 0
ATP(45) = 100 + 300 (170 + 165) = 65 ATP(47) = 300 (140+120) = 40 ATP(49) = 250 (85 + 45) = 120
10
Orders Booked
Projected On-Hand Inventory Master schedule Available-to-Promise
170
230 300 65
165
65 0
140
215 300 40
120
65 0
85
165 250 120
45
15 0
20
115 250 230
0
(35) 0
Orders Booked
Projected On-Hand Inventory Master schedule Available-to-Promise
170
230 300 0
230
0 0
140
150 300 40
120
0 0
85
125 250 120
45
0 0
20
125 250 230
0
0 0
12
13
MPS
Considerations of MRP
15
Assume that weve scheduled 500 chairs to be ready five weeks from now.
. . . Now what?
16
Seat
Leg Assembly
Seat
Back Assembly
Legs (2)
Cross bar
Cross bar
Graphic Lead-Time
Week 1 Week 2 Week 3 Week 4 Week 5
Back Support (2 weeks) Side Rails (2 weeks) Cross Bar (2 weeks) Back Assembly (1 week) Seats (2 weeks)
Leg Assembly (1 week)
19
Legs (2 weeks)
Cross Bar (2 weeks)
6 400 400
7 400 0
22
Seat
LT = 2 weeks Minimum Order = 1 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 0 0 2 0 0 5 400 0 400 400 6 400 0 400 400 7 0 0
500
400
Where do the gross requirements come from? Do you understand the MRP logic?
23
Chairs
LT = 1 week MPS Due Date Start Assembly 1 0 0 2 0 0 3 0 0 Week 4 0 500 Week 4 500 0 500 500 400 5 500 400 6 400 400 7 400 0
Seat
LT = 2 weeks Minimum Order = 1 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 0 0 2 0 0 3 0 0 5 400 0 400 400 6 400 0 400 400 7 0 0
Going Deeper
500
400
Leg Assembly
LT = 1 week Minimum Order = 1000 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 25 2 0 Week 3 4 0 500 5 400 125 6 400 725 275 1000 7 0 725
25 0
25 0
25 0
1000
Back Assembly
LT = 1 week Minimum Order = 250 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 0 0 2 0 250 250 5 400 100 400 500 500 6 400 200 300 500 7 0 200
250
25 0 25 0 25 0
1000
1000
Legs
LT = 2 weeks Minimum Order = 1 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 0 0 Week 2 3 4 5 0 2000 0 2000 0 0 2000 2000 2000 0 0 2000 2000 6 0 0 7 0 0
2000
25 0
25 0
25 0
1000
Back Assembly
LT = 1 week Minimum Order = 250 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 0 0 2 0 250 250 3 0 0 5 400 100 400 500 500 6 400 200 300 500 7 0 200
250
Crossbars
LT = 2 weeks Minimum Order = 1 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 0 0 2 3 0 1250 0 1250 1250 500 1500 0 Week 4 5 500 1500 0 0 500 1500 500 1500 6 0 0 7 0 0
Note effect of differences in lead times and order sizes on the gross requirements for each component
1250
26
We cannot do this since the planned order would be in the past. Thus the 250 crossbars will be delivered late one week to back assembly. What does this do to our chair schedule?
LT = 1 week Minimum Order = 1000 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order
1 0 25
2 0
3 0
5 400 125
7 0 725
25 0
25 0
25 0
1000
Back Assembly
LT = 2 weeks Minimum Order = 250 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 0 0 2 0 250 250 3 0 0 5 400 100 400 500 6 400 200 300 500 7 0 200
250
500
Crossbars
LT = 2 weeks Minimum Order = 1 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 0 0 2 3 250 1500 0 0 250 1500 250 1500 500 1000 Week 4 5 500 1000 0 0 500 1500 500 1500 6 0 0 7 0 0
250 1500
27
28
Other Considerations I
MRP
Feedback Planned Orders Feedback
Production
Suppliers
29
Other Considerations II
When do we update the system?
Capacity requirements planning using MRP output Pegging Lot sizing issues
30
Recall ...
Leg Assembly
LT = 1 week Minimum Order = 1000 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 25 2 0 Week 3 4 0 500 5 400 125 6 400 725 275 1000 7 0 725
250
250
250
1000
1000
Legs
LT = 2 weeks Minimum Order = 1 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 0 0 Week 2 3 4 5 0 2000 0 2000 0 0 2000 2000 2000 0 0 2000 2000 6 0 0 7 0 0
2000
If we order lot-for-lot
Leg Assembly
LT = 1 week Minimum Order = 1 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 25 0 25 2 0 Week 3 4 0 500 5 400 0 400 400 400 6 400 0 400 400 7 0 0
250
250
475
Legs
LT = 2 weeks Minimum Order = 1 Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Order 1 0 0 0 2 0 0 Week 3 4 950 800 0 950 950 800 0 800 800 5 800 0 800 800 6 0 0 7 0 0
950
800
DRP Example I
Wholesaler A
ROP = 50, Q = 200 Forecast Demand Ending Inventory Expected Order Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 20 20 20 20 20 20 20 20 85 65 45 225 205 185 165 145 125 200
Suppose we forecast demand for Wholesaler A for the next 8 days (the best time horizon to use will depend on many factors) Based on this, we anticipate that Wholesaler A will order on Day 3
34
DRP Example II
Wholesaler A
ROP = 50, Q = 200 Forecast Demand Ending Inventory Expected Order Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 20 20 20 20 20 20 20 20 85 65 45 225 205 185 165 145 125 200
Wholesaler B
ROP = 75, Q = 200 Forecast Demand Ending Inventory Expected Order Total Orders Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 14 14 14 14 14 14 14 14 108 94 80 66 252 238 224 210 196 200 200 200
We extend the analysis to include Wholesaler B Combined, we expect to see orders on Days 3 and 4
35
Wholesaler B
ROP = 75, Q = 200 Forecast Demand Ending Inventory Expected Order Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 14 14 14 14 14 14 14 14 108 94 80 66 252 238 224 210 196 200
Distributor
Q = 400 Total Expected Orders Ending Inventory Planned Receipts Planned Orders Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 200 200 50 50 50 250 50 50 50 50 50 400 400
The distributor then uses this information to plan its own orders. In this case, suppose it takes two days for the supplier to replenish; based on the information, the distributor would order on Day 1
36
DRP Benefits
Helps improve customer service Provides a better and faster understanding of the impact of shortages and/or promotions Helps reduce costs
Inventory Freight Production
DRP Constraints
Accurate forecasts and inventory levels Consistent and reliable lead times Nervousness
Necessary to anticipate correctly when orders will be placed
To ensure that orders can be placed and arrive by the time they are needed Even slight changes in demand for downstream partners can have a significant impact on order volumes, especially when order sizes are relatively high
38