Project System

Module (PS) SAP Project System Module

Projects System Module


Basics

1
Project System Project
Identification
Module (PS)

WHAT IS A PROJECT ?
 Projects are tasks with special characteristics.
 They are generally complex, unique, & involve high degree of risk.
 They have precise goals which are agreed as per Contract.
 They are limited in duration and are cost and capacity intensive.
 They are subject to definite set of quality requirements.
 They are mostly of strategic importance for Client executing them.

PROJECTS IN MCGM PERSPECTIVE


 Construction Works (Buildings / Bridges / Drainage System, etc).
 One time Repair works.
 Construction of Trenches.
 Treatment of Ward level & Departmental Projects is different in
MCGM SAP Process.

2
Project System
Module (PS) Dept. Level Projects

DEPARTMENTAL PROJECT
Project Criteria
 BOQ
 MEASUREMENT BOOK
 RUNNING BILLS
 VALUE DURING PROJECT IS ACCOUNTED AS CWIP
(CAPITAL WORK IN PROGRESS)

3
Project System
Module (PS) Ward & Hospital Projects

 WARD 
 NORMALLY ONLY CWC CONTRACTS
 TRENCHING WO

 HOSPITALS 
 CWC CONTRACTS
 LARGE SUPPLY
 INSTALLATION PROJECTS

EXCEPTIONS
PURE PROCUREMENT OF STOCK OR ASSET
---------
PURE MAINTENANCE WORK OR AMC (HIRING
OF VEHICLES, REPAIR OF AC’s)
SMALL REPAIR WORKS & PATTY WORKS OF
HOSPITAL
4
Project System
Module (PS) Project System Process
Project Structuring

Block Estimate

Detail Estimate

Project Budgeting

Work Order Process

Executed work details

Service Entry sheet

Payment Certification

Payment Processing

Period-End Process

Notification Process
5
Project System
Module (PS) Project Structuring

 IDENTIFICATION OF PROJECT

CREATION OF PROJECT
 IDENTIFICATION OF PROJECT DEFN.
 (THE NEXT AVAILABLE NO.)
 PROJECT DESCRIPTION
 TYPE OF PROJECT
 CAPITAL PROJECT
 MAINTENANCE PROJECT
 BUSINESS AREA
 START DATE
 LONG TEXT

6
Project System
Module (PS) Project Coding
 PROJECT NUMBERING
 THE 1ST ## 3 LETTERS IDENTIFIES THE RESPECTIVE DEPT.S AND
WARDS.
 THE NEXT ## 2 LETTERS ARE FOR THE SPECIFIC FISCAL YEARS
 THE LAST ## 3 LETTERS ARE THE SERIAL NUMBER OF THE PROJECT

 BUSINESS AREA
 BUSINESS AREA SHOULD BE 2001, 2002, 2003, 1000, 5000
 IF BUSINESS AREA IS CUTTING ACROSS DIFFERENT ZONES ---1000
 IF OUTSIDE CITY LIMIT-----------------------------------------------------------5000
 FOR WARD LEVEL THERE ARE RESPECTIVE BUSINESS AREAS

7
Project System
Module (PS) Project Coding Mask

8
Project System
Module (PS) Project coding

9
Project System
Module (PS) Project Builder

10
Project System
Module (PS) Project Creation

Nomenclature Project Description

11
Project System
Module (PS) Proposed Project Definition

Next Available No. in Series

12
Project System
Module (PS) Project Profile

13
Project System
Module (PS) Basic Data for Project

14
Project System
Module (PS) Project Creation….
 Project Structuring : WBS Elements

The project is structured with multiple wbs elements


at 2nd Level if :
 If the value of the project is more than Rs. 100 Cr,
 If sections of the projects are using different rebate
percentages/charges.
 If sections of the projects are using different budget
allocations.

15
Project System
Module (PS) Accessing the Project

Put no. of required project

16
Project System
Module (PS) Creation Of WBS Elements

Click on WBS Element Overview

Level 1 WBS

Level 2 WBS

17
Project System
Module (PS) WBSe Parameters

G/L A/C, FA & F

Cost center

18
Project System
Module (PS) Project Estimation

Block Estimate

Detail Estimate

• Carrying out Block Estimate


• Carrying out Detail Estimate per
WBS element with Schedule items
with measurement details

19
Project System
Module (PS) Project Estimation

20
Project System
Module (PS) Project Estimation..

Summary GREY AREA

Detail of activity

21
Project System
Module (PS) Claim_Notification Process

22
Project System
Module (PS) Notification Process

23
Project System
Module (PS) Notification Process..

Details date , Time & the concerned


person.

24
Project System
Module (PS) Document Mgmt. System

25
Project System
Module (PS) DMS- In Project / WBS

Document

26
Project System
Module (PS) DMS-In Notification

27
Project System
Module (PS) Notification Process : Business Workplace

Business Workplace

28
Project System
Module (PS) Business Workplace for Claim

29
Project System
Module (PS) Business Workplace for Claim..

Double Click to open

30
Project System
Module (PS) Business Workplace : Inbox..

Save after giving comments

31
Project System
Module (PS) Business Workplace : Forwarding

Login ID

32
Project System
Module (PS) Notification Process**

33
Project System
Module (PS) Estimation–Deviation

34
Project System
Module (PS) Estimation–Deviation..

Quantity yet to get updated


Approval Still Pending

35
Project System
Module (PS) Business Workplace : Inbox

Details of
Deviation

36
Project System
Module (PS) Estimation – after Approval

Notification No. after approval 37


Project System
Module (PS) Project Budgeting
Project Budgeting • Allocate Overall and Annual
Budget for the Project
• Check the fund, fund center and
functional area for the Project WBS
elements
• Release the budget
• Release the WBS elements

THE BUDGET WILL BE ALLOCATED BY THE


EE ------------------IN DEPT LEVEL
AE-------------------IN THE WARD LEVEL

THE BUDGET WILL BE RELEASED BY THE ACCOUNTS OFFICER


38
Project System
Module (PS) Budget Allocation
Basis for Allocation
 Budget Allocation is determined based on Following :

 Estimated Value of the Project


 Contractors rebate (if applicable),
 Water / Sewerage Ch/ Supervision Charges, etc.,
 Contingencies (if applicable).

 Budget for the respective Project will be booked in the Liability


Register which shows outstanding liability.

39
Project System
Module (PS) Budget Allocation.. CJ30

Budgeted Amount to be Released

40
Project System
Module (PS) Budget Allocation.. CJ30

41
Project System
Module (PS) Liability Register :ZPS_LBR

42
Project System
Module (PS) Liability Register..

43
Project System
Module (PS) Work Order Structure

 WO STRUCTURES

 AS MANY ITEMS ARE REQUIRED AS THERE ARE WBS


ELEMENTS
 QUANTITY ---- UNPAID,
 EXT.SER.NO.------PAID UP TO 31ST MARCH
 IF COMPLETE PAID QTY.------- PUT 0.001 IN QUANTITY
COLUMN.

44
Work Order Structure..
Project System
Module (PS)

 T CODE----ME21N

 TYPE------- PROJECT WORK ORDER(ZTPS)


 PUT VENDOR CODE
 ACCOUNTING ASSIGNMENT-------P
 ITEM CATEGORY -------------------D
 SHORT TEXT -----------------------WBS ELEMENT
 MATERIAL CODE -------------------PROJECT WORK
 PLANT
 STORAGE LOCATION---------------0001
 PURCHASING ORGANISATION-----MCGM
 PURCHASE GROUP

45
Project System
Module (PS) Work Order Structure..ME21n

G/L A/C

46
Project System
Module (PS) Variation In Work Order
Project Work Orders
 IF THERE ARE MORE THAN 1 WBS THE work order SHOULD
HAVE AS MANY HEADER ITEMS AS WBS ELEMENTS , UNDER
WHICH SERVICES ARE SPECIFIED.
This is to ensure that payment certificates are created properly
----as rebates / additional charges etc. Would be different for
different WBSe elements.

FOR RELATED ADDITIONAL WO AS


ARBITATION FEES, CONSULTATION
FEES-----
 A SEPARATE WBS ELEMENT IS TO BE CREATED
 WO --- WITH ACCOUNT ASSIGNED AS (P) [WITH NO ITEM
CATEGORY AS (D)]

FOR LS CONTRACT -------------------------


 WO --- WITH ACCOUNT ASSIGNED AS (P) [WITH NO
ITEM CATEGORY AS (D)]

47
Project System
Module (PS) Consultancy PO .. ME21n

48
Project System
Module (PS) PO Release .. ME29n

49
Project System
Module (PS) Work Order Printout.. ZPSWORD

50
Project System
Module (PS) Project Execution.. ZPSPRO
 PHYSICAL PROGRESS

 Enter date wise executed Quantities for various Activities.

 You can enter executed quantities for the Activity for


duration (from / to) also.

 You can maintain text description for the entered executed


quantity.

 Once the executed quantities are saved it cannot be deleted

51
Project System
Module (PS) Project Execution..ZPSPRO

Executed Quantity

Details of Execution

52
Project System
Module (PS) Service Entry Sheet..ML81n

Payment Certification

Service
Selection

53
Project System
Module (PS) Service Entry Sheet..ML81n

Services Selected

54
Project System
Module (PS) Release- Service Entry Sheet

 T CODE----ML81N

 THE SERVICE ENTRY SHEET WILL BE REALEASED


BY THE HIGHER AUTHORITY
 THE SERVICE ENTRY SHEET WILL BE RELEASED
ONLY AFTER THERE IS SUFFICIENT BUDGET
AVAILABLE IN BUDCON FOR THE GIVEN
COMBINATION.

55
Project System
Module (PS) Release of Service Entry Sheet

Release Flag

56
Project System
Module (PS) Payment Certificate

 T CODE----ZPSCERT

 DEDUCTIONS
 ADDITIONS
 OTHER PROJECT COST
 PRICE ESCLATION

57
Project System
Module (PS) Payment Certificate..ZPSCERT

58
Project System
Module (PS) Payment Certificate..ZPSCERT
Deductions
 WCT
 TDS
 PENALTY
 RECOVERY
 ADHOC RECOVERY
 DEFERRED PAYMENT
 DIFFERENCE IN TAXES
 LIQUIDATED DAMAGES

59
Project System
Module (PS) Payment Certificate..ZPSCERT
ADDITIONS
 SERVICE TAX
 EXCISE DUTY & TAXES
 TDS ON MOBILISATION ADVANCE RECOVERY
 WITHHELD AMOUNT TO BE RELEASSED

OTHER PROJECT COST


 SUPERVISION CHAGES
 WATER TAXES
 SEW. CHARGES

ESCLATION
 PRICE
 LABOUR CHARGES
60
Project System
Module (PS) Payment Certificate..ZPSCERT

61
Project System
Module (PS) Goods Receipt_MIGO

62
Payment Processing- MIRO
Project System
Module (PS)

63
Project System
Module (PS) MIRO

64
Project System
Module (PS) MIRO

65
Project System
Module (PS) Reports on Work


BOQ Details ...PZSBOQ

Project Structure..CN41

PO History.. ME2J

Change History..ME2J

Budcon ..

Budcon report
66
Project System
Module (PS) Reports on Work


Total WO value on GL basis.. ME2J

Service Entry Sheet Ward Wise

Status Service Entry Sheet.. ML84

Status of WBS till date

Project Score Card

Project Cockpit
67
Project System
Module (PS) Project Cockpit

68
Project System
Module (PS) Project Score Card

69
Project System
Module (PS) REPORTS- VENDOR PO VALUE

70
Project System
Module (PS) Project Structure

71
Project System
Module (PS) Reports-PO Release status

72
PO-Released.. ME80FN
Project System
Module (PS)

73
Project System
Module (PS)