VLSI Development:

Chip Design Challenges in the Real World


EECE 579 - Advanced Topics in VLSI Design
Spring 2009
Brad Quinton
Goal of this Talk
Building a chip is about far more than circuit
design

how does an Application Specific Standard
Product (ASSP) get built?

who is involved? (i.e. what jobs are available?)

what are the challenges?

what can go wrong?

Scope
this presentation is based on what I have
seen at PMC, Altera, Teradici

companies like, AMCC, Broadcom, Vitesse,
Cypress, Motorola will be very close to this

however, other chip design may be quite
different (i.e. CPU at Intel, or memory design
at Infineon, analog design at TI, etc.)
Key Terminology

RTL: VHDL or Verilog that can be synthesized to
gates

verification: the process of simulating RTL on a
workstation to check functionality

validation: the process of generating input patterns
and evaluating outputs using a real chip
A design team
digital designers
analog designers
verification engineers (the biggest group!)
validation engineers (another large group)
physical designers
software/firmware engineers
production engineers
research engineers
marketing
The support team

CAD tools support engineers
IP QA engineers
CAD tools QA engineers
packaging/PCB design engineers
field application engineers
Phase 1: Product Research
goal: identify all the potential applications that
could benefit from a ASSP (on going)

whos involved:
marketing: talk to customers, look at competition

research engineers: talk to customers
customers, go to conferences, participate in
standard bodies (SONET, Ethernet), think...
Phase 1: Product Research
challenges:
customers want you to build a product just for
them
trying to predict the future is always hard
customers like to have second sources, but this
kills profit margins
there are many potential applications

what can go wrong?:
you guess wrong about the future, spend a lot of
money and dont sell anything
Phase 1: Product Research
Phase 2: Feasibility
decide if it is possible to address the application
given the technology available (~ 2 months)

whos involved:

research engineers: perform high level performance, cost
and power estimates

digital, analog, IP QA engineers: perform more detailed
performance, cost and power estimates
Phase 2: Feasibility
challenges:

it is difficult to estimate a design without actually building it;
this requires a lot of experience

what can go wrong?:

it is easy to miss a detail in the design specification that
radically changes the cost/power of a design

sometimes standards change


Phase 2: Feasibility
IEEE 802.3 Ethernet Collision Detection (150 pages):
Phase 3: Product Planning
decide how much it will cost to build the chip, how
much it will sell for, and how many will sell (6 weeks)

whos involved:
marketing: talk to customers, investigate competition,
negotiate with customers

research engineers: talk to customers customers, consider
application space

Phase 3: Product Planning

designers, verification, validation, layout, production:
estimate who much time and resources it will take to finish
the chip

executive: compare all of the potential chips, potential
profits, resource cost; decide which will be built


Phase 3: Product Planning
challenges:
everything is based on estimates! if even one of them is wrong the
chip might not make money

a competitor might have done the same analysis a year ago and
will beat you to market

what can go wrong:
you may decide to build a chip, and commit millions of dollars only
to find out that one of the estimates that you made was wrong

cancel the project
Phase 4: Design Planning
need to develop documents, schedules and job
descriptions for all the engineers on the team (4-6
weeks)

whos involved:
designers: start writing the initial engineering document,
start partitioning the design in smaller blocks

verification: start reading the engineering document and
partitioning the testbench

validation: start reading the engineering document, and
planning the test infastructure
Phase 4: Design Planning
challenges:
everyone wants to start at once, but they need information
from each other

communicating between all the design groups is key

marketing is likely still changing the requirements

what can go wrong?:
it may take a long time to plan in enough detail to get all the
the team working efficiently

marketing may change their mind, causing you to rewrite
your documents

Phase 4: Design Planning
Phase 5: Documentation
each member of the team needs to document their part of the
design or testbench in detail (6 - 8 weeks)

whos involved:
designers: each designer write an ~80 page document describing
every aspect of their design; top level designer writes an ~400 page
document describing every function in the entire chip in detail

verification: read ALL the design documents and write a
verification plan describing every test that will be simulated on each
block and and the chip level (~200-500 pages)

validation: read ALL the design documents and write a validation
plan describing every test that will be performed in the lab
Phase 5: Documentation
challenges:

documents are tedious to read and write, it is easy to miss
something

what can go wrong?:

again, marketing may change their mind, now you have to
rewrite ALL your documents

Phase 6: Document Review
read each others documents to make sure that
everything is consistent (2-3 weeks)

whos involved:
designers: each designer needs to read document
verification documents, and all adjacent block documents

verification: needs to re-read all design documents to make
sure no tests are missing

validation: needs to re-read all design document to make
sure no tests are missing
Phase 6: Document Review
challenges:

boring

what can go wrong?:

once again, marketing may change their mind, now you have
to rewrite ALL your documents

you may have designed something that is too difficult to
verify (random arbiters, asychronous logic, etc.)

Phase 7: Design
write RTL for the design(s) and create testbench(s)
(4-5 weeks)

whos involved:

designers: writes VHDL/Verilog RTL based on documents

verification: writes testbench in VHDL, tcl, C, Specman

validation: designs PCB, FPGAs, software

software/firmware: generates C-based device driver for the
chip
Phase 7: Design
challenges:
keeping design consistent with documentation

what can go wrong?:

you may find an error in the documentation when you start to
write code

new features

Phase 8: Verification
simulate the RTL view of the design to verify it (8-12
weeks)

whos involved:
designers: help to debug problems found by verifiers

verification: run write test scripts, run tests, debug results

Phase 8: Verification
challenges:
CPU time becomes a critical resource
debugging can take a long time
long run times (up to 12 hours) slow productivity

what can go wrong?:

testbench does not cover all the functionality, and a bug is
missed (this is a million dollar mistake !)


Phase 9: Backend Design
synthesize RTL to gate-level netlist, perform netlist
QA (6-8 weeks)

whos involved:
designers: synthesize RTL, DFT, check design timing, gate
level sims, generate production vectors, formal verification

production engineers: evaluate coverage of production
vectors, cost of tester time to run vectors

CAD tool QA engineers: QA a complete set of CAD tools
for a given technology, deal with bugs in CAD tools

Phase 9: Backend Design
challenges:

understanding CAD tools

what can go wrong?:

if there is a tool bug or other problem then this phase can
delay the entire chip schedule

you may have to pipeline your design to meet timing, this will
effect ALL of the other designers...


<< picture from design vision here>>
Phase 10: Physical Design
place and route the entire design, final design QA (16
weeks)

whos involved:
layout engineers: run CAD tools to place and route design

designers: perform static timing on post-layout design to
make sure that design goals were met

IP QA engineers: review final placement and timing of all
external IP (RAMs, standard cells, etc)

Phase 10: Physical Design
challenges:

timing closure!
manufacturing design rules
CAD tool run time (up to 48 hours..)

what can go wrong?:

a single design rule violation that was ignored could make
the entire chip useless (another million dollar mistake!)


Milestone: Tapeout!
once the physical design, verification, QA,
documentation, etc is done it is sent to the fab
(TSMC), where the masks are created and the wafer
are built (16 -18 weeks)

at this point there is nothing to do but celebrate!


Phase 11: Manufacturing Test
apply a set of vectors to detect manufacturing
defects (3 weeks)

whos involved:

production engineers: apply vectors from DFT phase of
design to the chip using expensive testers

designers: debug vector failures, regenerate patters


Phase 11: Manufacturing Test
challenges:

when vectors fail, it is hard to know why
the testers are expensive and complicated (they are used 24 hours
a day, so engineers/technicians have to work night shifts.)

what can go wrong?:

if a chip that has a manufacturing defect gets accepted, then it may
appear as if there is a functional bug

customers like Cisco will not buy parts unless you can show that
you have a high quality process for catching defects


Phase 12: Validation
run tests to exercise all the features on the chip on the REAL
chip (16 -24 weeks)

whos involved:

validation engineers: write test scripts in tcl or C to control
signal generators, logic analyzers, microcontrollers, and
FPGAs to exercise all functions of the chip

designers: debug failures, update documentation to clarify
functionality

verifiers: recreate lab problems in simulation to allow
observation of internal signals


Phase 12: Validation
challenges:
debugging is extremely difficult since you cant see what
happening inside the chip

deciding what is a bug and what is a feature

what can go wrong?:
miss a bug that is later found by a customer

cause customer to recall their designs (very expensive)


Phase 12: Device Revision
almost all chips need at least one revision (6-
8 months)

whos involved?:

everyone: repeat all the previous tasks, only
quicker!


Phase 12: Device Revision
challenges:
a new set of masks cost ~ $800,000 US (130 nm)
customers want fix right away
executives want to be sure that there will not be another
revision


what can go wrong?:

if you try to do your revision too quickly you may make
another mistake






Milestone: Release to Production







make the decision that the device is ready to ship in
volume (2 - 2.5 years from project start)


whos involved?:
validation engineers: confirm that all test pass

production engineers: confirm that yield is as
expected, performance margins are large enough

design engineers: documentation,
documentation, documentation.














Conclusion







although circuit design is part of the process,
a large amount of work is in the
documentation, verification and validation
of the chip

the key skills required for success in this
industry are: communication, problem
analysis, and attention to detail












Questions?