A project is a temporary Endeavour involving a connected sequence of activities and a range of resources. Project planning is a method of breaking down a project into individual elements ( components, subcomponents, activities and tasks) it defines tasks that can be completed independently of other tasks, facilitating resource allocation, assignment of responsibilities and measurement and control of the project.
A project is a temporary Endeavour involving a connected sequence of activities and a range of resources. Project planning is a method of breaking down a project into individual elements ( components, subcomponents, activities and tasks) it defines tasks that can be completed independently of other tasks, facilitating resource allocation, assignment of responsibilities and measurement and control of the project.
A project is a temporary Endeavour involving a connected sequence of activities and a range of resources. Project planning is a method of breaking down a project into individual elements ( components, subcomponents, activities and tasks) it defines tasks that can be completed independently of other tasks, facilitating resource allocation, assignment of responsibilities and measurement and control of the project.
of resources, which is designed to achieve a specific and unique outcome and which operates within time, cost and quality constraints and which is often used to introduce change.
A unique, one-time operational activity or effort Requires the completion of a large number of interrelated activities Established to achieve specific objective Resources, such as time and/or money, are limited
The application of a collection of tools and techniques to direct the use of diverse resources towards the accomplishment of a unique, complex, one time task within time, cost and quality constraints.
Project planning Project scheduling Project control Project team Made up of individuals from various areas and departments within a company
It is foundation of project planning
A method of breaking down a project into individual elements ( components, subcomponents, activities and tasks) in a hierarchical structure which can be scheduled and cost.
It defines tasks that can be completed independently of other tasks, facilitating resource allocation, assignment of responsibilities and measurement and control of the project
Gantt Chart
Critical Path Method (CPM)
Program Evaluation and Review Technique (PERT)
Project Scheduling and Control Techniques Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule
1. Draw the CPM network
2. Analyze the paths through the network
3. Determine the float for each activity Compute the activitys float float = LS - ES = LF - EF Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project
4. Find the critical path is that the sequence of activities and events where there is no slack i.e.. Zero slack
Longest path through a network
5. Find the project duration is minimum project completion time
CPM Network Example: a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 CPM Example
ES and EF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 Projects EF = 33 a, 6 b, 8 c, 5 0 6 0 8 0 5
PERT is based on the assumption that an activitys duration follows a probability distribution instead of being a single value.
Three time estimates are required to compute the parameters of an activitys duration distribution: Pessimistic time (t p
Most likely time (t m ) Optimistic time (t o )
Pessimistic time (t p ) - the time the activity would take if things did not go well.
Most likely time (t m ) - the consensus best estimate of the activitys duration
Optimistic time (t o ) - the time the activity would take if things did go well.
Mean (t e ) = t p + 4 t m + t o
6 Variance (V t ) = 2 = t p - t o
Draw the network.
Analyze the paths through the network and find the critical path.
The length of the critical path is the mean of the project duration probability distribution which is assumed to be normal
The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum.
Probability computations can now be made using the normal distribution table.
Immediately Optimistic Most Likely Pessimistic Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A -- 4 6 8 B -- 1 4.5 5 C A 3 3 3 D A 4 5 6 E A 0.5 1 1.5 F B,C 3 4 5 G B,C 1 1.5 5 H E,F 5 6 7 I E,F 2 5 8 J D,H 2.5 2.75 4.5 K G,I 3 5 7
Darla/mbs/vit 18
A D C B F E G I H K J
Activity Expected Time Variance A 6 4/9 B 4 4/9 C 3 0 D 5 1/9 E 1 1/36 F 4 1/9 G 2 4/9 H 6 1/9 I 5 1 J 3 1/9 K 5 4/9