Professional Documents
Culture Documents
PROJECT MANAGEMENT
PROJECT MANAGEMENT.
Total no of projects (Rs 20crores &
above)
866.
No of delayed projects=297.
Cost over-run=Rs 24,389 cr
Total anticipated cost=3,75,888cr
Expenditure till Dec 2006 =1,38,905 cr
Scale of time over run =1-196 months.
PROJECT MANAGEMENT.
Out of a total of 866 projects, each costing
Rs 20cr or more ,297 projects- spawned by
13 ministries GOVT of India are running
badly behind schedule. More than 24,000 cr
will be spent additionally, because of delay
an amount sufficient for many more
projects.
---- Quarterly report by the ministry of
statistics and program implementation.
PROJECT MANAGEMENT.
By the time we build the airports, they
have become obsolete.
By the time we build the roads, they
have already become over crowded.
- Mr Ratan Tata.
PMBOK GUIDE
PURPOSE OF PMBOK
The primary purpose of the PMBOK guide is to
identify that subset of project management body of
knowledge that is generally recognized as good
practice.
PMBOK Guide provides guide lines for managing
individual projects. It defines project management
and related concepts and describes project
management life cycle and related processes.
PROJECT MANAGEMENT
Project Management Institute, USA
(PMI) was founded in 1969 to provide a
means for project managers to
associate, share information, and
discuss common problems.
Making project management
indispensable for business results.
www. pmi.org.
PROJECT MANAGEMENT
Project management is application of
knowledge, skills, tools & techniques to
project activities to meet project
requirements.
PROJECT MANAGEMENT
PMI standards are developed, by teams
of hundreds of volunteers from around
the world with expertise, enthusiasm
and dedication to advancing the
practice of project management and the
profession.
PROJECT MANAGEMENT
Over its almost 40 years history, PMI has
created standards and practices that are
globally recognized.
Through its credential programs and
publications, which include A guide to the
project management body of knowledge
(PMBOK Guide), PMI identifies, defines,
documents, and champions valued
approaches.
PURPOSE OF PMBOK
The PMBOK guide also provides and promotes a
common lexicon for discussing, writing and applying
project management. Such a standard lexicon is an
essential element of a profession.
PURPOSE OF PMBOK
Generally recognized means the knowledge and
practices described are applicable to most projects,
most of the time, and there is consensus about their
values and usefulness.
PROJECT MANAGEMENT.
PROJECT MANAGEMENT
A project is a temporary endeavor undertaken to
create a unique product, service or result.
Cost Overrun
Mega Projects
Underground
Railways in Calcutta
Moonidih Coal Mine
Salal Power Project in
J&K
Vizag Steel Plant
20 years
25 years
> 18 years
8 years
General Elections
In your opinion
why do projects
often fail?
Unclear requirements
Poor planning
Lack of clear, realistic project objectives
Misunderstanding of team roles, responsibilities,
authority, and power
Failure to communicate and act as a project team
Lack of buy-in from team members
Project Management Methodology
Project management
Examples of project include, but are
not limited to:
Developing a new product or service.
Effecting a change in structure, staffing, or style
of an organization.
Designing a new transportation vehicle.
Developing or acquiring a new or modified
information system.
Constructing a building or facility.
Building a water supply system for a community.
Project management
Repetitive
PROJECT MANAGEMENT
Uniqueness is an important
characteristics of project deliverables.
For example: many thousands of office buildings
have been developed, but each individual facility
is unique different owner, different design,
different location, different contractors and so on.
The presence of repetitive elements does not
change the fundamental uniqueness of the project
work.
3. Progressive Elaboration
General
Level
of
detail
Detailed
Requirements
High-level design
What is subproject?
Sub-projects are often contracted:
1. to an external enterprise, or
2. to another functional unit in the
performing organization
Project managers of the sub-projects are
accountable to the project manager of a project.
PROJECT MANAGEMENT
The purpose of a project to attain its objectives and
then terminate.
Project
Quality is
affected by
balancing
triple
constraints
Ifscope
any one of the triple constraint factors is affected, at
least
other factor
likely
to be effected,
e.g.,
TIME one
constraints
limits is
team
to determine
& manage
time lines
Deliver high quality product, service or result within scope, time and budget
COST
If scopeconstraints
is increased, itlimits
has a team
likely effect
on time,life
and cycle
cost ascost
well i.e., project
to estimate
cost
If time
or scope
is increased,
cost is most likely
to be effected
plus
operating
and implementation
costs
Organizational Project
Management (OPM)
Projects: temporary endeavors
undertaken to create a unique product,
service or result
PROJECT MANAGEMENT
The projects or programs of the portfolio may not
necessarily be interdependent, or directly related.
For ex:
An infrastructure company that has the strategic
objective of maximizing the return on investment
may put together a portfolio that includes a mix of
projects in oil and gas, power, roads, rail, and
airports.
From this mix, the firm may choose to manage
related projects as one program. All of the power
projects may be grouped together as a power
program. Similarly , all of the water projects may be
grouped together as water program.
Market demand.
Strategic opportunity/business need.
Customer request.
Technological advance.
Legal requirement.
Social need
Project Characteristics
Why do we
undertake Projects?
NEED
NEED
C = f (Q, T, S)
COST
is a function of
QUALITY, TIME, & SCOPE
PMBOK
Project Mgmt.
Methodology
Areas of
expertise
by project
team
3. Product-life-cycle expectations
influence project
Product life cycle includes following projects:
1.
2.
3.
4.
5.
6.
7.
8.
9.
The Internal-Business-Process
Business
PLAN
Need to upgrade
need
Customer
NEED
Identified
Need
Operation
to
Discard
Customer
NEED
Satisfied
PROJECT MANAGEMENT
CHARACTERISTICS OF PHASES
The completion and approval of one or more
deliverables characterizes a project phase.
Project Phases.
The phases:
Example:
Requirements gathering.
Design.
Construction.
Testing.
Implementation.
Project Phases.
Design documents.
Deliverables at kill points.
Test plans.
Exit gates.
Architectural design.
Low level design.
Coding standards
User interface approvals.
Planning phase
Construction phase
PROJECT MANAGEMENT
High
Low
Influence of Stakeholders,
Opportunity to add Value, and
Uncertainty of success
PROJECT MANAGEMENT
LIFE CYCLE
Project
manager
is
A
stakeholder
is someone
Project
management
Sponsor
is a person
or
responsible
to:
whose
interests
may
be
team are the members
1.
Accomplish
objectives,
group
that
provides
the
positively
or project
negatively
of
the
project
team
who
2.
Identify
&resources,
quantify
risks,
financial
in
impacted by the project.
response
to involved
the uncertainties,
are
directly
in &
cash
or
kind,
for
the
control risks during execution
the
project
management
They
may also
include those
3.
Continuously
utilize
project
activities
whoprogressive
may exertelaboration
influence
over
the project
but would
technique
throughout
the
not project
otherwise
be considered
life cycle,
stakeholders.
4.
Adhere to code of professional
conduct
sponsor
Proj.
Mgr
Project
mgmt team
Proj. Team
Performance
organization
Performance
of
work
Organization
culture
Concerned with
identifying, analyzing, and
responding to project
risks
To ensure timely
completion of project
Estimate costs
Identify stakeholders
Determine budget
Plan communications
Distribute information
Control costs
Plan Quality
Report Performance
Control scope
Identify risks
Perform qualitative risk analysis
Perform quantitative risk analysis
Plan risk responses
Monitor and control risks
Plan procurements
Conduct procurements
Administer procurements
Close procurements
Introduction to
Project Management
Processes
Project management
processes
Project Integration Management: Develop project charter:- is the process of
developing a document that formally authorizes a
project or a phase and documenting initial
requirements that satisfy the stakeholders needs
and expectations.
Develop project management plan:- is the process of
documenting the actions necessary to define,
prepare, integrate, and coordinate all subsidiary
plans.
Direct and manage project execution:- is the process
of performing the work defined in the project
management plan to achieve project objectives.
Project management
Monitor and control project work:- is the process of
tracking , reviewing, and regulating, the progress to
meet the performance objectives defined in the
project management plan.
Perform integrated change control :- is the process
of reviewing all change requests, approving
changes, and managing changes to the deliverables,
organizational process assets, project documents,
and the project plan.
Close project or phase: is the process of finalizing
all activities across all of the project management
process groups to formally to complete the project
or phase.
Project HR mgt
Develop human resource plan :- is the process of
identifying and documenting project roles,
responsibilities, required skills, reporting
relationships, and creating a staffing management
plan.
Acquire project team:- is the process of confirming
human resources availability and obtaining the team
necessary to complete the project assignments.
Develop project team:- is the process of improving
the competencies, team interactions, and the overall
team environment to enhance project performance.
Manage project team:- is the process of tracking
team member performance, providing feed back,
resolving issues, and managing changes, to
optimize project performance.
PROJECT MANAGEMENT
PROCESS GROUPS
INITIATION.
PLANNING.
EXECUTING.
MONITORING & CONTROLLING.
CLOSING.
PROCESS
inputs
tools &
outputs
techniques
control
plan
information
monitor
Identify stake
Holders.
Project
objective
+40%
ROI
Sponsor
Project
mgr.
Project
stakeholders
Time
Activities
Interaction between
Project mgmt. process groups
Executing
Process
Planning
Process
Initiating
Process
Phase
Start
Closing
Process
Controlling
Process
time
Phase
Finish
PROJECT MANAGEMENT
Project Management Office :
A PMO is an organizational unit to centralize and
coordinate the management of projects under its
domain.
PMO
The responsibilities of PMO, can range from
providing project management support functions to
actually being responsible for the direct
management of a project.
PMO
Coaching, mentoring, training and oversight.
Monitoring compliance with project management
standards policies, procedures, and templates via
project audits.
Developing and managing project policies,
procedures, templates, and other shared
documentation.
Coordinating communication across projects.
Initiatio
n
Process
group
Planning
Process
group
Executing
Process
group
4.Project
Management
Integration
4.1Devel
op
Project
Charter.
4.2 Develop
Project
Management
plan.
4.3 Direct
& Manage
Project
execution
5. Project
scope
management.
6. Project
Time
Management
7. Project
Cost
Management.
8.Project
Quality
Management
9. Project
Human
Resource
Management.
5.1 Collect
requirements.
5.2 Define
Scope.
5.3 Create
WBS
6.1 Define
activities.
6.2 Sequence
Activities.
6.3 Estimate
Activity
Resources.
6.4 Estimate
activity
durations.
6.5 Develop
Schedule.
7.1 Estimate
Costs.
7.2 Determine
Budget.
8.1 Plan
Quality.
9.1 Develop
Human
resource plan.
Monitoring
&
controlling
Process
group
4.4 Monitor
& control
Project
work
4.5
Perform
Integrated
Change
control
5.4 Verify
Scope.
5.5 Control
Scope.
6.6 Control
schedule
7.3 Control
Costs.
8.2
Perform
Quality
assurance.
9.2 Acquire
Project
Team.
9.3Develop
Project
Team
9.4 Manage
8.3
Perform
Quality
Control
Closing
Process
group
4.5 Close
project or
Phase.
10.1
10.2 Plan
Identif Communicatio
y
ns
Stake
holder
s.
11. Project
Risk
Management.
12. Project
Procurement
Management.
2
Total = 42 processes.
10.3
10.5 Report
Distribute
Performanc
Information e
.
10.4
Manage
Stake
holder
Expectation
s.
11.6
Monitor
and Control
Risks.
12.3
Administer
procuremen
ts
10
12.4 Close
Procuremen
ts.
2
Process group
break up
2
20
8
10
2
42
processes
processes
processes
processes
processes
Chief Executive
Functional
manager
Functional
manager
Functional
manager
Functional
manager
Functional
manager
Functional
manager
staff
staff
staff
staff
staff
staff
staff
staff
staff
staff
staff
staff
staff
staff
staff
staff
staff
staff
Function organization
In balanced
People
have
split
the loyalty
focus
matrix,
between
the
towards
project
power
isand
their
function
functional
balanced
manager PMs
responsibilities
between
& not
&
to weak
in
functional
the projects
matrix
mgrs
Chief Executive
Functional
manager
Functional
manager
Functional
manager
staff
staff
staff
staff
staff
staff
P.Mgr
staff
staff
Chief Executive
Functional
manager
Functional
manager
Functional
manager
Project
head
staff
staff
staff
P.Mgr
staff
staff
staff
P.Mgr
staff
staff
staff
P.Mgr
Chief Executive
Projectized organization
Project
manager
Project
manager
Project
manager
staff
staff
staff
staff
staff
staff
staff
staff
staff
Composite Organization
Project Roles
Project Manager:
Is the person ultimately responsible for the outcome of the project.
Found in balanced, strong matrix and projectized organization.
Project coordinator:
Is weaker than project manager, may not be allowed to make
budget decisions or over all project decisions, but may have some
authority to reassign resources.
Usually found in weak matrix or functional organizations
Project expeditor:
Is the weakest among the project roles.
Is staff assistant who has little or no formal authority.
Reports to the executive who ultimately has responsibility of the
project.
Responsibility lies in making sure that things arrive in time and the
tasks are completed on time.
Part time role --- found in functional organizations.
BCR
Pay Back Period
Discounted Cash Flow
IRR
ROI
Economic Value Added Method
PROJECT SELECTION
METHODS
Mathematical methods:
Constrained optimization methods linear, dynamic,
integer, non linear, and/or multi objective programming.
SCORING MODEL
SCORING MODEL:
criteria
weight
proj-A
proj-B
proj-C
profit potential
marketability
ease to produce
41
37
29
weighted score
project -A is the obvious choice.
Year.
1
2
3
Total
inflows.
10,000
15,000
5,000
30,000
PV
8,929
11,958
3,559
24,446
Less investment
NPV
24,000
446
Year
inflows
1
7,000
2
13,000
3
10,000
Total
30,000
Less investment
NPV
PV
6,250
10,364
7,118
23,732
24,000
<268>
RETURN ON INVESTMENT
Is a % that shows what return you make by making
in something.
Ex: a company invests in a project that costs
$200,000. The benefits of doing the project save the
company $230,000 in the first year alone.
ROI = (benefit-cost)/cost=30,000/200,000
15%.
For the exam:
ROI , bigger is better.
BEP
BREAK EVEN POINT:
BEP analysis is done for a predefined for future time
periods ( years, months, or weeks ).
It evaluates the time period when total cash inflow
equals fixed cost.
If calculated BEP value is less than expected value,
investment is considered justified.
BEP
A club is planning a dance party for its members.
The tickets will be sold for $30 each.
Fixed costs (band & hire hall etc, ) $1500.
The variable costs (food etc, ) will be $10, for each
ticket sold.
(x)*(30)= (x)*(10)+1500.
X=75
no of tickets to be sold for BEP.
Project Management
Charter.
Scope Statement.
Work Break Down Structure.
Understand requirements.
Define the scope.
Break down the scope in the form of WBS.
Control the scope of the project.
Verify that the project is completed correctly.
Define scope
.
Product analysis.
Product breakdown.
System analysis.
Requirement analysis.
System engineering.
Value engineering.
Define scope
Alternatives identification:
Brainstorming.
Lateral thinking. (Shift in paradigm)
Create WBS
Apply for
Passport
Get
Application
Form
Fill
Application
Form
Submit
Application
Form
Obtain
Police
verification
Visa
Get
Passport
Ticketing &
Boarding
Why it is important?.
If the stakeholders are not properly identified on the project
and their needs are understood, then there is little chance of
meeting their expectations.
Many projects are derailed because they did not understand
the needs of stakeholders and address them on the project.
Identify stakeholders
Stake holder analysis
tool.
high
Manage
closely.
Keep
satisfied.
power
Keep
informe
d.
Monitor(mini
mum effort).
low
low
Interest.
high
VERIFY SCOPE.
Verifying the project scope includes reviewing
deliverables with the customer or sponsor, to ensure
that they are completed satisfactorily and obtaining
formal acceptance of deliverables by the customer
or sponsor.
VERIFY SCOPE
If the project is terminated early, the project scope
verification process should establish and document
the level and extent of completion.
Control Scope
Control scope:
Is the process of monitoring the status of the project
and product scope and managing changes to the
scope base line.
It ensures all requested changes and recommended
corrective or preventive actions are processed
through the perform integrated change control
process.
Control Scope.
Is also used to manage actual changes when they
occur and is integrated with other change control
processes.
Uncontrolled changes are termed as Scope Creep:
Avoid scope creeps.
ESTIMATIONS
Analogous estimation:
top down estimate. It is a form of expert judgment.
Parametric estimating / Quantitative method :
it uses a mathematical model to calculate projected
times for an activity based on historical records from
previous projects. Such as time per line of code,
time per linear meter or time per installation.
Learning curve:
the 100th room painted will take less time than the
first room because of improved efficiency.
Scheduling Techniques
Activity on arrow (AOA) also known as ADP( arrow
diagramming method).
Activity on Node (AON) also known as PDM (
predecessor diagramming method).
CPM & PERT.
CPM-EXERCISE-1
Sl.no act
1.Estimate cost
to complete project.
2.Bid job& get order.
3.Build system
4.Dev-training
5.Implement.
dur
pred.
7d
15 d
7d
4d
5d
---1
2
2
3,4
CPM EXERCISE-2
SL. NO.
ACTIVITY.
DUR.
A
B
C
D
2 DAYS.
6 DAYS. 1
8 DAYS. 1
4 DAYS. 2,3
1
2
3
4
PRED.
CPM-3
SL
A
Activity
Dur(Hrs)
Remove & dis mantle
motar.
8
B. Clean & Paint frame.
7
C. Rewind armature.
12
D. Replace armature.
9
E. Assemble & Install
Motar.
4
Calculate the total time of the ovehaul.
Pred.
---A.
A.
A.
B,C,D
CPM-Exercise.
Sl no
activity
1 Get equipment.
2. hire people.
3. develop system.
4. training.
5. documentation.
6. install system.
dur
5d
4d
15 d
3d
6d
9d
pred.
1,2
3
3
4,5
CPM EXERCISE-3
Sl no.
Act
dur
pred.
1. project dels
12 d
---2.procure h/w
2
1
3.test h/w
8
2
4.procure s/w tools.
10
1
5.write programs
45
4
6.test & debug
22
5
7.install
8
3,6
8.training
3
7
9.acceptance
1
8.
Find critical path, float/slack, free float/free slack for
each activity.
CPM-EXERCISE HOUSE
CONSTRUCTION.
Sl.no
activity
1 lay foundation
2 erect frame
3 install mill works
4 install wiring
5 install plumbing
6 plaster walls
7 decorate interior
8 install siding
9 finish exterior
10 finish
duration
3w
4w
3w
1w
1w
4w
1w
3w
4w
0
pred
nil
1
2
2
2
2
3,4,5,6
2
8
7,9
CPM EXERCISE-6
Sl no act
1
2
3
4
5
6
7
8
specs
design data base part.
design GUI part.
code data base part.
code GUI part.
integrate & test.
write user manual.
finish.
dur
15d
45d
30d
105d
45d
120d
60d
0d
pred
nil
1
1
2
3
4,5
1
7,6
CPM
Sl no
1
2
3
4
5
activity
Dur
Predecessor.
Remove & Dismantle motar. 8hrs -----Clean & paint frame.
7hrs 1
Rewind armature.
12 hrs 1
Replace bearing.
9 hrs 1
Assemble & Install motar.
4 hrs 2,3,4
CRASHING
Sl no activity duration
A.
B.
C.
D.
5 days.
7days
11days
2 days
pred
----A
---B,C.
CRASHING
Task
Pred
Nor
mal
dur
Crash
time
Crashing cost/day
4$/D
1$/D
4$/D
2$/D
2,4
COST OF OVERHEAD
$4.5/D
CPM-7
PERT FORMULA.
Pert duration: p+(4)*(M)+0 divided by 6.
Standard deviation of an activity of
an activity=(p-o)/6.= s.d.
Variance of an activity = (s.d) squared.
Confidence = NORMDIST(D, PERT TIME, SD, TRUE ).
Duration needed at a confidence level = NORMINV
(PROB, PERT DUR, SD ).
PERT EXERCISE-1
SL.NO
pred
O M P
1 ESTIMATE
5 7 15
2 BID
1
10 15 25
3 BUILD
2
4 7 10
4 TRAIN
2
4 4
4
5 IMPLEMET.
3,4
3 5
10
Find PERT duration of the project.
Probability of completing the project?
PERT EXERCISE- 2
Sl no
1
2
3
Activity
A
B
C
OMP
2 4 6
5 13 15
13 18 35
PERT EXERCISE- 2
PERT EXERCISE- 2
If two tail statistical table is referred:
68% confidence = 68/2 = 34% confidence for 36 days
to 40.08 days.
34% confidence for 31.92 to 36 days.
So for confidence of 0.34 , z= 1.0
Z= (x- pert dur of project )/ s.d = 1= (x-36)/4.08 , x=
40.08 days.
If single tail statistical table is referred:
Add 0.5 to 0.34 i,e 0.84 that corresponds to z value
of 1.0 x=40.08 days.
If excel is used prob =0.84 excel uses single tail
PERT EXERCISE: 3
Sl no. Act
dur (d)
pred.
1. project dels
10- 12 -14
---2.procure h/w
2 -2 -2
1
3.test h/w
8 -8 -8
2
4.procure s/w tools. 8 -10 -14
1
5.write programs
38 -45 -57
4
6.test & debug
20-22 -30
5
7.install
5-8-10
3,6
8.training
3-3 -3
7
9.acceptance
1 -1-1
8.
Find critical path, float/slack, for each activity.
There is 68% chance that write program activity will be
completed in ------ days to -------- days.
PERT EXERCISE: 3
PERT duration of activity write program =
(p+4*m+o)/6 = (38+4*45+57)/6 = 45.83
Standard deviation = (p-o)/6 = (57-38)/6 =3.17
Now we can say:
There is 68% chance that write program activity
will be completed in 42.66 days to 49 days
Critical chain
Critical chain method:
Dr Goldratt.
Managing systems through constraints: TOC
Weakest link is the strongest, because it can break
it.
1. Identify the constraint of the system.
2. Decide how to exploit the constraint of the system.
3. Subordinate every thing else to the decision taken
regarding the constraint.
4. Elevate the constraint.
5. Go back to focusing step-1
Critical chain
Project management using TOC:
RESOURCE LEVELLING
Sl.no
1
2
3
4
5
6
7
activity
A1
A2
B1
B2
C1
C2
C3
duration
3D
2D
2D
2D
3D
3D
2D
pred
nil.
1
nil
3
nil
5
2,4,6
Reso.
Ram.
Lax.
Lax.
Lax.
Sita.
Sita.
Sita.
Earned Value
4-fences. Each fence/day. Rs1000/fence. One fence
after another.
Report at Day-3.
Completed one wall. spent Rs1000.(D-1)
Completed one wall. Spent Rs1200(D-2)
Completed 50%wall.spent Rs600 (D-3)
Pv=1000+1000+1000=3000
Ev=1000+1000+500=2500
Ac=1000+1200+600=2800
Earned Value
BAC =Rs4000.
Cost variance = EV-AC=2500-2800=-300
Cost performance index =EV/AC=2500/2800=0.893
Over budget. Getting 89 paise for every rupee.
Schedule variance =EV-PV=2500-3000=-500
Schedule performance index=SPI=2500/3000=0.833
Behind schedule & progressing @83% of the rate
originally planned.
Exercise - EV Problem
The project: 5 software package installs on 5 existing
PCs in 5 weeks (1 installation /week ) for a total
consulting fee of $5,000. After two weeks only 1 install
has been done for a cost of $1,500.
Determine PV, AC, EV.
Calculate SV, CV, SPI, CPI.
Assume the rate of progress continues and calculate
EAC .
164
Exercise Solution
165
Earned Value
You have planned for a project to write a software
application to take 1 year. The costs to this project
are budgeted at $12,500 per month.
Six months into the project, you find that software
application is 50% completed, & spent $70,000
Calculate CV, CPI, SV, SPI, VAC.
Earned Value
168
EVM
Consider a company that took earned value
measurements at monthly intervals for the past three
months:
EV
AC
Month-1
$22,000
$13,700
Month-2
$151,000
$ 137,900
Month-3
$ 107,000
$98,400
CPI cum? At the end of 3-months.
EVM
EV
EVc
AC
ACc
CPI
CPIc
1.61
RACI
RACI Chart
Person
Activity
Krishna
Ram
Sita
Karthik
Vinay
Define
Design
Develop
Test
PROJECT QUALITY
MANAGEMENT
INCLUDES ALL THE ACTIVITIES OF THE
PERFORMING ORGANIZATION THAT DETERMINE
QUALITY POLICIES, OBJECTIVES, AND
RESPONSIBILITES SO THAT THE PROJECT WILL
SATISFY THE NEEDS FOR WHICH IT WAS
UNDERTAKEN.
QUALITY
Quality is the degree to which a set of inherent
characteristics fulfill requirements.
Stated and implied needs are inputs to developing
project requirements.
QUALITY
Plan quality:
The process of identifying quality requirements and how
the project will demonstrate compliance /or standards
for the project and product, and documenting.
Plan communications:
The process of determining the project stakeholder
information needs and defining a communication approach.
Distribute information:
The process of making relevant information available to the
project stakeholders as planned.
Report performance:
The process of collecting and distributing performance
information, including status reports, progress
measurements, and forecasts.
Project Risk
Management.
probability is
the language
of uncertainty
Risk management is
the means by which
uncertainty is
systematic managed
Risk
Uncertain
event
or
condition
that if
occurs
has
+ ve - ve
A cause:
Having limited personnel assigned to design
a project.
Risk event / condition:
The design personnel available and assigned
may not be adequate for the activity.
Impact on project objective:
Cost, schedule ,or performance (quality).
Risk score=(probability)*(impact) for
prioritization.
Low
.1
<5%
Insignificant
cost increase cost increase
Insignificant
sch slippage
<5%
sch slippage
Affects vary
demanding
applications
Moderate
High
Very high
.2
.4
5-10%
cost increase
10-20%
cost increase
>20%
cost increase
5-10%
10-20%
>20%
sch slippage
sch slippage
Scope
Major areas
of scope
reduction
affected
unacceptable
Quality
reduction
requires
approval
Quality
reduction
unaccepted
.8
sch slippage
Effects
project
product
Effects
project
product
Threats
Probability
0.9
0.05
0.09
0.18
0.36
0.72
0.72
0.36
0.18
0.09
0.05
0.7
0.04
0.07
0.14
0.28
0.56
0.56
0.28
0.14
0.07
0.04
0.5
0.03
0.05
0.10
0.20
0.40
0.40
0.20
0.10
0.05
0.03
0.3
0.02
0.03
0.06
0.12
0.24
0.24
0.12
0.06
0.03
0.02
0.1
0.01
0.01
0.02
0.04
0.08
0.08
0.04
0.02
0.01
0.01
0.05
0.10
0.20
0.40
0.80
0.80
0.40
0.20
0.10
0.05
Moderate impact
High impact
RISK SCORE
Risk event : govt may increase commercial tax.
Likely Impact on the project objective: cost increase
<6%.
Ref impact matrix:
It is low with value 0.2
Prob of this event happening=0.2
The risk score =(0.2)*(0.2)=0.04
Ref PI matrix : this score is on Green.
This may not require response plan.
RISK SCORE
Risk event: there may be strike on port.
Likely impact on the project objective: cost . The
cost of out put of the project may increase >20%.
Ref impact scale : very high (0.8)
The team assess the prob of this event happening=
0.4
The risk score of this event =(0.8)*(0.4)=0.32
This score is on RED. To be taken on top priority
for response planning.
Technical
Requirements
External
Subcontractors
& Suppliers
Organizational
Project
dependencies
Technology
Project Mgmt
Estimating
Planning
Regulatory
Resources
Complexity &
Interfaces
Market
Funding
Controlling
Performance
& Reliability
Customer
Prioritization
Communication
Quality
Weather
Project Management
Risk can be threat or opportunity.
Responses for threat:
Avoid, transfer, mitigate.
RFP
Guide lines for drafting a formal request for proposal
for an contractor:
An RFP must provide statement of work.
Customer requirements.
What deliverables the customer expects the contractor or
the project team to provide.
Should list any customer- supplied items.
RFP might state approvals required by the customer.
Some RFP mention the type of contract the customer
intends to use.
An RFP might state the payment terms the customer
intends to use.
Should state the required schedule for completion of the
project.
RFP
Should provide instruction for the format and the content of
the contractors proposal.
Should indicate the due date by which the customer expects
potential contractors to submit proposals.
May include evaluation criteria.
In rare cases an RFP will indicate the funds the customer
has available to spend on the project.
Preparing proposal
The customer will select the one that it expects will provide the best
value.
In the proposal the contractor must convince the customer that the
contractor :
Preparing proposal
Preparing proposal
Proposal contents:
Technical.
Management.
Cost.
Technical section:
Objective is to convince the customer that the contractor understands
the need or problem and can provide least risky and most beneficial
solution.
Understand the problem.
Proposed approach / solution.
Benefits to the customer.
Management section:
Description of work tasks.
Deliverables.
Project schedule.
Project organization.
Related experience.
Equipment and facilities.
Preparing proposal
Cost section:
The objective is to convince the customer that the contractors
price for the proposed project is realistic and reasonable.
In some cases, the customer may want only the bottom line total
cost of the project.
Some customers also want to see the cost of optional items.
Government RFP s usually require contractors to provide a
detailed breakdown of various costs.
Labor.
Materials.
Subcontractors and consultants.
Equipment and facilities rental.
Travel.
Documentation.
Overhead costs.
Escalation.
Contingency.
Fee or profit.
Project
CHARTER,
Now I have
an authority
to direct the
assigned
resources on
project to:
scope
manage
Triple
Constraints
Budget
mile
stones
You not only contributed to the projects success, but also probably
expanded your knowledge and enhanced your skills along the way.
Project Management
Project management provides people with a
powerful set of tools that improves their ability to
plan, implement, manage activities to accomplish
specific organizational objectives.
Project management is wave of future.
It is a result oriented management style that focus
on building collaborative relationships among
diverse stakeholders.
Exciting opportunities wait people skilled in project
management.
Project Management
Project management provides people with a
powerful set of tools that improves their ability to
plan, implement, manage activities to accomplish
specific organizational objectives.
Project management is wave of future.
It is a result oriented management style that focus
on building collaborative relationships among
diverse stakeholders.
Exciting opportunities wait people skilled in project
management.
Project Management
Thank You