You are on page 1of 51

Role of Electricity Regulatory

Commissions

By
S C Shrivastava
Joint Chief (Engg)

Central Electricity Regulatory Commission

In this presentation
Overview
Legal/Policy framework
Regulatory framework

Regulatory scope/activities
Market Development - CERC

initiatives & impact


12/8/2014

CERC

OVERVIEW
12/8/2014

CERC

Sectoral Parameters
Unelectrified rural households (2001
Census)

77.8 million
(57%)

Power Supply Position during July


2010
- Energy shortages
- Peaking deficit

8.3%
12.1%

Generating plants PLF (2009-10) All


India
Generation performance (2009-10)

77.53%
771 BUs
(7.0 % growth over
corresponding period of
previous year)

Cumulative High Voltage Transmission 2,26,458 ckt km


links (220 KV and above) (upto April
2010)
12/8/2014

CERC

Installed Generation Capacity in India


(as on 31.01.2011)

Total Installed Capacity


(as on 31.01.2011)
12/8/2014

CERC

Installed Renewable Generation Capacity in India


(end December10)
Renewable Energy Installed Capacity (MW)

5%

1%
Wind Power

8%

Small Hydro Power

16%

Biomass Power

70%
Bagasse Cogeneration
Waste to Power
Solar Power (SPV)

Total Installed Capacity


(as on 31.12.2010)
Contributes 4% of total Electricity
Generation
12/8/2014

CERC

Power Infrastructure in India


(as on 31.01.2011)
State

CENTRAL SECTOR

PRIVATE SECTOR

21%
48%
31%

Total Installed Capacity


(as on 31.01.2011)

12/8/2014

CERC

Ownership Status of Transmission


and Distribution
Almost 100% of Electricity Transmission
in India is owned by public sector.

About 13 % of Electricity Distribution in


India is owned by private sector.

12/8/2014

CERC

Electricity Requirement 2031 - 32


GDP Growth Rate
8%

9%

Total Energy Requirement

3880

4806

Energy Requirement at Bus Bar

3628

4493

Projected Peak Demand (GW)

592

733

Installed Capacity Requirement (GW)

778

960

Billion kWh

Source: Integrated Energy Policy

12/8/2014

CERC

LEGAL/POLICY
FRAMEWORK
12/8/2014

CERC

10

Basic Legal Framework


Electricity a concurrent subject as per
Constitution of India.
Both Centre and States can legislate.
In

case

of

repugnancy,

Central

legislation prevails.
12/8/2014

CERC

11

Legal Framework under old laws

12/8/2014

Regulatory authorities under IE Act, 1910 and E(S)


Act, 1948
Central Government
State Government
CEA
SEB
Central Government Powers to fix capital ceiling for
TEC clearance etc.
State Government Powers to grant licence etc.
CEA TEC of generation projects, technical norms
etc.
SEB Several powers as main advisor of State
Govt.

CERC

12

Legal Framework

12/8/2014

Contd

Regulatory authorities under ERC Act,


1998
CERC
SERCs
JERC

Objective distancing of Govt./Govt.


organization from regulation.

CERC

13

Legal Framework Electricity Act, 2003

Consolidates laws of electricity relating to generation,


transmission, distribution and trading of electricity.

Creates environment conducive for development of


electricity industry.

Introduction of competition.

Constitution

of

Central

and

State

Regulatory

Commissions to rationalize electricity tariffs.


12/8/2014

CERC

14

Electricity Act 2003 -Key Features

12/8/2014

Open Access to Transmission /Distribution Systems

De-licensing of power generation

Trading in electricity permitted

Liberal provisions for captive power generation

Rural generation and distribution freed from licensing

Expanded role for the Regulatory Commissions

Envisages unbundling of transmission and distribution.

Regulatory Commissions to develop electricity markets.

CERC

15

The Electricity Act, 2003

Clear demarcation of role and responsibility of

Government (policy making)

Independent Regulatory Commission (powers of


regulation)

Other statutory bodies like Central Electricity

Authority (as expert body on technical matters)

12/8/2014

CERC

16

Government

Formulation of

National Electricity Policy

Tariff Policy

National Electricity Policies on rural electrification.

Powers to issue directions to the Regulatory


Commissions

on

issues

involving

public

interest.
12/8/2014

CERC

17

National Electricity Policy

Total village electrification by year 2010

By year 2012 :

Per capita availability 1000 units.

Installed capacity over 200,000 MW.

Spinning reserves 5% .

Minimum lifeline consumption of 1 unit per household per


day.

12/8/2014

Inter-regional transmission capacity 37,000 MW.

Energy efficiency/ conservation savings about 15%.

CERC

18

Tariff Policy

Mandates

competitive

procurement

of

power

and

transmission services transitional window of 5 years period

given to public sector companies.

Encourage efficiency in operations by sharing of gains


between licensees and consumers.

Promote Multi-Year Tariff (MYT) framework.

Encourage loss reduction Strategies.

Tariff design : Linkage of tariffs to cost of service

gradual reduction in cross subsidy (+/- 20% of average cost


of supply)

Progressive reduction in Cross-subsidy surcharge for open


access.

12/8/2014

CERC

19

REGULATORY FRAMEWORK
12/8/2014

CERC

20

Regulatory Commissions

At the Center CERC

Powers to regulate centrally owned generating companies


and companies having composite scheme for generation and
sale of electricity in more than one State.

To regulate inter-State transmission/Trading.

In the States SERCs

Powers to regulate intra-State generation, transmission and


distribution.

CERC vis a vis SERCs

No hierarchical relationship. However, SERCs are to be


guided by the principles of tariff determination specified by

12/8/2014

CERC.

CERC

21

Functions of CERC

to regulate the tariff of inter-state generating companies

to regulate the inter-State transmission of electricity

to

determine

tariff

for inter-State

transmission

of

electricity

to issue licenses for inter state electricity transmission


and trading.

to adjudicate upon inter-State disputes

to specify Grid Code

to specify and enforce the standards with respect to


quality, continuity and reliability of service

12/8/2014

to fix the trading margin


CERC

22

Functions of CERC

Advisory Functions:

formulation of National electricity Policy and tariff policy;

promotion of competition, efficiency and economy in the activities of


the electricity industry;

promotion of investment in electricity industry;

any other matter referred to the Central Commission by the Central


Government

12/8/2014

CERC

23

Functions of SERCs

determine the tariff for generation, supply, transmission and wheeling


of electricity, wholesale, bulk or retail within the State

regulate electricity purchase and procurement process of distribution


licensees

facilitate intra-State transmission and wheeling of electricity

issue licences for intra state transmission, distribution and trading.

promote co-generation and generation of electricity from renewable


sources of energy

adjudicate upon the intra-state disputes

specify or enforce standards with respect to quality, continuity and


reliability of service by licensees;

12/8/2014

fix the trading margin in the intra-State trading of electricity

CERC

24

12/8/2014

Functions of SERCs

Advisory Functions:

promotion of competition, efficiency and economy in


activities of the electricity industry;

promotion of investment in electricity industry;

reorganization and restructuring of electricity industry in


the State;

matters

concerning

generation,

transmission

distribution and trading of electricity or any other matter


referred to the State Commission by that Government.

12/8/2014

CERC

25

12/8/2014

Mission Statement-CERC

The

Commission

promotes

competition,

efficiency

and

economy in power markets, protects the interests of consumers


and promotes investments in power sector. In pursuit of these
objectives the Commission aims to

Formulate an efficient tariff setting mechanism which ensures economy and


efficiency in the pricing of bulk power and transmission services and leads to
least cost investments,

Promote development of power market by creating a market structure,


facilitating open access in inter-State transmission, facilitating interstate
trading,

Improve the operations and management of the inter-State transmission


systems through Indian Electricity Grid Code (IEGC), Availability Based Tariff
(ABT),

12/8/2014

CERC

26

Regulatory Commission - a quasi judicial body

Powers of Civil Court for the purposes of


inquiry or proceedings under the Act.
(Section 94)

Powers

to

compliance

impose
of

penalty

direction

of

for

non-

Regulatory

Commissions.

12/8/2014

Powers to adjudicate
CERC

27

Accountability of Regulators

Annual Report to be laid before the Parliament.

Accounts of Regulatory Commissions to be


audited by CAG.

Appeal against the orders of Regulatory

Commissions to lie before the Appellate


Tribunal.

12/8/2014

CERC

28

Procedure for Regulations

12/8/2014

CERC

29

PROCEDURE FOR PETITIONS


PETITIONER

RESPONDANTS

ARGUMENTS

REVIEW
PROCEEDINGS

12/8/2014

ORDERS

CERC

Appeal in
Appellate
Tribunal

30

Appellate Tribunal

Constitution of Appellate Tribunal consisting of Chairman,


three Members (Technical and Judicial) and one Member

with specialization in Petroleum Sector.

Appellate Tribunal to hear appeals against the orders of


CERC/SERC/PNGRB.

The appeal to Appellate Tribunal should be filed within 45


days of order issued by CERC/SERC/PNGRB.

Appeal against the orders of Appellate Tribunal to lie before


the Supreme Court within 65 days.

12/8/2014

Appellate Tribunal considered necessary to-

Reduce litigation and delay in decisions through High Court.

Provide technical expertise in decision on appeals.


CERC

31

REGULATORY
SCOPE/ACTIVITIES
12/8/2014

CERC

32

Generation

No requirement of licence.

Full freedom to captive generation.

For hydro-generation clearance of CEA is necessary


due to concern of dam safety and inter-State issues.

Generation from Non-Conventional Sources / Cogeneration to be promoted. Minimum percentage of

purchase of power from renewables may be prescribed


by Regulatory Commissions.

12/8/2014

CERC

33

Transmission

Transmission Utility at the Center and in the States to


undertake

planning/development

of

transmission

system.

Regional Load Despatch Centers to ensure integrated


operation of the power system.

Flexibility regarding keeping Transmission Utility and


load despatch together or separating them.

The

Load

Despatch

Centre/

Transmission

Utility/Transmission Licensee not to trade in power.

12/8/2014

CERC

34

Trading/ Market development

Trading distinct activity permitted with licensing.

Regulatory

Commission

to

specify

technical

requirement, capital adequacy requirement and credit


worthiness for a trader.

Regulatory Commission may fix ceiling on trading


margin to avoid artificial price volatility.

The Regulatory Commission to promote development

of market including trading.

12/8/2014

CERC

35

Tariff

Regulatory Commissions to determine tariff for

Supply by Generating Company to distribution licensee


through long term contract. For short term contracts only

minimum and maximum ceiling of tariff.

12/8/2014

Transmission of electricity.

Wheeling of electricity

Retail sale to consumers by Licensee.

CERC

36

MARKET DEVELOPMENT
- CERC INITIATIVES & IMPACT
12/8/2014

CERC

37

Market Development - CERC initiatives

Regulations on

Short-term Open Access

Grant of Connectivity, Long-term Access and Mediumterm Open Access in inter-State Transmission.

Grant of Regulatory Approval for execution of Inter-State


Transmission Scheme to CTU

12/8/2014

Transmission Pricing

Power Market
CERC

38

CERC initiatives

Special Features of CERC regulations on short-term open


access

Timelines for concurrence of SLDC in case use of


intra-State system is involved

Provision of deemed concurrence if SLDC does not


decide within above timelines.

SLDC to look at only two aspects:

existence of metering infrastructure, and

availability of surplus transmission capacity in the


State network.

12/8/2014

CERC

39

CERC initiatives

Features of CERC regulations on Grant of Connectivity,


Long-term Access and Medium-term Open Access in interState Transmission

Enabling transmission products of different varieties, standardization of


procedures, defining time lines and ensuring level playing field among

different categories of market players.

Introduced medium-term Open Access to inter-State grid - for a period


ranging from 3 months to 3 years.

New regulatory provisions for seeking connectivity to grid.

Discrimination between

public and private sector generators on

connectivity to grid, abolished.

12/8/2014

CERC

40

CERC initiatives

Regulations on Grant of Regulatory Approval for execution


of

Inter-State

Transmission

Scheme

to

Central

Transmission Utility

This is to facilitate network expansion keeping in view


the

anticipated

transmission

needs

without

the

requirement of prior agreement with the beneficiaries

CERC has granted approval for investment (of about Rs.


58000 Cr. ) to CTU for nine high capacity transmission

corridors.

12/8/2014

CERC

41

CERC initiatives

Regulations on Sharing of Inter State Transmission


Charges and Losses

National transmission tariff framework in line with


vision of tariff policy.

Sensitive to direction, distance and quantum;

Addresses short-comings of existing system like


pan-caking of charges, sharing of charges not
being fully sensitive to distance and direction,
pricing not efficient enough to address emerging
market requirements.

12/8/2014

CERC

42

CERC initiatives

Power Market Regulations

Provide a road map for development of power


market

Define roles of various players in the market


and

phases

of

introduction

of

products/contracts.

12/8/2014

CERC

43

Market Development- Impact


Volume of Open Access transactions
(inter-State transmission)
35.00
7.09

30.00

Volume (BUs)

25.00

2.77

20.00
15.00

26.82

10.00
11.85

14.19

15.02

2005-06

2006-07

20.96

21.92

2007-08

2008-09

5.00
0.00
2004-05

Electricity Transacted by Trading Licensees

12/8/2014

Source: NLDC

2009-10

Electricity Transacted by Power Exchanges

CERC

44

Market Development- Impact


Consumer Open Access through Power Exchange - A Snapshot
Details

12/8/2014

Indian Energy Exchange Ltd

Total Clients

300

Open Access Consumers

160

Nature of Business of these


Consumers

Industrial Consumers- Textiles, Spinning


mills, Auto Ancillary

Geographical Location of these


Consumers

Punjab, Rajasthan , Tamil Nadu, Andhra


Pradesh

% of Daily Cleared Volume by OA


consumers during Oct 2009 Feb
2010

25-30 % ( 5-7 MU) of total daily cleared


volume of Power Exchange

Nature of purchase

Peak , Off Peak

CERC

45

Market Development- Impact

Investment promotion:

12/8/2014

CTU has received 225


applications
from private
developers for Long Term Open Access amounting to
1,62,898 MW
Phase 1: 42,108 MW (LTOA granted to 43 applicants )
Bank guarantee of 875 Cr
given by developers and
BPTA signed
Geographical locations
Pit-head coal Orissa, Chhattisgarh, Jharkhand
Coastal with port facilities - Andhra Pradesh, Tamil
Nadu
Hydel sites Sikkim

CERC

46

Grid discipline - IEGC

IEGC and UI regulations amended to ensure greater grid

discipline .

Operational frequency band tightened from 50.3 Hz


to 49.2 Hz to 50.2 to 49.5 Hz.

This is aimed at ensuring better performance of


generating stations and user appliances.

All users of inter-State grid including distribution


utilities will also now be directly responsible for grid
discipline and load management, in addition to
SLDCs.

12/8/2014

CERC

47

Grid Discipline - Restructured UI mechanism

UI regulations amended to send a message that UI mechanism should not be


used as a trading tool

Underdrawls and over injections beyond the permissible quantities,


disincentivised and priced at lower rates

in order to push more electricity to organized electricity markets and


to further discourage use of UI mechanism for sale of electricity,

Additional UI charge of 40% on the normal UI rate (Rs. 8.73 per unit),
applicable at grid frequency below 49.5 Hz instead of 49.2 Hz

to more effectively curb the tendency of some states to heavily


overdraw

Additional UI rate has been made 100% on overdrawals when grid


frequency is below 49.2 Hz

to put further exemplary deterrent on overdrawls

Improvements in grid frequency profile subsequent to CERC regulation on IEGC


and UI

12/8/2014

CERC

48

Improvement in Grid profile


NEW Grid Fequency Profile April 10- May10
100

90

Frequency Profile in June10 ( 49.5-

80

70

Frequency Profile in May10 ( 49.5-50.2)


Percentage

60

50

40

Frequency Profile in April10 ( 49.5-50.3)


30

20

10

Day

0
1

12/8/2014

11

16

CERC

21

26

49

Grid discipline - constraints

Disconnection almost impossible in meshed system

Centre-State issues

J&K defaulting in UI payments, difficulties in


disconnection.

12/8/2014

CERC

50

Thank You
www.cercind.gov.in

You might also like