Professional Documents
Culture Documents
Road Construction
In the public sector, like the Ministry of Works and
Transport and stateowned companies, with the
necessary personnel and equipment resources, road
construction can be carried out in-house, either as an
end in itself or as part of the infrastructure (together
with water supply, electricity, etc.) for a housing or
other development.
In the private sector the latter is usually the case when
roadwork is carried out in-house with personnel
employed and equipment owned/leased by the
developer.
More often and particularly for major works, specialist
contractors are engaged. The role of technical
personnel engaged by the employer would be for
design and/or administration of the contract and
supervision of the construction.
Road Construction(Contd)
Clear and Grub
Site preparation for construction of the road
comprises clearing and grubbing.
During the clearing phase, trees are felled and
the topsoil, which is mostly organic material
that will decompose, is removed, generally
up to a depth of 300 mm.
Particularly in urban areas clearing may also
involve demolishing and removing man-made
obstructions and debris.
Earth-Moving Equipment
Bulldozer
Loader
Scraper
Dump Truck
Excavator
Road Construction(Contd)
Cut and Fill (Contd)
Excavation involves the use of equipment like
bulldozers and particularly on steeper slopes,
excavators, to get the required road widths and
slopes.
Depending on the extent of any rock excavation
specialist rock-breaking equipment or blasting
(controlled use of explosives) may be necessary.
Slopes should be protected/supported with temporary
shoring, etc. as required to prevent erosion and
landslides during construction.
Excavated material suitable for fill is loaded onto
dump trucks and hauled to the required areas on site.
Road Construction(Contd)
Cut and Fill (Contd)
The mineral soil (free of organic matter)
used for embankment construction
should be built up in layers or lifts each
of which is spread and then compacted.
While a bulldozer is used to spread the fill
it is not a good machine for compacting
because of its low ground pressure
characteristics, so rollers are required.
Typical lift heights should be about 300
mm and should not exceed 500 mm.
Vibrating Roller
Sheepsfoot Roller
Grader
GraGGGrader
Road Construction(Contd)
Compact Subgrade
Proper compaction results in a subgrade that is
sufficiently dense and stable to withstand the
stresses transmitted by the overlying
pavement .
This is particularly important for subgrades under
flexible pavements, however even in the case
of rigid pavements the subgrade must attain
the state of compaction anticipated in the
design procedure.
At least the top 300 mm of embankment and
preferably double this depth should be
compacted to the specified density .
Road Construction(Contd)
Compact Subgrade (Contd)
For cut sections the method of compaction
to achieve the design density at the
appropriate depth will be determined by
the soil type.
Fine-grained soils, especially those of high
plasticity, can be weakened by heavy
compaction equipment.
Particular attention must be given to
sections where the subgrade changes
from cut to fill as there should be no
abrupt change in the degree and
uniformity of compaction.
Road Construction(Contd)
Shape Subgrade
After compaction the surface of the subgrade will
still be fairly rough so at this stage irregularities
will be removed and the subgrade surface is
shaped to the final road cross-section.
This ensures that the pavement will be
constructed to its proper shape and any
moisture that enters into the subgrade can
drain readily.
Once the final shape of the subgrade surface has
been attained, the subgrade, now at formation
level, must be protected prior to the start of
pavement construction.
Road Construction(Contd)
Pavement Construction
Flexible Pavement
Drainage, either temporary or permanent,
should be in place during construction
of the pavement, which requires
effective co-ordination of these works.
Granular subbase material delivered to
the site is spread over the subgrade and
compacted in layers to the specified
thickness and density.
Road Construction(Contd)
Pavement Construction (Contd)
Flexible Pavements (Contd)
Crushed rock aggregate comprising roadbase
material is then spread on the subbase and
also compacted to the required thickness and
density.
Where specified a prime coat (low viscosity
asphaltic concrete) is applied to the roadbase.
In recent years this has been omitted as there is
no real evidence of failure resulting from its
omission.
Road Construction(Contd)
Pavement Construction (Contd)
Flexible Pavements (Contd)
Asphaltic concrete is premixed and delivered to
site at very high temperatures (generally over
120o C) in covered dump trunks.
The asphaltic concrete is discharged directly into
the paver which spreads and provides initial
compaction to the mix which is compacted in
accordance with the specifications.
Where asphaltic concrete comprises a
basecourse and a wearing course a tack coat
(asphalt emulsion) is usually specified to
improve adhesion.
Road Construction(Contd)
Pavement Construction (Contd)
Rigid Pavement
Both subgrade and subbase are prepared as
specified and formwork, dowel bars and
reinforcement are then placed on the
subbase and secured in position.
If dry the subbase is wetted shortly before
placing the concrete to prevent it
absorbing water from the bottom of the
concrete mixture, which can produce
warping stresses and eventual cracking in
the slab.
Road Construction(Contd)
Pavement Construction (Contd)
Rigid Pavement
Ready-mix trucks are used for both mixing and delivery of
the concrete and typically have up to 90 minutes from
initial mixing to delivery.
Concrete is placed and compacted, using small, towed
machines or larger self-powered equipment.
The finished concrete surface is textured (for skid
resistance). Wire brushing is a common example of this.
Curing is the final operation and a curing compound is
often used.
Road Maintenance
Road maintenance comprises routine/preventive
maintenance as well as emergency
maintenance and annual budgets for this
recurrent expenditure must cater for both.
Re-painting road markings is an example of the
former whereas replacing a traffic sign or cable
median barrier after a crash is typical of the
latter.
Scheduled maintenance of roads, including
maintenance of road surface features, has been
described as doing inexpensive repairs on good
roads to keep them good.