OBJECTIVES:
To determine the extent to which the
goods/services to be generated by the
project are needed or demanded; and
To design the appropriate marketing
strategies and plans that will help ensure
that the projects outputs will reach and
be accepted by the target users.
Technical aspect
OBJECTIVES:
The Product
A. Provide detailed description
of the product, in terms of:
1. Physical Properties
Weight, Volume, Density, Shape,
Color, etc.
2. Mechanical Properties
Expansion, Shrinkage, among others
3. Chemical Properties
Chemical
Content
Industrial Input
The
Product
Characteristics
Big
High Yield
PEANUT
Uses
Oven-Roasted
Peanut Butter
Peanut Brittle
2
Thawed bins tipped
over to release ice
blocks.
5
Chilled fish
placed in walk-in
freezers.
1
Chilled
fish
Frozen fish
undergoes
glazing.
Glazed
fish
Frozen
fish
3
Glazed fish to
cold store unit.
4
Fish frozen
at
30oC
2
Cold Store
Process Flow
Project Size/Component
A. Indicate the Volume of
Products to be Produced
Maximum
Minimum
C
A
P
A
C
I
T
Y
Y1
EGG
Y2
EGG
Y3
EGG
Y4
EGG
Production Schedule
A. Description of the Project Scale
of Operation for the Next
Several Years
Ac t ivit ies
5:00
6:00
7:00
8:00
9:00
0.65
0.65
10:00
Time
11:00
12:00
1:00
Weighing and
Sorting of Product
Chilled Fish to Freezer
(assuming 50% or .65 MT of
fish landed per trip are
already chilled)
Fresh Fish are first chilled
(.65 MT to be chilled for an
hour to bring temperature
down to 0 o C and chilled fish
are brought to the freezer)
chilling procedure
freezing
2:00
3:00
4:00
5:00
02
Weeks I and II
03
04
05
06
07
01
SCHEDULE OF TASKS
Week III
02
03
04
05
06
07
01
02
03
Week IV
04
05
ASSUMPTIONS
06
07
YEAR: 01
Raw Material Rqmt.6,300 kilograms
Volume Unloaded per Trip 300 kg except last trip
No. of Trips per Run:
21 Trips / 2 trips a day.
Production 50,331 250ml cans.
END OF RUN
REST DAY
REST DAY
1.
2.
3.
4.
5.
6.
7.
8.
YEAR: 02
END OF RUN
REST DAY
REST DAY
1.
2.
3.
4.
5.
6.
7.
8.
YEAR: 03
REST DAY
REST DAY
REST DAY
1.
2.
3.
4.
5.
6.
7.
8.
Machinery and
Equipment
A. Identify Machinery and Equipment
Needed
B. Types and Uses
C. Specification, Capacity and Efficiency
D. Origin of Machinery (Supplier Local
or Imported)
E. Manner of Transport
F. Installation Plan
G. Balancing of Capacities
Machinery Capacity vs Desired Maximum Output
THIS
NOT THESE
Structural Requirements
1. Building Types and Uses
2. Detailed Engineering Design
3. Structural Lay-Out
Facilities/Utilities
1. Communication
2. Water (Volume Required, Sources)
3. Power/Fuel (Capacity Requirement)
Sources
4. Transportation
5. Alternative Sources
DETERMINE:
1. Area
2. Site, Type and Cost of
Building and Land
3. Bodies of Water
Required
4. Land Improvement such
as, roads, drainages,
Location
1. Factors to consider:
Accessibility to, and Availability of, Raw Material
Sources
Availability of Cheap or Moderately-Priced
Utilities (e.g., power, water and fuel)
Combined cost of Transporting Raw Materials
and Fuel to the Plant Size
Proximity of Distributing Outlets
Availability of Skilled and Unskilled Labors
Suitability (for Agricultural Projects)
3. Location Map
Indicate Major Landmarks or Establishments
Factory
worker
10 kms
60 kms away
away
25
kms
away
30 kms away
PLAN
T
BURGER
HAUS
Technical Manpower
Requirement and
Organization
1. Technical Skills required by the Project
and Number of Skilled Personnel
2. Unskilled Labor Requirements
3. Analysis of Manpower Skills in the
Location of the Project
4. Sources of Skilled and Unskilled Labor
5. Technical Organizational Chart