Professional Documents
Culture Documents
Lecture 3
Essential Formulae in Project Appraisal
1
Other issues
Sunk costs. How should we account for costs
incurred in the past?
The cost of foregone opportunities.
Salvage values and terminal values.
Incorporating taxes into the valuation
decision.
B.
PV
Y
1 i
The NPV of a project equals the difference between the present value
of benefits, PV(B), and the present value of the costs, PV(C):
NPV = PV(B)-PV(C)
Y
PV
1 i ) nthe discount factor
The term 1/(1+i) is (called
n
10
Examples of Discounting
Year
Net Cash Flow
0
-1000
1
200
2
300
3
350
4
1440
200 300
350
1440
NPV 1000
676.25
2
3
4
1.1 (1.1)
(1.1) (1.1)
0
0.1
300 350
1440
743.88
2
3
1.1 (1.1)
(1.1)
350 1440
NPV 1000(1.1) 200(1.1) 300
818.26
1
2
(1.1) (1.1)
2
0.1
11
Financial Calculations
The present value of a single sum is:
PV = FV (1 + r)-t
the present value of a dollar to be received at the end
of period t, using a discount rate of r.
PV
CFt
(1 r )
t
12
Financial Calculations:
Cash Flow Series
A payment series in which cash flows are Equally
sized and Equally timed is known as an annuity.
There are four types:
1. Ordinary annuities; the cash flows occur at the
end of each time period. (Workbook 5.10 and
5.11)
2. Annuities due; the cash flows occur at the start
of each time period.
3. Deferred annuities; the first cash flow occurs
later than one time period into the future.
(Workbook 5.10 and 5.11)
4. Perpetuities; the cash flows begin at the end of
the first period, and go on forever.
13
14
15
16
17
Calculating Financial
Functions With Excel -Worksheet
Errors.
Common worksheet errors
are:
19
Calculating Financial
Functions With Excel -Error
Control.
Methods
to reduce
errors:
20
Alternative Investment
Criteria
1.
2.
3.
4.
21
2.
Alternative Investment
Criteria
First Criterion: Net Present Value (NPV)
Use as a decision criterion to answer
following:
a. When to reject projects?
b. Select project (s) under a budget
constraint?
c. Compare mutually exclusive projects?
d. How to choose between highly profitable
mutually exclusive projects with different
lengths of life?
23
A
PV
t
(
1
i
)
t 1
or PV = A x
Where
n
i
n
i is the annuity factor,
n
1
(
1
i
)
ain
i
n
i , which equals the present value of an annuity of
The term
$/Tk. 1 per year for n years when the interest rate is i
percent, is called the annuity factor.
27
Perpetuities
2/2
Present value of a perpetuity
PV = A/i, if i>0
Present value of an annuity that grows or declines at
a constant rate
PV(B) = [B1/ (1+g)]x ai0n , i0 = 1-g/1+g
if i>g
If g is small, B1/1+g is approximately equal to B1,
and i0 = 1-g
Present value of benefits (or costs) that grow or
decline at a constant rate in perpetuity
PV(B) = B1/ (1-g), if i>g
28
The formula:
NB
NPV
t 0
(1 i )t
Assumes that the net benefits are constant or grow at a constant rate.
Not a very realistic assumption.
For most long lived projects, select a relatively short discounting
period (useful life of the project) and include a terminal value to
k
reflect all subsequent benefits and costs.
NB
Where T(k) denotes the terminal value.
NPV
t 0
(1 i )
T (k )
29
Simple Projections
Salvage or Liquidation Value
Depreciated Value, economic depreciation
Percentage of Initial Constructions Cost
30
NPV
EANB n
ai
Where
ain
n
1
(
1
i
)
ain
i
31
Constant currency
im
r
1 mthe real interest rate is approximately equals the
If m is small,
Nominal interest rate minus the expected rate of inflation:
r = i-m
32
Alternative Investment
Criteria: Benefit Cost Ratio
33
Basic Rule
If benefit-cost ratio (R) >1, then the project
should be undertaken.
Problems?
NPVB
RB = 24/20 = 1.2
= $4.0 M
35
36
Pay-Out or Pay-Back
Period
Projects
with
shortest
payback
period
are
37
Alternative Investment
Internal
CriteriaRate of Return (IRR)
Bt Ct
0
t
i 0 (1 k )
t
38
(b)
(c)
39
Bt - C t
+300
Time
-100
-200
Solution 1: K = 100%;
Solution 2: K = 0%;
NPV= -100+300/(1+0)+-200/(1+0)2 = 0
40
...
...
+600
+4,000
+600
+4,000
+600
+4,000
+600
+4,000
+600
+4,000
+600
+4,000
Project A -2,000
Project B -20,000
0
A
0
B
43
1000
1200
800
3600
-8000
3600
-6400
10%
Compares Project A and Project B ?
Project B
IRR B
1000
1200
800
-2%
1000
1200
800
3600
-4800
-16%
-1000
1200
800
3600
-4800
4%
Project D is worse than C, yet IRR D > IRR C
Project E
IRR E
-1325
1200
800
3600
-4800
20%
Project E is worse than D, yet IRR E > IRR D
44
45
46
Year
Project A
Project B
Project C
-80,000
-80,000
-80,000
25,000
80,000
25,000
10,000
25,000
10,000
25,000
10,000
25,000
10,000
140,000
Total benefits
45,000
40,000
60,000
NPV (i=2%)
37,838
35,762
46,802
NPV (i=10%)
14,770
21,544
6,929
47
48
CF1
1
CF2
2
...
CFN
1 r 1 r
1 r
According to the NPV rule:
49
0?
Technical notes
50
CF1
1
CF2
2
...
CFN
1 IRR 1 IRR
1 IRR
According to the IRR rule:
51
52
53
54
Summing up
55
In this example:
Both A and B are worthwhile by both NPV and IRR
criteria
If discount rate = 6%
A is preferred to B by NPV rule
56
B preferred to A by IRR rule
NPV CF0
{
Cost of
project
CF1
1
CF2
2
...
CFN
N
11 4 r4 4 4 1 44r2 4 4 4 41 4r 43
Value today of future
project cash flows
1 4 4 4 4 4 4 42 4 4 4 4 4 4 43
Incremental wealth:
How much does the project's
net value add to your wealth?
58