You are on page 1of 118

HEAT

TREATMENT
TRAINING MANUAL
MAY-2001

(REV.-0)

HEAT TREATMENT MANUAL


This Manual is compiled by
Mr K S Rao (QA),
Mr S P Ghiya (Inspection ) and
Mr N M Bodalia (M FS)
Under the guidance of
Mr P D Lohidakshan (Weld Engg & Prod Engg )
2

INDEX
TOPIC

PAGE NO.

1 . INTRODUCTION ON HEAT TREATMENT

4- 24

2 . FURNACE PARTS AND ATTACHMENTS

25- 37

3. STD. OPERATING PROCEDURES(HFS)

38- 47

4 . STD. OPERATING PROCEDURES(PFS)

48- 56

5 . STD. OPERATING PROCEDURES(MFS)

57-69

6 . STANDARD PRACTICES FOR LSR

70-74

7 . GOOD ENGINEERING PRACTICE

75-88

8 . CODE EXTRACT(REFERENCE ONLY) 89- 101


9 . ANNEXURES

102- 118
3

General
Only qualified supervisors and operators including
LSR operators shall be authorised to operate furnace.
A list of qualified personnel shall be prepared by QA
and published periodically.
Thjs manual is prepared on the basis of experience
and feedback, taken from various personnel.
This manual is for reference only.

HEAT TREATMENT

WHAT IS HEAT TREATMENT ?


WHY IS IT REQUIRED ?
TYPES OF HEAT TREATMENT
HEAT TREATMENT AT HZW

WHAT IS HEAT TREATMENT


MATERIALS TREATED BY
APPLICATION OF HEAT NORMALLY
DONE IN SOLID STATE
VARIOUS SOURCES OF HEAT
PARAMETERS ARE HEATING
RATE,SOAKING TEMP,SOAKING
TIME,COOLING RATE AND COOLING
MEDIA
6

WHY IS IT REQUIRED ?
TO ENHANCE MATERIAL PROPERTIES / EASE IN
FABRICATION BY CHANGING
Strength,Improve corrosion resistance
Toughness/Ductility
Hardness,Dimensional stability etc
Remove diffusible hydrogen to avoid hydrogen
cracking
CARRIED OUT IN FABRICATION INDUSTRIES
,STEEL PLANTS, FOUNDRY, FORGING SHOPS etc..
7

MATERIALS HEAT TREATED


METALS & ALLOYS
SINGLE PHASE
MULTIPHASE

ALLOYS
Single Phase : Copper Nickel
Multiphase : Steels-LAS,QT

METALS (Single phase )


Titanium,Al,Ni,Cu etc..
8

MATERIALS HEAT TREATED


CRITERIA
COLD WORKED to NORMAL
All materials

UNEQUILIBRIUM PHASES to
EQUILIBRIUM:(Stabilise Microstructure &
Phases)
Stainless Steels ,Maraging Steels

STRESSED to UNSTRESED
All Materials

CREATION OF UNEQUILIBRIUM
CONDITIONS
Steels

MATERIALS HEAT TREATED


MATERIALS CATEGORY

C-Mn , C-Mo , Cr-Mo , Ni -Steels, QT


Stainless Steels-Austanitic.Martensitic
Steels enhanced by Heat Treatments
Non Ferrous Materials; Titanium alloys,
Aluminum alloys

10

TYPES OF HEAT TREATMENT

NORMALIZING
ANNEALING
STRESS RELIEVING
SOLUTION ANNEALING-Mainly SS
HARDENING
TEMPERING
AGING
11

IRON CARBON DIAGRAM

12

Iron Carbon Diagram


Portion related to Heat Treatment

13

NORMALIZING
The steel is heated to 40 C above the upper critical
temperature(910 c) followed by cooling in the still
air.
Normalizing is done to achieve the following :
To get Uniform structure and reduce chemical
gradients
To change Mechanical properties,
UTS,YS
Hardness
Impact properties

To refine the grains

14

ANNEALING
In this process, the steel is heated from 10 to
50C
above
the
upper
critical
temperature(910c) and held for the desired
length of time; followed by very slow
cooling in the furnace
Annealing is done to achieve following :

to soften the steel and improve ductility


to relieve internal stresses caused by previous
treatment
15

SOLUTION ANNEALING
In Stainless steels , it is heated to 1050C or
above ,and held for the desired time; followed by
quenching/blowing the air(cooling to room
temperature within few minutes).
Solution annealing is done on stainless steel and
non ferrous alloys to achieve following:
To soften the material
To dissolve carbide precipitation formed at grain
boundaries during manufacturing process
16
To improve Corrosion Resistance

AGING
The Material is heated to a certain temperature,
and held for the desired time; followed by
normally for precipitation hardened alloys or
cooling in air
Aging is done on materials susceptible for
aging characteristics : Maraging Steels
Normally increase in strength
To Improve Toughness/Ductile-brittle transition
temp.
17

AGING
Maraging Steels
M250

Temperature : 485 C
Normally 3 Hrs 15 mts
Heating Rate : 200 C per hr per inch
Cooling Rate : Cool in Air / Quench in water
18

STRESS RELIEVING
The steel is heated to a temperature below or close to the
lower critical point, followed by desired rate of cooling and
there is no change in grain structure.
Stress relieving is done to achieve following :
To reduce Internal Stresses (residual Stresses)
To soften the steel partially
To improve ductile-brrittle transition temp. and equalize
impact values

19

STRESS RELIEVING
C-Mn , C-Mo , Cr-Mo (< 2% Cr)
C - Mn Steels , C - Mo Steels,Cr-Mo Steels
SA 515Gr 70 , SA204GrA, SA387GR11CL1

Temperature : 593 C Min


Normally 600 - 640 C,650-690 C

Time : 15 minutes min


Time : 1 hr / inch

Heating Rate : 200 C per hr per inch


Cooling Rate : 260 C per hr per inch
20

STRESS RELIEVING
Cr-Mo Steels
Cr - Mo Steels (Cr >2%)
SA 335P22 ,SA335P5

Temperature : 676 C Min


Normally 680 - 700 C 2.25Cr

704 - 720 C 5 Cr

Time : 15 mts min


Time : 1 hr / inch

Heating Rate : 200 C per hr per inch


Cooling Rate : 260 C per hr per inch

21

STRESS RELIEVING
Ni -Steels
Nickel Steels : 1,2,3% Ni
SA 203 GrA ,D

Temperature : 593 C Min


Normally 600 - 640 C,650-690 C

Time : 60 mts min


Time : 1 hr / inch

Heating Rate : 200 C per hr per inch


Cooling Rate : 260 C per hr per inch
22

STRESS RELIEVING
Steels enhanced by Heat Treatments
Q&T Steels :
9.5% Ni Steels , SA 517 Gr E

Temperature : 538 C Typ


Normally < 600 C

Time : Minimum 15 minutes to 2 Hr


Time : 1 hr / inch

Heating Rate : 200 C per hr per inch


Cooling Rate : 260 C per hr per inch
23

FURNACE PARTS AND


THEIR ATTACHMENTS

24

LAYOUT OF A TYPICAL
FURNACE
(Electrical or Gas fired )
FURNACE
THERMOCOUPLE
COMPENSATING
CABLE

JOB

RECORDER

CONTROLLING BURNER

P.I.D.

25

THERMOCOUPLES
PRINCIPLE OF A THERMOCOUPLE
THERMOCOUPLE MATERIALS
TYPES OF THERMOCOUPLES BEING
USED IN HZW
26

PRINCIPLE OF THERMOCOUPLE
The basic principle of thermoelectric
thermometry is that a thermocouple develops
an emf which is a function of the difference in
temperature of its measuring junction &
reference junction. If the temperature of
reference junction is known, the temperature
of the measuring junction can be determined
by measuring the emf generated in the circuit.
27

THERMOCOUPLE MATERIAL
REQUIREMENT
1. High coefficient of thermal emf.
2. Continuously increasing relation of emf to temperature over
a long range.
3. Freedom from phase changes or other phenomenon giving
rise to discontinuity in temperature emf relationships.
4. Resistance to oxidation, corrosion and contamination.
5. Homogeneity and reproducibility to fit an establish
temperature & emf relationship.
SPEED OF RESPONSE MAY BE IMPROVED AND
RADIATION & CONDUCTION ERRORS MAY BE REDUCED
28
BY THE USE OF SMALL DIAMETER THERMOCOUPLES.

TYPES OF THERMOCOUPLE
BEING USED IN HZW
K type :
Material
Nickel based
Properties :

Chromel
( 10 %Cr )

Alumel

+ ( 2 % Al )

Non-Magnetic +

Magnetic

In this type of thermocouple, the wires are


joined at one end only to form a point-type
temperature sensor. Instrumentation converts
the millivolt signal to related temperature. 29

TYPES OF THERMOCOUPLE
BEING USED IN HZW contd...
K type :
Dia :
Insulation
coated

2.5 mm
Bare(ceramic)

0. 7 mm
Refractory

Attachment

Mech

Capacitor

Usability

Reusable

Disposable

Location

PIT F/c

except PIT F/c

Color

30

Red & Yellow

CONSTRUCTION OF A
K TYPE THERMOCOUPLE
pid
Blue Color

White Color

Blue Color

recorder

+Ve
-Ve

Red Color

White/yellow

Welded
junction

+Ve
-Ve

Compensating
cable

Accuracy : 0.75%

White/yellow

Red Color

White Color

Thermocouple
wire

31

S TYPE THERMOCOUPLE
Accuracy : 0.25 %
S TYPE THERMOCOUPLE ARE THE STANDARD
THERMOCOUPLES.

IT IS USED FOR CALIBRATING K Type


THERMOCOUPLES.

MATERIAL OF CONSTRUCTION
90% PLATINUM + 10% RHODIUM
PLATINUM

OXIDATION RESISTANCE , SO MORE LIFE .


32

ISSUE METHODOLOGY

For DISPOSAL TYPE

Users will send their requirement of thermocouple

through Consumable slip ( mentioning HTR No ) to


QA
QA shall issue the same .
QA shall issue identification sticker duly attached
Users shall ensure availability of identification sticker
on unused wire .
See Annexure-12 for further details
33

COMPENSATING CABLE
COMPENSATING CABLE IS DEFINED AS A PAIR OF WIRES
HAVING SUCH EMF TEMPERATURE CHARACTERISTICS
RELATED TO THE THERMOCOUPLE WITH WHICH THE
WIRES ARE INTENDED TO BE USED, THAT WHEN
PROPERLY CONNECTED TO THERMOCOUPLE THE
EFFECTIVE REFERENCE JUNCTION IS IN EFFECT
TRANSFERRED TO THE OTHER END OF THE WIRES.
MATERIAL ==> +ve COPPER ( white )
-ve COPPER NICKEL (blue ) for K TYPE .

See Annexure-9 (Annexure Page 1-4) for further details


34

P.I.D.
PID = PROPORTIONAL INTEGRAL DERIVATIVE

PID FUNCTIONS BOTH AS PROGRAMMER AND


CONTROLLER
PID CONTROLLER CAN BE ZONE WISE
PROGRAMME IS MADE IN SEGMENTS AS PER
DIFFERENT STAGES OF HEAT TREATMENT
DIGITAL DISPLAY IS AVAILABLE FOR PROGRAMME
TEMPERATURE AND FURNACE TEMEPERATURE
TYPICAL OR REPETITIVE HEAT TREATMENT CYCLE
CAN BE STORED IN PID(PROGRAMMER)

35

RECORDER
TYPES OF RECORDER
PAPERLESS --

WITH COLOUR DISPLAY SCREEN ,HARD DISC AND FLOPPY DRIVE.


NOT USED IN HZW.

WITH PAPER -- CURRENTLY BEING USED IN HZW.


24 CHANNEL -- CURRENTLY BEING USED IN PFS( CHINO MAKE-- model no.I003
/Graph ET 001).

12 CHANNEL -- CURRENTLY BEING USED IN MFS1 AND HFS1


( CHINO MAKE -- model no. EH100 / Graph ET 201).
COMPENSATING CABLES ARE CONNECTED BEHIND THE RECORDER SCREEN IN
CHANNELS.
X-AXIS IS FOR TEMPERATURE (RANGE = 0 TO 1200C)
THE SCALE ON X-AXIS IS NON-LINEAR.
Y-AXIS IS FOR GRAPH SPEED.
VARIOUS SPEED OF GRAPHS ARE 12.5, 25, 50, 100 MM / HOUR
WE GENERALLY KEEP 25 MM / HOUR.

36

GRAPH PAPER
GRAPH PAPERS ARE USED FOR PLOTTING THE
FURNACE TEMPERATURE VIA THERMOCOUPLE.
THEY ARE FITTED ON THE RECORDER.
GRAPH PAPER RECOMMENDED ON RECORDER ONLY
TO BE USED
GRAPH PAPER FOR MFS1 AND HFS1 FURNACE
==> ET 201 CHINO MAKE, JAPAN
GRAPH PAPER FOR PFS FURNACE
==> ET 001 CHINO MAKE, JAPAN
THE LENGTH OF ONE BUNDLE OF GRAPH PAPER IS
GENERALLY 2000 MM.
DOTTING TYPE RECORDER INK (CHINO MAKE, JAPAN)
IS USED IN RECORDER FOR PLOTTING OF GRAPH.
USUALLY , 6 COLOURS ARE FILLED FOR PLOTTING.
37
SEE ANNEXURE-10 FOR FURTHER DETAILS

STANDARD OPERATING
PROCEDURE FOR HFS-1
FURNACE

38

( ZONE-2 )

1640

( ZONE-4 )

( ZONE-6 )

( ZONE-8 )

BURNER

1650

7900
(BOGIE
WIDTH
)

1650
3575
( ZONE-1 )

3575
( ZONE-3 )

14300.

3575
( ZONE-5 )

3575
( ZONE-7 )

HFS-I FURNACE SKETCH

39

9000

1. PROJECT NO:
2. SECTION NO :
9500

3. CHARGE NO :
4. H. T. REQ. NO :

BURNER
1195

7900 BOGGIE WIDTH

1050

8700

HFS-I FURNACE SKETCH

40

STANDARD OPERATING PROCEDURE FOR HFS-1


FURNACE
1.

Receive the job as per HT request.

2.

Receive heat treatment request duly approved by


metallurgy engineer.

3.

Ensure that Insp. Clearance is available prior


to loading for job.

4.

Load the supporting arrangement as per the attached


annexure -3

5.

Ensure the spider arrangement as per attached


annexure - 5

6.

Fix the thermocouples at locations shown in furnace


charge.

7.

Check the entire job as per check list (annex.-I).


41

STANDARD OPERATING PROCEDURE FOR HFS-1


FURNACE
9.

Move the bogie inside the furnace

10.

Pass the thermocouples through ports and


connect it with compensating cables

11.

Set the program as per heat treatment request.


Secure it and then run it in fast mode as check.
Bring it back to the initial segment and hold.

12.

Insert heat treatment chart in recorder and adjust


the speed of the graph.

13.

Clear inspection of job and get the signature of


inspector on graph paper for firing the furnace.

14.

Check LPG level, pressure and temperature in the


42
storage tanks and note down in logbook.

STANDARD OPERATING PROCEDURE FOR HFS-1


FURNACE
15.

Switch on the power supply

16.

Close the bogie door

17.

Follow the procedure for startup of furnace in zone-I

18.

Start the blower from the field push button station


provided

19.

Give power supply to the ignition panel

20

When the system healthy contact comes from the


instrument panel, the lamp for the system healthy
signal is on. This indicates that the combustion air
pressure and gas pressure are within the specified
limits

21.

Now the firing on the cycle can start.

43

STANDARD OPERATING PROCEDURE FOR HFS-1


FURNACE
22.

Open the pilot and main gas valves

23.

Press start cycle button on doing so the cycle starts


and purging start indicator lamp is on.

24.

After 3 minutes ( time adjusted through timer ) the


purging is completed and ignition start lamp is ON
At the same time the purging start lamp gets OFF.

25.

After 10 seconds the ignition start lamp gets OFF


By this time the pilot burner should have been fired
and the pilot flame is established.

26.

Flame healthy signal LED gets on which is provided


on the flame sensor relay. This can be viewed through
the glass window provided in the ignition panel.

44

STANDARD OPERATING PROCEDURE FOR HFS-1


FURNACE
27.

Due to certain length of pipe between the burner and


solenoid valves, which may contain air, the burner
may not light up in the first attempt. In that case,
repeat the above mentioned procedure.

28.

Once the main flame is established, the control is


passed on to the temperature controller.

29.
For startup of furnace in other zones, follow the
same steps no 16 to 27 mentioned above.
30.

After all zones are started, start recording time and


temperature from recorder every 30 minutes in the
logbook.

31.

Conduct spot checks for heat treatment every 4hours


45
and fill the spot check format.

STANDARD OPERATING PROCEDURE FOR HFS-1


FURNACE
32.

Monitor the heat treatment process and graph till


the completion to ensure that it is as per program
and heat treatment request.

33.

After heat treatment cycle is completed, shut off


all LPG supply valves and let furnace run with
blowers on for 15 minutes.

34.

Open the bogie door. Disconnect thermocouples


from compensating cable.

35.

Submit the graph and duly filled spot check formats


to inspection for approval of heat treatment.
46

STANDARD OPERATING PROCEDURE FOR HFS-1


FURNACE
36.

Retrieve the thermocouples from the ports and the


bogie out of the furnace.

37.

Allow the job to reach room temperature.

38.

Remove the thermocouples from the job carefully


without damaging the junction of thermocouples and
without making impression on parent material of job.

39.

Unload the job from the bogie and move the bogie
inside the furnace.

40.

Close the furnace. Shut off the main power supply.

47

STANDARD OPERATING
PROCEDURE FOR PFS
FURNACE

48

125T Bogie hearth furnace -- PFS

49

PFS FURNACE SKETCH


5600

5500

2650

BURMER

BOGGIE WIDTH

1460

1050

1235

4100

50

STANDARD OPERATING PROCEDURE FOR PFS


FURNACE
1.

Receive the job as per HT request.

2.

Receive heat treatment request duly approved by


metallurgy engineer.

3.

Ensure that Insp. clearance is available prior to


loading for job.

4.

Load the job on the bogie as per the heat treatment


furnace request.

5.

Ensure the supporting arrangement as per the


attached annexure-I.

6.

Ensure the spider arrangement as per annexure- II.

7.

Fix the thermocouples at locations shown in furnace


charge.
51

STANDARD OPERATING PROCEDURE FOR PFS


FURNACE
8.

Check the entire job as per check list attached as


annexure-III

9.

Move the bogie inside the furnace.

10.

Pass the thermocouples through ports and


connect it with compensating cables.

11.

Insert heat treatment chart in recorder and adjust


the speed of the graph.

12.

Clear inspection of job and get the signature


of inspector on graph paper for firing the furnace.

13.

Check LPG level, pressure and temperature in


52
the storage tanks and note down in logbook.

STANDARD OPERATING PROCEDURE FOR PFS


FURNACE
14.

Switch on the power supply.

15.

Close the bogie door.

16.

Switch on ID blower first and then the air blower


and maintain pressure at about 800mm WG by
slowly opening the suction valve.

17.

Ensure that pressure of LPG from yard to inlet


of pressure regulator is always less than 20psi
(1.5kg/CM2).

18.

Open the inlet valve to the regulator and open


the outlet valve.

19.

If pressure exceeds 1600 mm WG , isolate the


pressure by lifting the handle of safety shut off
53
valve.

STANDARD OPERATING PROCEDURE FOR PFS


FURNACE
20.

Immediately start lighting the pilot burners and adjust


the flame with the air valve .

21.

Open the isolating valve for pressure gauge and


adjust the pressure regulator by turning the screw
provided in the stem so that the pressure is
maintained at about 1000mm WG.

22.

Light up alternate main burners and adjust the flame


lengths uniformly.

23.

Lock the doors by pneumatic locking.

24.

After all zones start, record time and temperature


from recorder every 30 minutes in the logbook.
54

STANDARD OPERATING PROCEDURE FOR PFS


FURNACE
25.

Conduct spot checks for heat treatment every


4 hours and fill the spot check format. Monitor the
heat

treatment

process

and

graph

per

heat

treatment request.
26.

After the heat treatment cycle is completed, shut off


all LPG valves and let furnace run with blowers on
for 15 minutes.

27.

Open the bogie door. Disconnect thermocouples


from compensating cables.

28.

Submit the graph and duly filled spot check formats


to inspection for approval of heat treatment.

55

STANDARD OPERATING PROCEDURE FOR PFS


FURNACE
29.

Retrieve the thermocouples from the ports and move


the bogie out of the furnace.

30.

Allow the job to reach room temperature.

31.

Remove the thermocouples from job carefully and


without marking impression on parent material of
job.

32.

Unload the job from bogie and move the bogie

inside the furnace.


33.

Close the furnace. Shut off the power supply.

56

STANDARD OPERATING
PROCEDURE FOR PIT
FURNACE IN MFS-I

57

FIRE BRICK

CERMIC
BLANKET
OUTER
SHELL

GROUND LEVEL
CERMIC FIBER
SLABER BLOCK

HEATING
ELEMENT
BAFFLE

INSULATING
CASTABLE
ROOF
CERAMIC
BLANKET

3700 1/D OF BAFFLE

4150 ( REFRACTORY I/S )

BLOWER

4020

125

250

TROLLEY
STRUCTURE
1380

PIT FURNACE SKETCH

4961

1000

58

STANDARD OPERATING PROCEDURE


FOR PIT FURNACE
1.

Receive heat treatment request duly authorized


by metallurgy engineer.

2.

Receive the job for heat treatment with


inspection clearance.

3.

Put the job either on support or on heat


treatment fixture inside the furnace.

4.

Ensure that equal clearance is available on all


sides between job and baffle.

5.

Ensure that the furnace is calibrated.

6.

Connect thermocouples with compensating


cable to PID.

59

STANDARD OPERATING PROCEDURE


FOR PIT FURNACE
7.

Set the program in the programmer as per heat


treatment request.

8.

Take a trial run of program to ensure the accuracy.

9.

Calibrate all 5 PIDs prior to starting the furnace.

10.

Insert the graph inside the recorder and take the


signature of inspector on the graph paper.

11.

Close the furnace door.

12.

Start the furnace by giving power supply ON


60

STANDARD OPERATING PROCEDURE


FOR PIT FURNACE
13.

Start recording the time and temperature in the


logbook every 30 minutes.

14.

Ensure that the cycle is functioning as per program.

15.

After the heat treatment is over, open the furnace


cover.

16.

If the job calls for water quenching, lift the job and
dip it in quench tank.

17.

It the job calls for air cooling in still air, lift the job
and put it outside on supports in open air.
61

STANDARD OPERATING PROCEDURE


FOR PIT FURNACE
18.

It the job doesnt call for anything above, allow the


job to cool down in furnace.

19.

Keep the job outside after removing from furnace.

20.

Submit the heat treatment graph to inspection for


approval of heat treatment cycle.

21.

Close the furnace cover after the furnace is cooled


down to room temperature.
62

PROCEDURE FOR EMPTY FURNACE


CALIBRATION
Calibration of PIDS ( indicator & controller )
1.

Connect the millivolt source to the temperature


indicator or controller by a compensating
cable. Care should be taken to clean the wires and
terminals thoroughly before connections are
made.
2.

The millivolt output for various temperature


ranging from 00C to 10000C in steps of 500C is fed
to the indicator / controller.

3.

After the millivolt value / temperature reading


displayed is steady, the reading of
indicator/controller shall be noted.

63

PROCEDURE FOR EMPTY FURNACE


CALIBRATION
4.

If the error in the indicated readings is more than


the specified accuracy ( +/- 10C ), then correction
to be carried out for the indicator / controller and
points 1 to 4 shall be repeated till the specified
accuracy is obtained is obtained.

Calibration of recorder
1.

Connect the millivolt source to the recorder by a


compensating cable. Care should be taken to
clean the wires and terminals thoroughly before
the connections are made.
64

PROCEDURE FOR EMPTY FURNACE


CALIBRATION
2.

The millivolt output for various temperature


ranging from 400 C to 10000C is fed to the
recorder and is allowed to plot on a graph.

3.

The graph thus obtained is reviewed for time


and temperature values. These values should
meet the accuracy requirements.

4.

If there is error in the values plotted on the


graph, then correction to be carried out for
the recorder and points 1 to 4 shall be
repeated till the specified accuracy is
obtained.

65

PROCEDURE FOR EMPTY FURNACE


CALIBRATION
EQUIPMENT REQUIRED

ACCURACY

1.

20 Nos. big K-type thermocouples

+/- 0.25%

2.

10 Nos. small K-type thermocouples

+/- 0.25%

3.

Millivolt source (wahl unit )


( 1 micro volt at 1000 micro volts )

4.

Heat treatment fixture.

5.

Temperature indicators (PID)

6.

Recorder

+/- 10C

+/- on temperature scale.


+/- minutes on time scale.
66

PIT FURNACE CALIBRATION PROCEDURE


1.

Ensure that the PIDs are calibrated as mentioned above.

2.

Ensure that the recorder is calibrated as mentioned


above.

3.

Ensure that all the thermocouples used are calibrated.

4.

Ensure that the thermocouples are attached to the heat


treatment fixture as shown in sketch-I.

5.

Place the heat treatment fixture inside the furnace with


thermocouples in position.

6.

Close the furnace lid. Start the furnace and the recorder.
67

PIT FURNACE CALIBRATION PROCEDURE


7.

Set the temperature of controller to 4000C.

8.

After reaching the set temperature, it is allowed to


stabilize for half an hour.

9.

Measure and record the temperature indicated by


each of the 20 thermocouples. The temperature is to
be read through WAHL UNIT.

10.

Three sets of readings are to be taken for each


thermocouples at an interval of 10 minutes.

11.

Also record the readings indicated by each of the


thermocouples at an interval of 10 minutes.
68

PIT FURNACE CALIBRATION PROCEDURE


12.

The temperature is then raised in steps of 50 C up to


10000C. ( I. e. 4000C, 4500C, .., 9500C, 10000C. ) The
measured temperature is stabilized for 30 minutes.
PID reading are also to be recorded along with this.

13.

The allowed temperature variation with respect to the


set temperature is +/- 50C up to 8000C and +/- 100C
above 8000C.

14.

This is allowed to plot on the graph and thus


obtained for time and temperature values.

15.

Calibration of furnace is valid for 1 year.

69

STANDARD OPERATING
PRACTICES FOR LOCAL
STRESS RELIEVING

70

LOCAL STRESS RELIEVING


WHY

Local SR to be done only when furnace SR not feasible


When only certain components to be PWHT

HOW

Can be done by Electrical / Gas / diesel / Induction etc..

DETAILS ON ENSURING PWHT TEMP. IN WELDMENT AREA

Soaking band(SB) = Widest weld width x+ t or 2 inches


whichever is less from edge of weld
Heating band width (HB)
Induction stress level
Through thickness criteria
SB + 4 rt where r = Inside radius, t = thickness
Insulation band width (IB)
Axial gradient
71
HB + 4 rt

LSR -BAND WIDTH


Soak band
X

Weld width X +
lesser of 1T or 2

Inside radius

Heating band
Insulation band

72

LOCAL STRESS RELIEVING SET UP


1. Provide multitonne roller on one end of vessel during
LSR ofcircular seam when job is horizontal.
2. If both ends are open during LSR, provide insulation
from inside. If not possible , prevent airflow so that
temperature on inside surface do not drop down.
3. Spider/prop shall be provided in such a way that upper
portion of spider / prop is not welded with inside
surface to allow contraction/expansion of shell surface.
4. Spider/prop shall be between 200- 500mm from heating
zone.
5. Temporary attachments, provided for holding insulation,
shall be within soak band only.
6. Minimum two thermocouples shall be provided from
inside, when accessible.
73

LOCAL STRESS RELIEVING


SB+HB+IB

LSR of C/S

Spider or
prop

No Welding at top
Multitonne roller

200 to 500mm from heating band

74

GOOD ENGG. PRACTICES


FOR FURNACE CHARGES
&LSR

75

SUPPORTING ARRANGEMENTS
1.

Heat Treatment request shall be as per Annexure-7


and Annexure-8.

2.

Minimum distance between floor of the furnace


and lower most part of the job shall be 300mm.

3.

The distance between burner flame and saddle


support as well as furnace wall and job
shall be 600mm.

4.

Minimum 90 degree saddle to be used, however


120 degree saddle is desirable.
76

SUPPORTING ARRANGEMENTS

burner

600mm
90

450mm

600mm

300mm(point no:2)

5. Saddle shall be arranged in such away that open


end of the vessel is maximum 450mm from saddle
support.
6. Saddle shall be located as close to spiders
(temporarily arranged to control deformation) as
possible.
77

SUPPORTING ARRANGEMENTS

7. Spiders shall be provided as per annexure-5


8

Saddle supports shall be selected as per annexure.-3

9. Spiders or vertical prop shall be provided at open


ends, center and below man way/nozzles above 24
10. Avoid gap between saddle support and job surface

78

SUPPORTING ARRANGEMENTS
Zero gap
Supporting
arrangement

11. Locking/clamping of job, restricting the movement


(axial/lateral) during heat treatment shall be avoided.
12. All long nozzles projecting outside job surface shall
be supported.

79

SUPPORTING ARRANGEMENTS
13. Checklist shall be prepared and attached with HT
request before furnace is fired as per Ann-1
14. Spot check report shall be filled by supervisor as
per Annexure-2 during job is being heat treated.
15. Moonplate support and welding inside surface
prior to release for Heat treatment as per
Annexure-4
16. General idea about thermocouple locations and its
attachments is as per Annexure-6
80

GENERAL
1. Blocking the flame of the burner is not desirable
2. Burner shall have blue flame and not yellow
3. Flame shall not directly impinge on job
4. All burners shall be fired at a time
5. Keep all job nozzles open during heat treatment
6. Above 24 nozzles / manways shall be located
towards bottom
81

GENERAL

Gasket machined surface

Temp. support
Furnace floor

7. Deoxidization agent shall be applied on all


machined and gasket faces
8. Gasket / machined face of loose assemblies
shall not be touching any object.
82

THERMOCOUPLES
1. All the thermocouples shall be
tagged with aluminum
sheet
and identification hard punched
on it.
(For PIT furnace only)

2. Minimum two thermocouples to


be attached for any charge.

83

THERMOCOUPLES

3. Minimum 8 thermocouples to be used for a charge in


HFS- I furnace if the job occupies all 8 zones
4. Maximum distance between two thermocouples for a
sample job is as shown in annexure- 6
5. PTC shall have separate thermocouple

84

THERMOCOUPLES
ATTACHMENTS
1. Use only TAU-90 capacitor Discharge Welding
machine for thermocouple connection
2.

Use WPS:999-154 R0 for attachment of


thermocouple for cs/alloy steel material

3.

Only trained person by welding engineering shall


attach thermocouple

4.

A list of qualified person shall be by Welding


Eng.
85

THERMOCOUPLES
ATTACHMENTS
5.

Clean surface prior to attachment.

6.
7.

Two wire of thermocouple shall be attached one


after another.
Gap between two wire of a thermocouple shall be

8.

max. 3.0mm
Only calibrated thermocouple shall be used.
Calibration shall be by QA.

9.

After PWHT, thermocouple area shall be ground


and DP shall be carried out.

10. For further details see Annexure-11 & 13-(page861&2)

THERMOCOUPLES
ATTACHMENT UNIT

87

SPECIAL NOTE
IF THE TEMPERATURE OF HEAT TREATMENT
EXCEEEDS

650-DEGREE

CENTIGRADE,

THE

MATERIAL AND SIZE OF SPIDERS AND SUPPORTS


TO BE DECIDED BY PLANNING AND APPROVED BY
DESIGN.

88

CODE EXTRACTS
FURNACE PWHT
LSR

89

REQUIREMENT OF HEAT TREATMENT


AS PER ASME-SEC VIII Div.-1
SERVICE CONDITION

(UW-2)

MATERIAL

(UG-85, UW-40,UCS-56,UAT-80,UHA-32,UNF-79)

THICKNESS

(UG-85, UW-40,UCS-56,UAT-80,UHA-32,UNF-79)

LOW TEMERATURE
OPERATION
COLD WORKING

(UCS-68)
(UG-79)

CUSTOMER SPEC.

90

CODE EXTRACT FOR HEAT TREATMENT


( 1 ) The soak band shall contain the weld, heat
affected zone and a portion of base metal adjacent to the
weld being heat treated. The minimum width of this
volume is the widest width of weld plus 1T or 2 inches,
whichever is less, on each side or end of the weld. The
term T is the nominal thickness.
( 2 )
The operation of postweld heat treatment shall
be performed either by heating the vessel as a whole in
an enclosed furnace or heating the vessel in more than
one heat in a furnace, provided the overlap of the heated
sections of the vessel is at least 5 feet ( 1.5m). When this
procedure is used, the portion outside of the furnace
shall be shielded so that the temperature gradient is not
harmful. The cross section where the vessel projects
from the furnace shall not intersect a nozzle or other
91
structural discontinuity.

CODE EXTRACT FOR HEAT TREATMENT


( 3 ) When the vessel is required to be postweld heat
treated, and it is not practicable to postweld heat treat the
completed vessel as a whole or in two or more heats; any
circumferential joints not provisionally heat treated may be
thereafter locally postweld heat treated by heating such
joints by any appropriate means that will assure the
required uniformity.
( 4 )
While carrying out local postweld heat treatment,
the soak band shall extend around the full circumference.
The portion outside the soak band shall be protected so
that the temperature gradient is not harmful.
( 5 ) Heating a circumferential band containing nozzles
or other welded attachments in such a manner that the
entire band shall be brought up uniformly to the required
92
temperature and held for the specified time.

CODE EXTRACT FOR HEAT TREATMENT


( 6 ) Where more than one pressure vessel or more
pressure vessel part are postweld heat treated in one
furnace charge, thermocouples shall be placed on
vessels at the bottom, center, and top of the charge or in
other zones of possible temperature variation so that the
temperature indicated shall be true temperature for all
vessels or parts in those zones.
( 7 ) Postweld heat treatment, When required, shall be
done before the hydrostatic test and after any welded
repairs. A preliminary hydrostatic test to reveal leaks
prior to PWHT is permissible.
( 8 ) For pressure vessels or parts of pressure vessels
being post weld heat treated in a furnace charge, it is the
greatest weld thickness in any vessel or vessel part
which has not previously been postweld heat treated. 93

CODE EXTRACT FOR HEAT TREATMENT


( 8 contd...) The nominal thickness is the total depth of
the weld exclusive of any permitted weld
reinforcement.

For groove weld, the nominal thickness is the


depth of the groove.

For fillet welds, the nominal thickness is the


throat dimension.

If a fillet weld is used in conjunction of groove


weld, the nominal thickness is the depth of the
groove or the throat dimension, Whichever is
greater.

For stud welds, the nominal thickness shall be the


diameter of the stud.
( 9 ) For P1 material ( carbon steel), minimum holding
temperature during postweld heat treatment shall
94
be 1100 Deg. F ( 593 Deg.c).

CODE EXTRACT FOR HEAT TREATMENT


P. NO.

HOLDING TEMP.

1 ( CARBON
STEEL) & 3
(LOW ALLOY
STEEL)

1100 DEG. F(593


C)

NOM.
THICKNE
SS
UPTO 2

SOAKING PERIOD

OVER 2
TO 5

2 HOURS , PLUS 15 MIN.


FOR EACH ADDITIONAL
INCH ABOVE 2
2 HOURS , PLUS 15 MIN.
FOR EACH ADDITIONAL
INCH ABOVE 2

OVER 5

1 HR. PER INCH. ,


HOWEVER 15 MINUTES
MINIMUM

* POST WELD HEAT TREATMENT IS MANDATORY ON P-NO.3 GR. NO. 3


MATERIAL IN ALL THICKNESSES.

95

CODE EXTRACT FOR HEAT TREATMENT


( 10 ) Postweld heat treatment is mandatory in
Following conditions :
For welded joints over 1. 5 nominal thickness.
For welded joints over 1.25 nom. Thickness
through 1.5 nom. Thickness, unless preheat is
applied at a min. Temperature of 200F ( 94c )
during welding.
Vessels or parts of vessels constructed of base
material with corrosion resistant integral or weld
metal overlay cladding or applied corrosion
resistant lining material shall be postweld heat
treated when the base material is required to be
postweld heat treated. In applying this rule, the
determining thickness shall be the total thickness
of base material.
96

When the PWHT is a service requirement.

CODE EXTRACT FOR HEAT TREATMENT

SERVICE CONDITION
LETHAL SERVICE PWHT IS MANDATORY
EXEMPTIONS ARE FEW

97

CODE EXTRACT FOR HEAT TREATMENT


( 11 ) Postweld heat treatment is not mandatory for carbon
steel jobs (P1 material ) in Following conditions
(UG2):

If groove welds is not over in size or fillet weld


with a throat thickness of or less used for attaching
non pressure parts to pressure parts provided preheat
to a minimum temperature of 200F is applied when the
thickness of pressure Part exceeds 1.25.

If studs are welded to pressure parts provided


preheat to a minimum temperature of 200F is applied
when the thickness of the pressure parts exceeds
1.25.

for corrosion resistant weld metal overlay


cladding or for welds attaching corrosion resistant
applied lining provided preheat to a minimum
temperature of 200f is maintained during application
98
of the first layer when the thickness of the pressure
part exceeds 1.25.

CODE EXTRACT FOR HEAT TREATMENT

The temperature of furnace shall not exceed 800F

( 4270C) at the time when the vessel or part is placed in it.

Above 8000F( 4270C), the rate of heating shall not be more

than 4000F Per hour (2000C/Hour) divided by the maximum


metal thickness of the shell or head plate in inches, but in no
case more than 4000F Per hour( 2220C Per hour ).

During the heating period, There shall not be a greater

variation in temperature throughout the portion of the vessel


being heat treated than 2500F( 1390C) within any 15 feet
( 4.6m) interval of length.

99

CODE EXTRACT FOR HEAT TREATMENT

During the holding period, there shall not be a

greater difference than 1500f ( 830c) between the highest and


the lowest temperature the portion of the vessel being heated
During the heating & holding periods, the furnace
atmosphere shall be so controlled as to avoid excessive
oxidation of the surface of the vessel. The furnace shall be of
such design as to prevent direct heat impingement of the
flame on the vessel.

Above 8000F ( 4270C), The rate of cooling shall not be

more than 5000F Per hour (2780C/Hour) divided by the


maximum metal thickness of the shell or head plate in inches,
0

100

but in no case more than 500 F Per hour ( 278 C Per hour).

CODE EXTRACT FOR HEAT TREATMENT


when it is impractical to postweld heat treat at the
temperature specified in table mentioned in Sr.. No. 9, It is
permissible to carry out the post weld heat treatments at
lower temperatures for longer periods of time as shown in
table below :
DECREASE IN TEMP. BELOW
MIN. SPECIFIED
TEMPERATURE IN F
50 (10C)

MINIMUM HOLDING
TIME AT DECREASED
TEMPERATURE (NOTE 1)
2 HOURS

NOTES

100(38C)

4 HOURS

----

150(68C)

10 HOURS

200(94C)

20 HOURS

----

NOTES :
1. MINIMUM HOLDING TIME FOR 1 THICKNESS OR LESS ; ADD 15 MINUTES PER INCH OF
THICKNESS FOR THICKNESS GREATER THAN 1.
2. THESE LOWER POSTWELD HEAT TREATMENT TEMPERATURES PERMITTED ONLY FOR PNO.1 GROUP NO. 1 AND 2 MATERIALS.
101

102

103

104

105

SELECTION OF SPIDERS AT OPEN ENDS FOR HEAT TREATMENT

100

90

80

70

60

50

40

30

20

10000

10

SHELL THICKNESS

Annexure-5

9500
9000
8500
8000
7500
7000 ISMB 250
ISMB 250 BOX SEC

ISMB 250

6000
5500
5000
4500
4000
3500

ISMB 150

3000
2500
2000 ISMB 125

ISMB 150

1500
1000

100

90

80

70

60

ISMB 150
50

40

30

ISMB 125
20

500
10

SHELL DIAMETER

6500

SHELL THICKNESS
DATA FOR ABOVE CHANNELS:
DESIGNATION WT/ MTR.(KG) WEB HT FLG WD FLG THK WEB THK
ISMB 125
13
125
75
7.6
4.4
ISMB 150
14.9
150
80
7.6
4.8
ISMB 250
37.3
250
125
12.5
6.9
ISMC 250
30.4
250
80
14.1
7.1

106

107

HT REQUEST

Annexure-7

108

HT CHARGE

Annexure-8

109

Usage of compansating cable

Annexure-9
page 1 of 4

110

Usage of compansating cable

Annexure-9
page 2 of 4

111

Usage of compansating cable

Annexure-9
page 3 of 4

112

Usage of compansating cable

Annexure-9
page 4 of 4

113

Information on Graph Paper Usage

Annexure-10

114

Mechanical v/s capacitor discharge attachments Annexure-11

115

Thermo. Couple Procurement Procedure

Annexure12

116

Thermo. Couple Attachment Procedure

Annexure13
page 1 of 2

117

Thermo. Couple Attachment Procedure

Annexure13
page 2 of 2

118

You might also like