DRIVAGE OF INCLINES IN

MANDLA NORTH COAL


MINE
of
Jaiprakash Associates Limited, Noida

by

M N Jha & M S Sandhu


1

COAL MINING SCENARIO


Coal mines were nationalized during 1971-73.
80% of coal production came from underground
mine during that era.
Emphasis was given to develop Opencast mining to
meet rising demand.
This trend continued with high level of mechanization
resulting into only 10% share of coal production from
underground mines as of now.
Ministry of Coal identified Coal blocks for allocation
to be developed scientifically through underground
method only.
2

GENERAL INFORMATION
Mandla North coal block with coal seams at a depth
varying from 210 to 300 m was allotted to M/S
Jaiprakash Associates Ltd.
It covers an area of 10.41 sq. km.
Coal seams are highly disturbed with 29 faults in the
property. The major fault (F2A) with 100m throw
divides the property in two parts.
The mine has been planned to extract 1.5 mtpa
deploying 3 sets of Continuous Miner.
One set of inclines with one ventilation shaft are
proposed to access coal seams.

COAL SEAMS
Barakar formation contains 5 coal seams splitted in
to 19 workable/non-workable seams occurring at a
depth varying from 173-350m.
The following distinct horizons formed by coal
seams are found workable.
COAL HORIZON COAL SEAM
TOP SET
1 Seam I B
2 Seam I C
3 Seam II
4 Seam III B
BOTTOM SET
5 Seam IVA/A2
6 Seam VA/A1
7 Seam VB/B1

METHOD OF WORKING
It is planned to develop Seam IC initially having found in all 24
sectors with Gross reserve of 45.48 mt since Seam IA has not
developed into workable thickness and Seam IB coalesced with
Seam IC at various places.
Life span for extraction of IB/IC is estimated at 25 years @ 1.5
mtpa.
Extraction of II/IIIB shall be planned after a lapse of 5 years on
completion of depillaring of the first panel of Seam IB/IC. This
sequence will be followed for the remaining lower seams.
It has been decided to work this mine by Bord & Pillar method
with deployment of Continuous Miner for driving Trunk headings
along rise and dip of the property.
Panels comprising a set of 5 headings with cross connecting
galleries will be opened on either side of the main trunk
roadway for lateral development.
3 sets of Continuous Miners will be deployed to achieve the
targeted Mine capacity of 1.5 mtpa.

METHOD OF WORKING (Contd)


VENTILATION
The proposed Mandla North Coal Mine has been
considered as Degree-II Gassy Mine for
assessment
and
planning
of
ventilation
requirements.
18000cum/minute of air is required to be produced
by Mechanical system installed in Ventilation shaft.
3.3 kv, 350kw motors shall be installed.
These figures has been arrived taking into account
all relevant DGMS requirements.
6

METHOD OF WORKING (Contd)


EVACUATION OF COAL
Continuous Miner shall convey the coal into Shuttle
cars through its bridge conveyor.
Loaded Shuttle car will discharge coal onto the
feeder-breaker via coal hopper.
Coal will be discharged uniformly onto the gate belt
conveyor from feeder breaker.
The gate belt in turn will discharge the coal onto the
trunk belt conveyor and to bunker on the surface.
Mechanically covered trucks will carry the coal from
bunker to Railway siding for loading into the railway
wagons.
7

INCLINE DRIVAGE
A single set of inclines measuring 5.2mX3.5m at a
gradient of 1 in 4.5 are being driven in the centre of
the property.
The above parameters will restrict the length of the
inclines to 903mx2 with optimum level of efficiency
both for evacuation of coal and man riding system.
The inclines will pass through Deccan Traps
(495mx2) and Moturs (348mx2) before intersecting
the coal bearing Barakars.
8

INCLINE DRIVAGE (Contd)


TECHNOLOGY
Deployment of Road header - This option was not
considered because of its unsuitability in Basalt
having hardness >8.
Drilling, blasting with combination of SDL and
conveyor belt The frequent shifting of Conveyor
belt along with high level of maintenance makes
this option unviable.
Deployment of Jumbo drill, SDL and 150kw
haulage with 10t skips This has been adopted
being the most suitable for Indian condition and
subsequently to be used for man riding.

INCLINE DRIVAGE (Contd)


EQUIPMENTS-HAULAGE
Haulage with man riding provision with following
specifications have been installed.
Haulage rating 150 kw
Rope Speed 2.2 to 2.5 m/sec
Rope pull 20 Tonnes in 1 in 4.5 gradient
Rope diameter 25 mm
Motor RPM 1000
Drum diameter 1500 mm
Rope length 1200 m
10

INCLINE DRIVAGE (Contd)


EQUIPMENTS-JUMBO DRILL
One Jumbo drill capable of drilling both face and
roof holes in two inclines with following
specifications has been deployed.
Make Sandvik HL 510
Percussion pressure 120-175 bar
Rotation (max) 175 bar
Impact power 16 kw
Feed length 3900mm+860mm
Feed force 9 Kn/120 bar
Water pump 1 x Water booster pump
Length 8015 mm
Width 1700 mm
Height (without canopy) 1800 mm

11

INCLINE DRIVAGE (Contd)


EQUIPMENTS-SIDE DISCHARGE LOADER
Two SDLs to load the broken rock into the 10 t
skip with following specifications.

Overall length 5428 mm


Height over canopy 1850-2100 mm
Ground clearance 205 mm
Bucket capacity 0.66 cum (side tipping rock bucket)
Gradient to be negotiated 1 in 4.5
Track width (grouser pads) 330 mm

12

INCLINE DRIVAGE (Contd)


EQUIPMENTS-VENTILATION FAN
In order to get air flow of 8cum/sec at the face end
of 900 m long drift, fans of 37.5 kw with following
specifications are installed in respective inclines.
Fan Pressure 3200 Pa
RPM 2950
Voltage 415 V
Rating of fan motor 37.5 kw

13

INCLINE DRIVAGE (Contd)


BLASTING PATTERN

14

INCLINE DRIVAGE (Contd)


BLASTING PATTERN

15

INCLINE DRIVAGE (Contd)


Time Study
Activity
Tramming
Water connection
Scaling (Dressing)
Face Drilling
Roof Drilling
Roof bolting
Water dis-connection
Tramming
Face charging
Blasting
Entry after blast
Face clearance after blast
Mucking(Blasting muck clearance)
General work(Ducting, lighting etc)
Total Time

Total Time (In minutes)


05
15
20
52
20
50
15
07
60
10
20
30
240
60
604 (Say 600 minutes) i.e 10 hours.

16

CONCLUSION
We expect to achieve a progress of 90m per month
in each incline to touch coal seam within a time
span of 10-12 months.
Continuous Miner will be deployed to drive trunk
heading and for formation of panels.
3 set of Continuous Miner along with allied
equipments shall be commissioned to achieve the
target production of 1.5 mtpa.

17