GENERAL INFORMATION
Mandla North coal block with coal seams at a depth
varying from 210 to 300 m was allotted to M/S
Jaiprakash Associates Ltd.
It covers an area of 10.41 sq. km.
Coal seams are highly disturbed with 29 faults in the
property. The major fault (F2A) with 100m throw
divides the property in two parts.
The mine has been planned to extract 1.5 mtpa
deploying 3 sets of Continuous Miner.
One set of inclines with one ventilation shaft are
proposed to access coal seams.
COAL SEAMS
Barakar formation contains 5 coal seams splitted in
to 19 workable/non-workable seams occurring at a
depth varying from 173-350m.
The following distinct horizons formed by coal
seams are found workable.
COAL HORIZON COAL SEAM
TOP SET
1 Seam I B
2 Seam I C
3 Seam II
4 Seam III B
BOTTOM SET
5 Seam IVA/A2
6 Seam VA/A1
7 Seam VB/B1
METHOD OF WORKING
It is planned to develop Seam IC initially having found in all 24
sectors with Gross reserve of 45.48 mt since Seam IA has not
developed into workable thickness and Seam IB coalesced with
Seam IC at various places.
Life span for extraction of IB/IC is estimated at 25 years @ 1.5
mtpa.
Extraction of II/IIIB shall be planned after a lapse of 5 years on
completion of depillaring of the first panel of Seam IB/IC. This
sequence will be followed for the remaining lower seams.
It has been decided to work this mine by Bord & Pillar method
with deployment of Continuous Miner for driving Trunk headings
along rise and dip of the property.
Panels comprising a set of 5 headings with cross connecting
galleries will be opened on either side of the main trunk
roadway for lateral development.
3 sets of Continuous Miners will be deployed to achieve the
targeted Mine capacity of 1.5 mtpa.
INCLINE DRIVAGE
A single set of inclines measuring 5.2mX3.5m at a
gradient of 1 in 4.5 are being driven in the centre of
the property.
The above parameters will restrict the length of the
inclines to 903mx2 with optimum level of efficiency
both for evacuation of coal and man riding system.
The inclines will pass through Deccan Traps
(495mx2) and Moturs (348mx2) before intersecting
the coal bearing Barakars.
8
11
12
13
14
15
16
CONCLUSION
We expect to achieve a progress of 90m per month
in each incline to touch coal seam within a time
span of 10-12 months.
Continuous Miner will be deployed to drive trunk
heading and for formation of panels.
3 set of Continuous Miner along with allied
equipments shall be commissioned to achieve the
target production of 1.5 mtpa.