Professional Documents
Culture Documents
at
Kattupalli
Introduction
Lot of complexity
Central/State/Local
approvals
Funding issues
50+ vendors/suppliers
Day-to-day sync issues
Geo-political issues
Labor issues
Technology issues
Durations are estimates
Lot of Slack
Background
The
shiplift,
jetties)
and
land
facilities
(shops,
Based
on
our
past
experience
in
implementing
TOC
in
Project overview
fighting)
o The 2nd shiplift in India. First is 175 m long, 25 m
3.5
km of Breakwater (completion of forward pass for navigational
wide,
manufactured and commissioned by a foreign
clearance)
company (with over 90% market share) in 25 months
Shiplift
o L&T is the only company in India to design, build and
commission a Shiplift completely in-house (200 m
long; 46 m wide) emphasizing its leadership in
engineering & construction
o Safety First - Throughout the 28 months of
execution, and more than 2.5 million man-hours,
there were zero accidents at site.
o Uncompromised Quality - Internationally acclaimed
Lloyds Registrar of Shipping involved in thorough
inspection from procurement of raw material to final
ANIMATION
VIDEO
Shipyard
Due to large investment of over 1800 crores, interest and the depreciation
Shiplift in particular
A common facility between the new-build and repair business streams, as
Summary of results
FK
Phase
3
months
FK
Phase
Sep 2011
Shiplift
commissioned
Plann
ed
Oct 2009
Site activity starts
5 months
recovered through
improved execution
24
months
3
months
Jan 2012
Shiplift
commissioned
Actual
Oct 2009
Site activity starts
28
months
Ban on river sand
5 months of
delays in supply
of plates
3 excessive
monsoons
Heavy manpower
shortage due to
CG
3 cyclones
Bought outs
delayed by 4.5
months
No fire-fighting
Entire management capacity could focus on one or two problem
areas at a time
Vendors
Contractors
President, L&T
HED
Focused on
managing
schedule
Key
Management
Team
Realization
Director
Finance/ Legal
Project Team
Realization
Site team
Operations/
Supply Chain
HR
Marketing
and
Sales
Platform Erection
Platform Erection
Hoist Erection
Hoist Erection
Transfer System
Transfer System
Commissioning
Commissioning
Transfer System Manufacturing
Transfer System Manufacturing
Hoist Manufacturing
Hoist Manufacturing
Commissioning
Commissioning
Platform Fabrication
Platform Fabrication
Shiplift Civil Works
Shiplift Civil Works
F
BF
B
Hoist Manufacturing
Hoist Manufacturing
Transfer System Manufacturing
Transfer System Manufacturing
Platform
Platform
Erection
Erection
FB
FB
Hoist
Hoist
Erection
Erection
Commissioning
Commissioning
Commissioni
Commissioni
ng
ng
FB
FB
PB
PB
Actual
time:
7043
Planned
time:
days +
Ensure completion
Actual duration: 70 days
70 days recovered
Module Assembly in
batch of 3
Initial plan
Platform
erection
Platform
erection
Hoist Erection
SL
commissioning
SL
commissioning
HE for 13
mod
FK
PE of 13
mod
HE for 13
mod
PB
SL
commissioning
PE of 13
mod
Plan executed
Hoist Erection
SL
commissioning
Results Achieved
(pictographical)
Crisis faced due to cycle time
increase in Marine Piling: Advance
Warning signal
Scope
increased to
200m and
timeline
extended
Shortage of
manpower for PEB
works
3 cyclones
Unanticipated
dewatering
requirements
3 severe
monsoons
Project comparison
Shiplift
Key Learnings