Professional Documents
Culture Documents
TO
THE
PRESENTATION ON
AUGMENTATION OF LIGNITE
HANDLING SYSTEM
THERMAL POWER
STATION - II
1470MW (7X210)
MARCH 1986-JUNE1993
COMMISSIONING
Unit 3-1986
Unit 2-1987
Unit 1-1988
Unit 4-1991
Unit 5-1991
Unit 6-1992
Unit 7-1993
AREA
207 HECTARES
FUEL
ANNUAL LIGNITE
USAGE
~ 10.5 MT
Conveyor C1
from Mine-II
Bunker toTPSII Expn
Conveyor
from JT 5
to TPS-II
Expn
Diversion/sharing
arrangement in JT 5
Conveyor CC 1
from Mine-II
Bunker to TPS-II
JT 2
Conveyor No 3
JT 3
CONVEYOR CC 2
Conveyor No.2
Cover shed
STACKER
Junction Tower 2
Transfer Tower 1
Junction Tower 3
Reclaimer A
Corridor
conveyor 2
PRESENT PROPOSAL
CORRIDOR CONVEYOR SYSTEM-II
The proposed project, CORRIDOR
CONVEYOR SYSTEM-II, envisages a
link between JNT-5 of TPS-II Expn. and
JT-3 of TPS-II, through a new conveyor
C-2, in succession to C1 conveyor
The Conveyors C1 and C2 will be in
parallel alignment to existing Conveyors
CC1 and CC-2.
Conveyor C1
from Mine-II
Bunker toTPS-II
Expn
Conveyor
from JT 5 to
TPS-II Expn
Primary
Crusher
TPS II Expn
Diversion/sharing
arrangement in JT 5
Conveyor CC 1
from Mine-II
Bunker to TPS-II
Propo
s
Conv ed
eyor C
2
JT 2
Con
veyo
rN
JT 3
o3
CONVEYOR CC 2
Conveyor No.2
Cover shed
STACKER
Lignite Stock
pile
Lignite Stock
pile
PROJECT JUSTIFICATION
CC1 & CC2 is in operation for more than 20 years in
a corrosive environment.
Break down probability of CC1 or CC2 is rare But
possibility can not be ignored
In such exigencies single source of supply of lignite to
TPS-II, and feeding of lignite to TPS II would come
to halt
On depletion of the available stock at TS-II will lead
to Generation loss
Requirement of additional facility to receive lignite
to TPS II helps TPSII s generation programme
unhindered
Conveyor C2
The Conveyor-C2 is fed with lignite either fully
(3000 T/Hr.) or partially (1500 T/Hr.) from
Conveyor-C1 via JNT-5 discharge hopper /
stationary feeder SFD-1 located at 3.5 mtr.
Level in TPS-II Expn..
The belt conveyor-C2 straight from JNT 5 of
TPS II Expn. up to JT-3, conveys lignite
through Con-3.1, Con-3.2 in JT3 to the storage
yard via Con-2 or directly to the boiler bunkers
via Con-7A.
Details of Conveyor C2
Belt Length
850 mtrs.
Belt Capacity
Belt speed
Belt width
Lift
Power
4.2 m/sec.
1800 mm
12 mtrs. approx.
2 x 350 KW at head end.
Belting
Conveyor design
Angle of conveying
Max. 5
CAPITAL COST
Basis of Estimation :
Estimate for Conveyor-C2 (Mechanical portion)
has been made based on Project cost for
2000mm conveyor for Mine-II Expn. Project .
From the above, Cost/Ton for the mechanical
portion was Rs. 1.18 lakhs/ton.
The escalation for 3 years is worked out
@ 40%, Cost/Ton for the mechanical portion is
arrived @ 1.7 lakhs/Ton.
ESTIMATE ABSTRACT
Mechanical portion
Electrical portion
Civil portion
Rs.1811.10 lakhs
Rs.1900.00 lakhs
Impact on Tariff
( Rupees in Lakhs
1900.00
Depreciation @ 3.6%
68.40
47.50
512.91
9657.90
965.79
8692.11
0.59 0.6
IMPLEMENTATION
The project is proposed to be executed on turnkey basis.
The scope includes Design, Manufacture &
Supply, Erection, Civil works, Commissioning
and performance test of the system.
Time period for completion of the project must be
within 20 months from the date of LOA.
COMMITTEE
THANK YOU.