Professional Documents
Culture Documents
401
Project Management
Spring 2007
Lecture 6
Estimating
Project Management
Phase
FEASIBILITY
Fin.&Eva
l.
Risk
DESIGN
PLANNING
DEVELOPMENT CLOSEOUT
Organization
Estimating
Estimating
Planning
OPERATIONS
Detailed Estimates
Definitive Estimates
Conceptual
design
Detailed
design
Pre-bid
Construction
Detailed Estimates
Outline
Cost indices
Parameter Cost
Detailed Estimates
Estimates
Cost classification
Calculation
Decide Feasibility
Categories:
Complexity
Accuracy
Cost-capacity Factors
Parameter Costs
Outline
indices
Parameter Cost
Detailed Estimates
Estimates
Cost classification
Calculation
Cost Indices
Cost indices show the changes of a certain facilitys costs over time
Year 1913 = 100, Year 2007 = 4432
If Facility A is similar to my wish facility and I know the value of Facility A at 1913,
I can assume my wish facilitys value at 2007.
Source: http://www.enr.com/features/conEco/
Cost Indices
Source: http://www.enr.com/features/conEco/
2007
4432
Source: http://www.enr.com/features/conEco/
Source: http://www.enr.com/features/conEco/
Example:
Components:
Source: http://www.enr.com/features/conEco/
costIndexes/constIndexHist.asp
Outline
indices
Cost
capacity factor
Parameter Cost
Detailed Estimates
Estimates
Cost classification
Calculation
Cost-Capacity Factor
C2 = C1 (Q2/Q1)
Where
Cost-Capacity Factor
Cost-Capacity Factor
Example
Example Revisit:
Cost-Capacity Factor
Example
Where
Example Revisit:
Outline
Conceptual Estimates
Cost
indices
Cost
capacity factor
Parameter
Cost
Detailed Estimates
Estimates
Cost classification
Calculation
Parameter Costs
Characteristics
Exterior
wall
variation
Exterior
wall
variation
Base Cost =
129.65 $/S.F
Perimeter
&
Height
Adjustment
Perimeter
&
Height
Adjustment
Basement
Additives
60 191
Perimeter Adjustment
Basement Addition
Location Modifier
Basic SF Cost in R.S. Means for S.F Area=80000, L.F Perimeter = 530,
Story Height = 10 & No Basement
$128.35/SF when exterior walls are Brick w/ Concrete Block Backup (North)
$122.25/SF when exterior walls are Decorative Concrete Block (East, West,
south)
Perimeter Adjustment
Basement Addition
Location Modifier
Perimeter Adjustment:
Apartment building perimeter is 28 L.F (530 -502) less than the M.020 model
building in RS Means
Height Adjustment:
Apartment building story height is 1 4 (11 4-10) more than the M.020
model building in RS Means
Perimeter Adjustment
Basement Addition
Location Modifier
Basement Addition:
Perimeter Adjustment
Basement Addition
Location Modifier
Location Modifier
Basement Addition:
$10,182,270
Perimeter Adjustment
Basement Addition
Location Modifier
Depreciation Adjustment
Depreciation
Adjustment Factor
$ 11,505,965
Outline
Conceptual Estimates
Cost
indices
Cost
capacity factor
Parameter
Cost
Detailed Estimates
Estimates
Cost classification
Calculation
Detailed Estimates
Definitive Estimates
Conceptual
design
Detailed
design
Pre-bid
Construction
Detailed Estimates
Important General
Lesson
Always consider:
Detailed Estimates
Conceptual
design
Detailed
design
Pre-bid
Construction
Detailed Estimates
Engineers
Engineers Detailed
Estimates
Engineers Detailed
Estimates
RS Means (2006) Building Construction Cost Data, Page 84
Engineers Detailed
Estimates
Building
Foundations
Piles
Concrete
foundations
Steel erection
Structural steel
Columns
Beams
Detail steel
Concrete decks
Stairs
Conceptual
design
Detailed
design
Pre-bid
Construction
Detailed Estimates
Engineers
Bid
Who? contractor
Often relies on
Subcontractor bids
Bid Breakdown
Example
Building (Engineers
estimates)
Foundations
Piles
Concrete foundations
Steel erection
Structural steel
Columns
Beams
Detail steel
Concrete decks
Stairs
Detailed Estimates
Definitive Estimates
Conceptual
design
Detailed
design
Pre-bid
Construction
Detailed Estimates
Definitive Estimates
Traditional
Unit-price
Professional CM
Design-Build
Definitive Estimates:
Traditional & Unit Price
Start
Preliminary design
Detailed design
Contract
Start
Preliminary design
Detailed design
Contract
Definitive Estimates:
CM & Design-Build
CM definitive estimate
Start
Preliminary design
Detailed design
Contract
Start
Preliminary design
Detailed design
Contract
Outline
Conceptual Estimates
Cost
indices
Cost
capacity factor
Parameter
Cost
Detailed Estimates
Estimates
Cost
classification
Calculation
Cost Classification
Direct Cost
Direct Labor
Indirect Labor
Material Cost
Equipment Cost
Subcontractor Price
Labor Cost
Project Overhead
Markup
General Overhead
Profit
Contingency
Source: Shtub et al., 1994
Labor Cost
Difficult to evaluate precisely but all effort is done to get an accurate estimate as
possible
Costs that are additional to the basic hourly rates (e.g., tax, insurance, fringe benefits)
Commonly used approach adds indirect labor costs as a percentage to the total direct
labor costs or for each major work category
Equipment Cost
Material Cost
Subcontractor Price
Markup
Profit
Contingency
Cost Classification
(Example)
Cost Classification
(Example)
1.24
Outline
Conceptual Estimates
Cost
indices
Cost
capacity factor
Parameter
Cost
Detailed Estimates
Estimates
Cost
classification
Calculation
Example:
Item
unit
quantit
y
Unit
price
price
Reinforced
steel
lb
6,300
0.60
$
3,780
Labor Costs
Components
Productivity
Considerations
Considerations
Learning Curves
Productivity Effects of
Overtime
Concluding Remarks
Functions of Estimating
Concluding Remarks