You are on page 1of 34

TRAINING PROGRAMME ON

ENGINEERING DESIGNS - CANAL STRUCTURES

GENERAL DESIGN PRINCIPLES

Aqueducts, Canal Syphons & Escapes

BY
ROUTHU SATYANARAYANA
CHIEF ENGINEER (Retired.)
FORMER ADVISOR, GOVERNMENT OF A.P

Cross Drainage WorksAqueducts


1. Aqueducts:
Classified as: type-I, type-II and type- III depending up on the arrangement of canal passing
over the Stream/drain,
Type-I: Structures come under this type where the canal continuous over the stream with
its normal earthen section including the banks and earthen slopes. The HFL of the stream
shall be lower than the bottom level of the canal trough.
Type-II: Structures where the canal continues over the stream but the outer banks are
replaced by outer walls.
Type-III: The canal banks will be discontinues over the stream and the canal water is
carried by a masonry or concrete, RC C Box, Pipe of suitable section. The Service and
inspection Tracks may be continuous or discontinues. Generally the canal section is
flumed and head loss is accounted for.

2. Viaducts:

Similar to type-III aqueduct except the length of the structure is very large compared to the
stream or there is no stream/drain existing in the valleys joining the two sides of the
structure.

3. Syphon Aqueduct:

The HFL of the stream/drain will be lower than the under side of (bottom level) the canal
trough . If the HFL of the stream is above the canal bed it is called syphoned.

Cross Drainage WorksAqueducts

4. Under tunnel (barrel/ pipe)/ Syphon Aqueduct:

Stream discharge carried in the barrel if required by depressing stream bed level to make
the headway below the canal. Canal section carried over barrel as it is with head walls to
replace the outer slopes of canal partially/ fully. The under tunnel flowing full under
pressure is called syphon aqueduct.

5. Buttress type under tunnel:

Steam discharge carried in the barrel if required by depressing the stream bed level to
make the head way below the canal and canal discharge carried in the flumed trough
(Trapezoidal or rectangular). The abutments and piers raised to the bottom of trough in
case of Trapezoidal shape. For continuity of inspection path, a bridge and for non
inspection path foot bridge will be provided.

6. Super passage:

Stream discharge carried in the trough normally rectangular shape (1 or more bays) with
vertical clearance over F.S.L. of canal. For continuity of inspection path bridge and for non
inspection path foot bridge will be provided separately.

7. Canal siphon:

Canal discharge carried below the stream by depressing the canal bed to make the
headway. For continuity of inspection path a bridge will be provided separately.

CD Works Level Crossings


8. Level Crossing:

In this type of works the drainage water and canal water are allowed to intermingle with
each other .
A Level crossing is provided when large canal and a huge drain approach at the same
level.
An Inlet and out let for the canal and an escape for the drainage or vice versa are
provided.
Perennial drainage discharge can be used in the canal supplies.

9. Inlets and Out lets:

Provided at exceptional cases.

Cross Drainage WorksAqueducts


Design Criteria :

Hydrology of the drain or stream.

Hydraulic design of

a.

The stream or drain

b.

The hydraulic deign of the canal

Structural Design.
a.

Design of sub structure

b.

Design of super structure

Cross Drainage WorksAqueducts


Basic Data :

Site plan with net levels at 10m intervals and contours and duly marking the flow direction of the canal
and the stream.

Hydraulic particulars of the canal

LS of the stream covering 500m on u/s and d/s with levels at 10m to 20m intervals and CSs at centre
line and at 10m, 25m, 50m, 100m, 200m, 300m, 400m, and 500m on /s and d/s sides.

Levels on the CS to be 3m, to 5m, in the gorge portion and 10m, intervals on the flanks up to 50m
beyond HFL mark on the ground.

Catchment area plan of the seam/drain on the topo sheet for Catchment up to 2.5 Sq..m and the CA
to be traversed on ground for Catchment less than 2.5 sq..m.

Computation of Maximum Flood Discharge (MFD) of the stream/drain. and the HFL/ MFL are to be
marked on ghe LS & CSs and cross checked with the Observed MFLs (OMFL).

Trial Pit (TP) particulars (Bore logs) taken up to hard strata, for a minimum depth of 2m below ground
level or drain bed level or canal bed level for shallow foundations and up o 1.33R below maximum
scour level on the centre line of the structure, (and) at least one on either side or as decided as per the
filed conditions along the centre line and One each on u/s and d/s side.

Safe bearing capacity of the strata may be obtained and furnished.

Cross Drainage WorksAqueducts


Hydraulic data:

Canal
a.

Width of road way and class of IRC loading.

b.

Head loss provided.

The Stream or drain:


a.

Allowable afflux.

b.

Nature of bed material and value of n

Cross Drainage WorksAqueducts


I. Hydrology of the drain:

Computation of maximum flood discharge and the MFL

II. Hydraulic design:

Water way/Vent way:

Vertical Clearance:

Free Board:

Crust Level of the Road way or a Bridge:

Afflux:

Depth of Scour:
i.

Mean Depth of Scour (d):

ii.

Maximum Depth of Scour or Designed Depth of Scour (D or R):

Uplift

Exit gradient.

Loss of Head (Energy Loss):

Joints:

III. Structural Design:

Super structure
Sub structure

Aqueducts - Hydrology
I. Hydrology of the Drain/Stream:

1. Compute the designed flood of the stream from catchments area plan using any
one of the empirical formulae or by the flood frequency method, SPF, PMF.

2. Compute the MFL in the stream by step by step method by trial and error and
verify with observed MFL.

3. For drains with discharge > 150 cumecs and canals with discharge > 30 cumecs
detailed study is to be conducted in respect of Catchment area and computations of
HFD/SPF or PMF.

Aqueducts - Hydrology
I. Hydrology of the Drain/Stream:

Formulae for computation of maximum Flood Discharge:

_____________________________________________________________
S.No.
in Sq. Miles

Type of Canal

Catchment Area (CA) in M

---------------------------------------------------------------------------------------------------------Up land Areas


Deltaic Tracts
-------------------------------------------------------------------------------------------------------------------------------------------------------1.
Main Canal
Dickenss formula,
Rye's formula
Q = CM 3/4
Q = CM 2/3
C=1400 for CA<1.00
C=1200 for CA=1 to 30

2.

3.

C=1000
Velocity shall not exceed
10 ft/sec

C=1060 for CA=30 to 500


-------------------------------------------------------------------------------------------------------------------------------Q=7000 M1/2 for CA>500
Velocity in the barrel up to
12 to13 ft/sec
------------------------------------------------------------------------------------------------------------------------------Branch Canal
Q=CM 2/3
Q > 500 c/s
C=1000 and Velocity<10/sec
same as upland area
------------------------------------------------------------------------------------------------------------Distributaries
Q = CM 2/3
same as upland area
Q < 500 c/s
C=750 and Velocity< 10/sec
------------------------------------------------------------------------------------------------------------------------------------------------Lr. No. CDO/EE-C1/1084/83-3 dated 23.08.1983.

CD Works - Aqueducts
1. Water way / Vent way and the Lay out:
Design the vent way of the stream/drain limiting the velocities in the drain, Keeping in
view the Laceys wetted perimeter limiting the fluming ratio to 60% to 80%
and velocity<3m/s.
i. A vent way in Masonry with RCC trough or RCC box with height not less than
1200mm (1500mm preferred)
ii. For smaller discharges RCC Hume pipes diameter no <900mm
Design the tail channel and the approach channel
Drain transactions :
i. Wings and returns are provided both on u/s and d/s side of the stream with
splays 2:1 but not flatter than 4:1 on the u/s and 3:1 but not flatter than 5:1
both on d/s side.
ii. Drop wall on the d/s side of the structure may be avoided.
Design/Fix the canal trough limiting the fluming ratio not more than 70% and energy
losses not greater than the values provided in HPs and velocity generally not more
than 3 to 4m/s.
Transition lengths both on the u/s and d/s side of the canal is fixed.
i. Canal transitions 2:1 and 3:1 splay but not flatter than 4:1 and 5:1 on u/s and d/s
respectively.

CD Works - Aqueducts
Transition walls : Transition walls to be provided at either ends keying 600mm in to the
earth banks both for drain and canal.
Compute the TELs of the canal starting from d/s side end of the canal transition up to
u/s side transition of the canal (Designed canal section on either side) and verify that
the head loss and the velocities are with in the permissible limits.
Finalize the widths of the inspection tracks foot paths on either side if required.
Design the tail channel and the approach channel of the stream.
Compute the TELs in the stream limiting the velocities, and permissible afflux etc.
Draw flow diagrams both for the stream and canal.
Compute and design foundation levels considering scour depths.
Compute and design the barrel and the floors of the stream for uplift pressure.
Check for exit gradient.
(cont)

CD Works - Aqueducts
Lay out :

Preferably a straight reach.

The carrier canal and the drain shall be at right angle crossing.

Proper training works for the drain and suitable protection works like turfing, pitching
and launching aprons etc.,

Expansion joints, Contraction Joints and construction joints.

AqueductsHydraulic Design
II. Hydraulic Design:
Vertical Clearance:

It is the vertical distance between the HFL of the stream and the under side of
the canal trough including afflux.

S. No.
mm
1.
2
3.
4.
5.

Designed flood in Cumecs


<3
Between 3 and 30
Between 30 and 300
Between 300 and 3000
3000 and above

Minimum Vertical Clearance in


450
600
900
1200
1500

AqueductsHydraulic Design
Free Board:

It is the vertical distance between the HFL/FSL to the top of


embankment/TBL in case of stream and canal respectively.
Crust Level of the Road way or a Bridge:
The TBL of the canal or the crust level of the road way or the natural ground
level which ever is higher.

Afflux:

It should be restricted to the value which should not cause serious bed
scours or submergence.
It is the rise in water level on the upstream due to an obstruction to the flow
of drain or canal.
It is computed using the Rational formula, Orifice formula or Empirical
formula
It is the vertical distance measured from HFL or FSL to the underside of
trough, including afflux.

Aqueducts Hydraulic Design


Scour:
Mean Scour Depth:

Mean scour depth is the depth (d) below HFL or FSL in m


d = 1.34[q2 /f]1/3
Where, q = Discharge per meter width with or without concentration of flow in
cumecs, f = Layces silt factor expressed as f = 1.76 (d m )1/2
dm = average grain size

Designed Scour Depth (Dor R):

Straight reaches for individual foundations without floor protection


In the vicinity of pier
Near abutments

2.00 d
1.27 d approaches retained
2.00 d scour all round
For floor protection works, for raft foundations and shallow foundations
In straight reaches
At moderate bends

1.27 d
1.50 d

Aqueducts Hydraulic Design


At sever bends
At right angle bends

1.75 d m
2.00 d

Structures and earth work connections :


Uplift:

Uplift under floor of the barrels and under the u/s and d/s side floors caused
by the seepage flow from the canal when it is running full and the drain is
dry or vise versa may be accounted for the design using the Khoslas
theory and the thickness checked for adequacy.
Cut off walls may be provided on either ends.
For reducing the uplift and exit gradient pucca floor should be provided for
in the canal bed in adequate length u/s and d/s side with cut off walls at the
ends.

Exit gradient.

The rigid structure and the flexible earth work shall be properly connected
and checked for exit gradient (GE).
GE = H/d[1/ () 1/2]

Aqueducts Hydraulic Design


Loss of Head (Energy Loss):

The losses are at inlets (h 1) and outlets (h2), at bends elbows (h3), losses due to
transitions (h4) and losses due to skin friction (h 5). The sum of losses (H) shall be
sum of all the losses

H = h1 + h2 + h3 + h4+h5

Joints:
Bell Mouth on U/S side:
Cut and ease waters:
Water Stops:
Bearings:
Miscellaneous works:

Aqueducts Structural Design


III. Structural Design:

Design Loads:
Dead Loads
Live Loads
Impact and Dynamic Loads
Water Load
Braking force
Wind Load
Water currents
Centrifugal forces
Buoyancy
Earth pressures
Temperature Forces
Erection Loads.
Seismic Loads.
Water Pressure.

AqueductsStructural Design
III. Structural Design:

Combination of Loads:

a. Canal empty and drain at low water - normal condition with & without earth quake

b. Canal at FSL and drain at low water - normal condition with & without earth quake

c. Canal empty and drain at HFL

- normal condition without earth quake

d. Canal at FSL and drain at HFL

- normal condition without earth quake

e. Construction condition: without earth quake

1. Piers constructed without super structure and drain at HFL

2. Super structure is constructed on one side of pier and the drain at HFL

Wind load should not be considered simultaneously with earthquake.

The effect of earth quake force in all directions that is Longitudinal (L), Transverse (T),
and Vertical (V) shall be taken into with combination T+V or

L+V. 5.05.

Aqueducts Structural Design


III. Structural Design:

Super Structure:

Design of RCC Slab under canal and under earth bank or an RCC Box

Inspection Track: To be designed for Single lane IRC class A Loading and Foot
bridge normally 1.5m wide on non-inspection track.

In case of RCC box, the road way is carried over the box with proper entry and exit
on either ends.

Sub Structure.

Design of piers under canal trough and earth bank or inspection track:

Design of abutments under canal trough, and earth banks or inspection track , by
adopting TVA procedure, Coulombs or Rankin's theory.

Design of abutments under service road / walk way

Design of all retaining walls, such as returns, wing walls, side walls for the drain and
canal both on the u/s and d/s side, by adopting TVA procedure Coulombs theory or
Rankins theory.:

CD Works Structural Design

Design Loads:
1. Dead Loads
4. Water Load
7. Water currents
10. Earth pressures
13. Seismic Loads.

2. Live Loads
3. Impact and Dynamic Loads
5.Braking force
6. Wind Load
8. Centrifugal forces
9. Buoyancy
11.Temperature Forces 12. Erection Loads.
14. Water Pressure.

Combination of Loads:
a. Canal empty and drain at low water - normal condition with & without earth quake
b. Canal at FSL and drain at low water - normal condition with & without earth quake
c. Canal empty and drain at HFL
- normal condition without earth quake
d. Canal at FSL and drain at HFL
- normal condition without earth quake
e. Construction condition: without earth quake
1. Piers constructed without super structure and drain at HFL
2. Super structure is constructed on one side of pier and the drain at HFL

CD Works Structural Design

Design Loads:
1. Dead Loads
4. Water Load
7. Water currents
10. Earth pressures
13. Seismic Loads.

2. Live Loads
3. Impact and Dynamic Loads
5.Braking force
6. Wind Load
8. Centrifugal forces
9. Buoyancy
11.Temperature Forces 12. Erection Loads.
14. Water Pressure.

Combination of Loads:
a. Canal empty and drain at low water - normal condition with & without earth quake
b. Canal at FSL and drain at low water - normal condition with & without earth quake
c. Canal empty and drain at HFL
- normal condition without earth quake
d. Canal at FSL and drain at HFL
- normal condition without earth quake
e. Construction condition: without earth quake
1. Piers constructed without super structure and drain at HFL
2. Super structure is constructed on one side of pier and the drain at HFL

CD Works Canal Syphon


Definition:

Structure, where the drain is taken over the canal such that the canal water runs below the
drain either freely or under syphonic action:

When the FSL of the canal is below the under side of the drainage trough and canal
water flows freely under gravity, the structure is known as Superpasage.

When the canal FSL is below the under side of the drainage trough, so that the canal
flows under syphonic action under the trough, the structure is known as Canal
Syphon or a Syphon.

Canal may be flumed for economy, subject to the availability of head loss in the HPs

The drainage trough should not be flumed.

Inspection Track: can not be provided along the canal.

A separate bridge/Causeway will be provided for inspection track.

Cross Drainage Works-Syphon

Hydrology of the drain:

Hydraulic design:

Computation of maximum flood discharge and the MFL


1. Water way/Vent way:
2. Vertical Clearance:
3. Free Board:
4. Crust Level of the Road way or a Bridge:
5. Afflux:
6. Depth of Scour:
Mean Depth of Scour (d):
Maximum Depth of Scour or Designed Depth of Scour (D or R):
7.Uplift
8. Exit gradient.
9. Loss of Head (Energy Loss):
10. Joints:

Structural Design:

Super structure

Sub structure

CD Works Canal Syphon


Lay out:

Shape can be circular or rectangular.

RCC barrel, pre cast RCC pipes, or masonry etc.,

Syphon barrel:

Horizontal under deep bed portion with slope not steeper than 1 in 3 at entry and 1 in 5 at
the exit end.

The invert level at the entry normally be kept at bed level.

The invert level at the exit end be little lower taking into account the loss of head.

Transition walls with splay 3:1 and 4:1 at the entry and exit end.

Stop log groove

Trash Rack

Miscellaneous items/works:

CD Works Level Crossings


Level Crossing:
Definition:

It is CD work admitting the drainage water in to the canal.

In this type of works the drainage water and canal water are allowed to
intermingle with each other .

A Level crossing is provided when large canal and a huge drain approach at the
same level.

An Inlet and out let for the canal and an escape for the drainage or vice versa
are provided.

Perennial drainage discharge can be used in the canal supplies.

Lay out :

Combination of all or any one of them

Canal inlet regulator

Drainage inlet regulator

Canal outlet regulator

Drainage outlet regulator

Cross Drainage Works- Inlets &


Outlets
Inlets and outlets:
Definition:

A canal inlet is constructed when the cross drainage flow is small and
its water may be absorbed into canal without causing appreciable rise.

Inlets are provided in exceptional cases only.

When the drain discharge is very negligible and less than 5%, an inlet is provided.

An out let or an escape shall be provided, when the total inlet discharge exceeds
more than 15% of the canal discharge.

In drought prone areas or zones of scanty rain fall or the tail end command, the
drainage water can be supplemented.

Cross Drainage Works- Escapes


Escapes & Escape Regulators: See under controlled structures
Escapes are safety valves for the canal system, provided to
escape surplus water or excess water from the canal.
Though the canals are regulated, excess rise in water level
may take place at a point on the canal down stream as a
result of entry of storm water, or sudden reduction in
demand or closure of out lets down stream, or faulty water
regulation may cause breaches, out flanking or dangerous
leaks in the canals banks.
Similar situation may happen in the lift irrigation system,
when the pumping mains on the down stream fail suddenly.
Hence surplus escapes are provided:

1 To control the water levels in such situations and avoid damages


to the system.
2. To empty the canal system for repair and maintenance.
3. As scouring sluices at the head reaches.

THANK YOU

You might also like