Professional Documents
Culture Documents
Bidding Strategies
& Issues
Rajat Misra
04 July 2008
IIT Kanpur
SBICAP
pfi rankings
#1 MLA in Asia pacific (# 9 globally)
#1 Advisor in Asia pacific (#5 globally)
Petrochemicals deal of the year (GGSRL)
04 July 2008
IIT Kanpur
SBICAP
Power Sector Assignments
Bid Advisory & MLA to TPL for UMPP
Bid Advisory to CSEB for 1500 MW
Bhaiyathan Project
Advisor to PGCIL for Tala Transmission
Advisor to GERC for all rules and regulations
under EA03 and Gujarat Act
Unbundling & Privatization of DVB
04 July 2008
IIT Kanpur
Current State
The story of future
GDP growth rate 8% will require similar
growth in power capacity
Installed generating capacity of 128 GW
Required 200GW / 300GW by yrs 2012/2017
IIT Kanpur
ISSUES
All (??) procurement through bidding
No cost-plus projects through MoU (??)
Advantages
Competition
Transparent process
Risk Allocation to Bidder and its Lenders
Incentivization for Efficiency
04 July 2008
IIT Kanpur
ISSUES
However, flawed strategy can negate the
advantages
Further, no real competition if mines are
allocated in non-transparent manner
Difference in Bids where mines are attached
vis--vis case2 bids is evident
04 July 2008
IIT Kanpur
Bid Scenario
04 July 2008
IIT Kanpur
Policy Framework
Section 63 of EA03:
..the Appropriate Commission shall adopt the
tariff if such tariff has been determined
through transparent process of bidding in
accordance with the guidelines issued by the
Central Government.
IIT Kanpur
Bidding Guidelines
Case I: Location, technology or fuel is not
specified
Example GUVNL bid
IIT Kanpur
Bidding Guidelines
Guidelines binding on procurers and
deviations to be approved by ERC
Role of SERCs extremely important
Appropriate deviations should be approved
keeping in view special situations (eg qualification
criteria in case of bhaiyathan; umpp;
overleveraging)
04 July 2008
IIT Kanpur
Bidding Guidelines
A 2 part tariff (Capacity and Energy
charges) for long term procurement.
Combined allowed
Tariff to be in Indian Rupee only (except)
Capacity charges may have separate
escalable and non-escalable components.
Min/Max capacity Charges > 0.7
How feasible is it?
04 July 2008
IIT Kanpur
Bidding Guidelines
Energy Charges
Fixed in Base Year and indexed
May have separate escalable and non-escalable
components
04 July 2008
IIT Kanpur
Bidding Guidelines
Energy Charges for Imported Coal
Base Energy Charge to be escalated
Imported fuel in USD/kWh
Transportation in USD/kWh
Inland fuel in Rs/kWh
IIT Kanpur
Bidding Guidelines
Combined Capacity and Energy Charges
permitted
No escalations above those quoted
allowed
Min offtake to be specified in Bid dox
04 July 2008
IIT Kanpur
Bidding Guidelines
Indices for bid evaluation by CERC
Discounting rate for levelised tariff
calculation to be specified by CERC
Current Rates are as follows:
04 July 2008
IIT Kanpur
Rate
10.49%
7.61%
14.79%
6.39%
04 July 2008
IIT Kanpur
Developers Perspective
Case Studies
04 July 2008
IIT Kanpur
Bidding Steps
Extremely important to have pre-bid tieups in place
Commitment on major costs
Time period for financial close
Interest rates risk?
Escalation & Currency provisions on EPC?
Bids not required to be underwritten
04 July 2008
IIT Kanpur
Bidding Steps
Imported Coal as Fuel
Bidding Strategy and appetite for risk are
more important
Recent bids have clearly underlined this fact
Mix of Indexed and non-indexed costs much
more important
More sensitive to variation in quality
04 July 2008
IIT Kanpur
Imported Vs Domestic
Criteria
Domestic
Imported
Calorific Value
(kcal/kg)
3500
6000
Cost (Rs/MT)
1000
2700
Variable Cost
(Rs/kWh)
0.80
1.4
04 July 2008
IIT Kanpur
04 July 2008
IIT Kanpur
Bidding Scenario
Scenario
Affect on Tariff in
spreadsheet example
D/E 80:20
8 paise
Loan repayment 15
years
7 paise
IIT Kanpur
Lenders Views
Paradigm Shift in financing
Move from Payment Security based lending
to Competitive Tariff based lending
Avoids mistakes of the past
Unbundling, Open Access Provisions drive
lenders comfort
04 July 2008
IIT Kanpur
Lenders concerns
Buy Out Provisions
Evacuation Transmission Risk
Time Frame to achieve Financial Closure
1 year from date of signing of PPA
Environmental Concerns
ECA/ECB financiers
Force Majeure
Land acquisition
Procurers responsibility!!
Change in Law, still
04 July 2008
IIT Kanpur
Lenders Perception
Imported Coal as Fuel
Take or pay only at 65% on imported fuel
Lenders see the above as a risk in long term
contracts.
What would a developer do??
04 July 2008
IIT Kanpur
Case Studies
Imported Coal
04 July 2008
IIT Kanpur
04 July 2008
IIT Kanpur
04 July 2008
IIT Kanpur
IIT Kanpur
04 July 2008
IIT Kanpur
UMPP Krishanapatnam
Significant change in Reliance Strategy
What do the numbers tell?
04 July 2008
IIT Kanpur
Summary
04 July 2008
IIT Kanpur
For SERCs
Take a pragmatic view on deviations from
bidding documents
BE TRANSPARENT ALL BID
NUMBERS TO BE IN PUBLIC DOMAIN
Bidding Strategies Take a call on
appropriate risk sharing mechanism
WHEN TO CANCEL A BID????
04 July 2008
IIT Kanpur
Any Questions?
Bhaiyathan Model???
04 July 2008
IIT Kanpur
Thank you
04 July 2008
IIT Kanpur