Professional Documents
Culture Documents
DISTRIBUTION PLANNING
UNIT 2
Transmission
system:
Transfers bulk
power from the
generating
system to
distribution
system
Sub transmission
system:
segregates power
into dist. systems
Distribution
system:
Between
transmission and
consumers
VOLTAGE LEVELS
Generation :
11 KV
Primary transmission :
220 KV
Secondary transmission
:
33 KV
Primary distribution :
6.6 KV
Secondary distribution :
415 V
Consumers :
415 / 230 V
TRANSMISSION NETWORK
Interconnection permits power exchange
Planning of transmission system involves :
Power flow requirements
System stability
Selection of voltage levels
Voltage and reactive power flow
Conductor selection
Losses
Insulation levels
Type of structure
Right of way
TRANSMISSION NETWORK
Criteria for planning of transmission system :
Availability of generation and demand
Voltage levels
Size and configuration of systems
Distance
Right of ways
Resource constraints
done
Indian loading 90 % ( Healthy loading 50 % )
Network reaches alert state of operation at peak load
Small disturbance causes major network collapse
DISTRIBUTION NETWORK
Sub transmission system:
33 220 KV
Delivers energy to distribution substation
Distribution substation :
converts to lower primary distribution system voltage
Boosts voltages for better voltage regulation of primary voltage
Distribution transformers :
10 2500 KVA
Transform the primary voltage to utilisation voltage at 110 440 V
Secondary circuits :
carry energy from the D.T along streets
Service lines :
deliver energy from secondary circuits to consumer premises
RADIAL
interupption
Low reliability
Suitable for small loads
PRIMARY LOOP
reclosers
Loop is normally operated with tie sectionaliser switch open
Outage time due to fault is reduced
Additional line increases frequency of faults
SECONDARY SELECTIVE
SPOT NETWORK
GRID NETWORK
HV TRANSMISSION (HVAC /
HVDC)
HV preferred due to :
increasing requirement of bulk power transfer over
long distances
Feasibility i.e. economical and ecological advantages
of generating power near the fuel source instead of
load centres
0.5V 2
53.6 * r
P
and PL
Voltage level of transmission X * D
X
Power
power (MW)
handling capacity of a linewhere
: PP Total
Power loss (MW)
L
depends on :
Quantity of power
Distance to be transmitted
HV TRANSMISSION (HVAC /
HVDC)
V (kV)
X (ohm/km)
r (ohm/km)
PL (in %)
400
0.327
0.031
5.12
800
0.272
0.0136
2.7
1000
0.231
0.0036
0.85
1200
0.231
0.0027
0.64
Observation :
The capital cost per MW-km decreases with Higher
Voltage
P(1*800 KV line) = P(4*400 KV lines) for same
distance
For PL(800KV) = 1/10th of PL(400 KV)
HVDC LINKS
Asynchronous HVDC links is used where
Connecting system widely differs
AC mode of connecting systems is impossible
TYPES OF DC LINKS
Based on location of
converting stations :
Two terminal D.C. line
Power transfer is economical
over long distances
HVDC TRANSMISSION
Technical advantages of HVDC links :
Power flow can be controlled independent of system operating
conditions.
System operating at different frequencies may be interlinked
Improves stability
Common reasons for using HVDC links:
Lower line costs 2 wire system
Lower losses no reactive power flow
Asynchronous connection-two different frequencies
Controllability- semiconductor technology yielded better
reliability ,controllability
Major electrical networks
long distance transmission
interconnection between systems
high power underground distribution system feeders
HVDC TRANSMISSION
Increased transferability :
the same voltage will transfer higher power, with the
same infrastructure
A single AC circuit can be re-arranged into bipolar DC
line transmission capacity increases by 150 %
Right of way retained
HVDC TRANSMISSION
Other advantages of using HVDC links :
DC cables are cheaper compared to AC
One single cable can take up to 500-1000 MW
A DC cable does not contribute to short circuit power
Costly and difficult overhead line paths in a city centre can be avoided by
cabling
It ensures better conductor utilization
It provides for three times the capacity, using the same conductors
It has an even higher capacity with new towers in an existing right of way
It makes it possible to control reactive power in a city centre
It ensures increased system stability
It provides for increased power capacity in parallel AC lines
It provides for controlled power flow
It provides for double circuit performance of a converted single circuit AC
line
There is higher power without increased short circuit power
There is better control of the line load factor
HVDC TRANSMISSION
Disadvantages of using HVDC links :
Economical only for long distances
Harmonics are generated due to semiconductor devices
used- checked by filters
Costs in HVDC links :
Converter stations : the valves made of series connected
thyristors modules, no parallel connection needed
Converter transformers : to achieve galvanic separation
between DC and AC side
Switchgear : used for clearing faults, must be highly
reliable and maintainable
Load level
Supply
Voltage levels should be max 3
voltage
above LV value
Upto 60 KW
LT supply
EHV level / lower level > 3
60 KV - 50 MW 11 KV
HV level / lower level > 5
5 30 MVA
33 / 66 KV
Reduction in no. of levels allows
30 50 MVA
132 KV
increased length of MV systems
>50 MVA
220 KV
THERMAL LOADING
Loading limit is decided by :
ambient temperature varies with location and
season
maximum permissible conductor temperaturespecified for standard sizes
Loading(MVA) based on
40 deg
225
257
258 sq.
mm
45 deg
189
225
ACSR
40 deg
943
1077
345sq.
mm
45 deg
785
943
ACSR
DESPATCHABILITY : LOADING
System should be planned such that :
It is self sufficient as well as suitable for sharing with
neighbours
Maximum angular separation between bases : 40 deg for
steady state
Should stand outage of 2 circuits of 220 KV system/1 circuit
DESPATCHABILITY : SECURITY