Professional Documents
Culture Documents
Estimating completion
times
Week 9 Supplement: explaining the statistics
09-01
a 4m b
Duration = TE
6
Variance is defined as s2
Pessimistic time
Activities complete in times
greater than the pessimistic
time with p=0.01
TE
Since the activity durations are skewed towards pessimistic durations the activity duration Time Estimate (TE) will be
slightly greater than m, the most likely activity completion time
Activities will complete sometime between times a and b, with p = 0.98
Activities will complete in time greater than Activity TE with p = 0.5, and complete in time less than Activity TE with p = 0.5
Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall
09-3
distribution
Variations in activity completion times can affect project
completion time
Completion times will be clustered around most likely time
Project completion time estimate (TE)
Sum of the completion times of activities on the critical path
Ignores activities not on the critical path: a simplifying
assumption
Project completion time variance
Sum of the variances in completion times, for activities on the
critical path
Project completion times should fall within +/- 3 standard
deviations of average completion time: 99.7% of completion
times
4
2013
Copyright
Project
Pearson
Standard
Education, Inc.
Deviation
Publishing as
=Prentice Hall
TE; Z =0
Since the activity Time Estimates (TEs) are skewed towards pessimistic durations, and because the project Time Estimate
(TE) is the sum of the TEs for activities on the critical path, the project TE will be slightly greater than the most likely time for
project completion. Since the individual project TE has already accounted for the skew in activity completion times, the
09-5
Copyrightofproject
2013 TEs
Pearson
Education, Inc. Publishing as Prentice Hall
distribution
is symmetrical.
2.5%
0.975
= 1-0.95 = 0.05
1- /2 = 1- 0.05/2 =
0.025
From the Normal
Distribution table
Z 1-0.25 = Z 0.975 = 1.96
2.5%
95%
-Z
0.975
P = 0.95 that completion time falls within the range of TE +/- Z times S
Since Z = 1.96, then completion time falls within the range of TE +/- 1.96 * S
09-7
If p = 0.95 that
project will
complete within a
certain time
This is equivalent
to p = 0.975 that
project will
complete by a
certain time; or
p (late) = 0.025
For p =0.975
we find Z= 1.96
http://www.six-sigma-material.com/Normal-Distribution.html
Optimisti
c (a)
Most
Likel
y
(m)
Pessi
misti
c (b)
A
A
3
3
4
4
11
11
Expected
Expected
time of
critical path
activities
5
5
Activity time
Variance
[(b-a)/6]
(
= 1.78
B
2
5
8
5
1.00
B
2
5
8
5
1.00
C
3
6
9
6
6
1.00
C
3
6
9
6
6
1.00
D
8
12
20
12.7
13
4.00
D
8
12
20
12.7
13
4.00
E
3
5
12
5.8
2.25
E
3
5
12
5.8
2.25
F
2
4
7
4.2
4
0.69
F
2
4
7
4.2
4
0.69
G
6
9
14
9.3
1.78
G
6
9
14
9.3
1.78
H
1
2
4
2.2
2
0.25
H
1
2
4
2.2
2
0.25
Projec
Projec
Expected project completion time: 30 Sum of expected activity30
completion times = 30
t
30
Variance
in
project
completion
time:
7.72
;
and
standard
deviation
= 7.72 = 2.78
t
Variance of
critical path
activities
only
1.78
1.78
1.00
1.00
4.00
4.00
0.69
0.69
0.25
0.25
7.72
7.72
Individual activities are independent of each other. Add the variances for activities on the Critical Path A-C-D-F-H = 7.72.
Variance in completion time for activities not on critical path, would not contribute to variances in project completion time
Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall
Z as a proportion of S:
2 / 2.78 weeks = 0.72
Look up Z = 0.72 in Pearson
P. 349, to find p= 0.7642
Probability of Completion by a
specified time = p
Determine p based on Z
statistic
Z=0
Time inWeeks
30
Copyright
2013 Pearson Education, Inc. Publishing
as Prentice32
Hall
Z = 0.72
09-10
From
Z= 0.72
We find
p = 0.7642
http://www.six-sigma-material.com/Normal-Distribution.html
11
12
13
Completion time = TE + Z *S
= 30 weeks + 1.65 * 2.78 weeks
= 34.59 weeks
Probability of Completion by a
specified time = p
Determine p based on Z
statistic
Z=0
Time inWeeks
30
34.59
Copyright
2013 Pearson Education, Inc. Publishing
as Prentice
Hall
Z = 1.65
09-14
We find
Z= 1.65
From
P = 0.95
http://www.six-sigma-material.com/Normal-Distribution.html
15
16