Professional Documents
Culture Documents
No Load
Loss(kW)
Rated Load
Loss (kW)
Monthly
No Load
Energy
loss(kWh)
Monthly
Load Loss
(kWh)
Total Energy
loss (kWh)
Percentage
Energy Loss
25
0.10
0.30
72.00
27.65
99.65
2.31%
50
0.17
0.50
122.40
11.52
133.92
3.10%
100
0.30
0.85
216.00
4.90
220.90
5.11%
160
0.44
1.30
316.80
2.93
319.73
7.40%
200
0.60
1.60
432.00
2.30
434.30
10.05%
Loss Summary
LT loss scenario
Other Factors
The loss also depends on conductor size
Thick conductor: less loss
Thin conductor: more loss
E.g the loss with dog conductor is about 1/3 rd of
loss with weasel conductor
Summary
Transformer should be appropriately installed to
minimized transformer loss. It should not be oversized.
The load center size should be as small as possible.
The feeder should be configured so that the consumers
should be as close to the source ( transformer).
To reduce the percentage loss its required to increase
the other activities than lighting only. As far as possible
minimize other use during peak hours.
While connecting consumers to supply phase balancing
should be keep in mind.
Thick conductor cause less loss but high cost
compromise is done to select appropriate conductor
Location of transformer
As far as possible the Distribution transformer must be
located at the center of gravity the Load center
In rural areas some times a single transformer is used to
serve 2,3 or more small villages located in proximity.
In such case following theoretical approach may be used to
locate approximate transformer location.
Take a reference point on the x, y coordinate, The location
X, Y is then find using,
Let's consider five different distribution transformers of same size and same
number of customers are desired to be connected from the substation
through a radial distribution feeder of similar conductor. Out of practically
feasible feeder layout options two are shown in Fig.(a) & (b).
2 km
S/S
2 km
2 km
2 km
S/S
2 km
2 km
2 km
2 km
2 km
2 km
(a) Option-A
Note that:
(b) Option-B
But it can be shown that the losses in option A is about 1.5 times
greater than option-B
2 km
5S
3S
2 km
2S
2 km
(a) Option-A
2 km
S/S
2 km
2 km
2 km
5S
3S
2 km
(b) Option-B
Node
Traveling
dist
ance
Probability
of
failur
e/yr
Probable No. of
consumer not
getting supply/yr
0.08
0.16
16
0.24
24
0.16
16
0.24
24
A
1+2j
1+2j
C
1+2j
1000 kVA
33/11kV
100 kVA
100 kVA
100 kVA
Service area
Input/Output voltage level
Sitting
Sizing
Source Grid Substation
High Voltage & low voltage side configuration
(e.g HT bus bar arrangement, No. of LV feeders,
No. of Transformer etc.)
Substation sitting
Availability of land for the various necessary equipment of the
required capacity and required number of distribution feeders for
the identified service area of the substation.
The cost of land.
Opportunity for Feeder getaway
The cost of preparing the site (slope, drainage, underlying soil and
rock)
The cost of transporting material
Esthetic requirements (fencing, landscaping)
Available options for expanding the substation capacities, addition
of distribution feeder and extension of sub transmission line for the
new substation that may come in future.
Right of way for transportation of substation equipments