Professional Documents
Culture Documents
Highway
Highway Engineering 2
Introduction
Practice of engineering involve many choices among
alternative designs, procedures, plans, and methods.
Question will the benefit of the project worth the cost?
(Will it pay?)
Basic questions and issues what approach to be
taken, what data are needed, what analytical
techniques to be used.
Alternative 1
Install gates and flashing light
Alternative 2
Construct a grade separated overpass
Objectives
General objective : to furnish the appropriate information about the outcome of each
alternative so that the selection can be made.
Some of the specific objectives in carrying out economic evaluation are:
I.
II. To rank the scheme competing for scarce resources in order of priority
III. To compare and select the most economic and
IV. To assist in phasing the program
Basic Principles
2. Consider total cost each alternatives, including user and facility, -> select
project with
lowest total cost
Need to identify elements of cost:
1. facility costs construction, maintenance, operation
2. user costs travel time, accidents, vehicle operating cost (voc)
Facility Costs
Two components:
first cost (design, row (right of way), construction)
- continuing cost (annual maintenance, operation and administration)
Formulae
F
To find A, given P (A/ P-i-n) :
A=P[ ]
To Find F, given A (F/ A-i-n) :
F=A[ ]
Present Worth
PW the most straight forward since represent current value of all the costs that will be
incurred over the lifetime of the project.
PW =
= Facility and user costs incurred in year n
n = service life
i = discount rate
Example:
As a routine maintenance work, RM.20 000/- each is to be spent on a particular stretch of a
highway during the 3rd year, 5th year and the 7th year.
Calculate the total present worth of these expenditures, if the annual discount rate is 12%.
Present Worth
Example:
As a routine maintenance work, RM.20 000 each is to be spent on a particular stretch of a
highway during the 3rd year, 5th year and the 7th year.
Calculate the total present worth of these expenditures, if the annual discount rate is
12%.
The present worth of the maintenance investment
is
1
1
1
RM 20,000
3
5
7
1.12
1.12
1.12
NPW = [ ]
where,
Bn is the benefit of the nth year,
Cn is the cost of the nth year,
n is the number of years.
Or
Example 1 NPW
The cost of improving an existing road, 25 km stretch is RM 4 million per km. The costs
of road users, accident and maintenance for with and without improvement are
tabulated below for a 10 year period after the completion of the improvements.
Assuming a discount rate of 10% find out whether the project is economically viable.
Use NPW method.
Year
Road User Costs
Accident Costs
Maintenance
Benefit
NPW
(n)
Costs
With
Without
With
Without
With
Without
-100
105.5
126.5
1.1
3.1
3.5
2.5
110.3
132.2
1.1
3.1
3.5
2.5
115.8
138.9
1.2
3.5
3.5
2.5
121.6
145.8
1.2
3.7
3.5
2.5
-100
Example 1 NPW
Year
(n)
Accident Costs
Maintenance
Costs
With
Without
With
Without
With
Without
134.0
161.0
1.3
4.0
3.5
2.5
140.7
168.9
1.4
4.0
3.5
2.5
147.8
177.0
1.5
4.4
3.5
2.5
155.1
186.2
1.6
4.7
3.5
2.5
Benefit
NPW
10
162.9
195.2
1.6
4.9
3.5
2.5
Continued
Total
Cost of improvements = RM 4 million x 25 km = 100 million
NPW = RM --- million, since the NPW is positive, the project is economically viable
Example 2 NPW
Example 2 NPW
Alternative
Constructio
n Cost
Annual
Saving in
accident
Annual
Travel Time
Benefits
Annual
Operating
Savings
Annual
Additional
Maintenanc
e Cost
$ 185 000
$ 5 000
$ 3 000
$ 500
$ 1 500
ll
$ 220 000
$ 5 000
$ 6 500
$ 500
$ 2 500
lll
$ 310 000
$ 7000
$ 6 000
$ 2 800
$ 3 000
The ratio of the present worth (PW) of Net project benefits (all of the savings, revenue
& etc) and Capital costs is called the benefit cost ratio (BCR).
BCR used to show extend to which investment will result in benefit to society
Negative flows are considered costs and positives flows as benefits.
The saving in the transport cost are considered as benefits.
If the B/C ratio is more than one, the project is worth undertaking.
Need to do comparison to determine added benefit with added investment
BCR 2/1 = (B2 B1) / (C2 C1)
B/C = benefit in the reference year / Capital costs
Example 1 BCR
Example 1 BCR
Existing road
Improved road
Benefits
Annual :
Road user cost
RM 2.00 x 2500 x
365 x 40 = 73
millions
RM 1.50 x 2500 x
365 x 40 = 54.75
millions
RM 73 -54.75 =
RM 18.25 millions
Annual :
Maintenance costs
RM 220 000
RM400 000 =
-180 000
18.25 0.18 =
18.07
Capital cost of
improvements
Annual :
Cost of improvement
RM 80 x (A/P 10 20)
RM 80 x 0.11746 = RM 9.40 M
Example 2 BCR
The department of Traffic is considering three improvement plans for a heavily
traveled intersection within the city. The intersection improvement is expected to
achieve three goals : to improve travel speeds, to increase safety and to reduce
operating expenses for motorists. The annual dollar value of savings compared with
existing conditions for each criterion as well as additional construction and
maintenance costs is shown in table. If the economic life of the road is considered to
be 50 years and the discount rate is 3 percent, which alternative should be selected?
Solve the problem using the BCR methods for economic analysis.
Alternative Constructio
Annual
Annual
Annual
Annual
n Cost
Saving in
Travel Time
Operating
Additional
accident
Benefits
Savings
Maintenanc
e Cost
I
$ 185 000
$ 5 000
$ 3 000
$ 500
$ 1 500
ll
$ 220 000
$ 5 000
$ 6 500
$ 500
$ 2 500
lll
$ 310 000
$ 7000
$ 6 000
$ 2 800
$ 3 000
BCR l/DN = [(-1500 + 5000 + 3000 + 500) / (185 000 x (A/P -3-50)]
BCR ll/DN = ?
BCR lll/ll or BCR lll/DN =