Professional Documents
Culture Documents
Abbhimanyu Gartia,
Dy General Manager, WRLDC, MUMBAI
In this Presentation
Historical Background
Evolution
Regional Postage Stamp Method
Drivers of Change
POC Mechanism Features
Issues
Regulation Amendment and Related Orders
Historical Background
Historical Background
explicit
allocation
source located
Transmission charges of intermediate regions involved in
Pancaking in Losses
5%
Drawee
Entity in NR
88.46 MW
4%
ER-NR
Boundary
93.12 MW
3%
NER-ER
Boundary
97 MW
Generation
Located in
NER
100 MW
Drivers of Change
47
4830
Generating Stations
557
Generating Units
1148
Loads
2672
Branches
Transformers
DC Lines
765 kV
400 kV
622
220 kV
3034
132 kV
5130
Total
8795
2031
load
New Pricing Framework
a necessity rather than a choice
Policy Mandate
Provisions of National Electricity Policy
Section 5.3.2
Network expansion should be planned and
implemented keeping in view the anticipated
transmission needs that would be incident on
the system in the open access regime. Prior
agreement with the beneficiaries would not be a
pre-condition for network expansion. CTU/STU
should undertake network expansion after
identifying the requirements in consultation
with stakeholders and taking up the execution
after due regulatory approvals.
Policy Mandate
Section 5.3.5
Policy Mandate
Provisions of Tariff Policy
Section 7.1(2)
The National Electricity Policy mandates
that
the
national
tariff
framework
implemented should be sensitive to
distance, direction and related to quantum
of power flow. This would be developed by
CERC taking into consideration the advice
of the CEA. Such tariff mechanism should
be implemented by 1st April 2006
Policy Mandate
Section 7.1(2)
Transmission charges, under this framework,
Policy Mandate
Section 7.1(4)
Policy Mandate
Section 7.1(7)
Policy Mandate
Section 7.2
Transmission Losses
Transactions should be charged on the
basis of average losses arrived at after
appropriately considering the distance and
directional sensitivity, as applicable to
relevant voltage level, on the transmission
system. Based on the methodology laid
down by the CERC in this regard for interstate
transmission,
the
Forum
of
Regulators may evolve a similar approach
for intra-state transmission.
Regulatory Initiatives
Discussion Paper on Sharing of Charges and losses
(2007)
Regulation
on
Sharing
of
Inter-State
Transmission Charges and Losses (February 2010)
NLDC
22
PoC Mechanism
Distance Sensitivity
Direction Sensitivity
Quantum Sensitivity
Average Participation
Tracing of Power
Load Tracing
Generator Tracing
NLDC
25
Marginal Participation
Marginal Participation
The charges are based on incremental utilization of
network assessed through load flows.
NLDC
26
Hybrid Methodology
Hybrid of
Average Participation
Marginal Participation
Average Participation
Marginal Participation
NLDC
27
Distance Sensitivity
Flow of electricity
Conductor Impedance
Charges of Transmission Lines
Direction Sensitivity
ZONE A
Quantum Sensitivity
Access vs Usage
Planning based on Access
Usage reflected in PoC Rates
Access is reflected in charges payable
Preparation of
Basic Network &
Load Flow
Studies
Scaling of PoC
Rates to Recover
Total Charges
Zoning of Nodes
(Generation Nodes
and Demand
Nodes)
Network
Truncation &
Load Flow
Studies on
Truncated
Network
Computation of
Nodal Charges
(Average and
Marginal
Participation)
ZoningSample Case
Bus
Name
Owner
BAWANA
DEL_TH
-G
BAMNOL
DEL_STU
4
BAWANA
DEL_STU
4
MAHARA
NR_PGCIL
NI
MANDOL
NR_PGCIL
A
PANIPAT
BBMB
*
Total
Generati
on
Charges
Load
Charges
Generati
on
Load
31242888
388
59138840
645
39132218
425
17697566
295
77146314
793
10870697
163
31242888
203985637
388
2321
Total Charges
Total LTA
100000
110000
85000
95000
70000
80000
NEW Grid
SR Grid
Average Loss
Siting Signals
Hydro Generation Location
PoC Method
(approx)
Total LTA : 47000 MW (approx)
Total Zones : 71 (Nodes: 500 approx)
Uniform Rate
NEW Grid : 80000 Rs/MW/Month
SR Grid : 90000 Rs/MW/Month
20/12/15
POSOCO
43
ISSUES
Discussed in SOR
Grid
Regional boundaries losing significance
Trans Regional ISGS
Increasing Inter Regional Flows
Meshed Network
Regional Pool
Signal for planning
NEP 2005 and Tariff Policy 2006
Single Scenario
Unavailability of Data
Adjustment Prone/Gaming/Disputes
Authentic Data Published by CEA
Single PoC Rate
Easy to Comprehend
Stable Signal
Market Friendly
Way Forward
Implement, Gain Experience & Ramp Up
Improvements in PoC mechanism based on the
experience gained
Similar Mechanism to be replicated in states.
Section 7.1(7) of the amended Tariff Policy:
After coming into effect of the CERC Regulation on the framework
for inter-State transmission, a similar approach should be
implemented by the SERCs in next two years for the intra-State
transmission, duly considering factors like voltage, distance,
direction and quantum of flow.
Definition of YTC:
Sub-clause (y) of clause (1) of Regulation 2
substituted as:
Amendment to Regulation 11 of
Principal Regulations
Revenue collected from Approved Additional MTOA in a
beneficiaries
Injection PoC Charges plus lowest of Demand PoC Charge among all
DICs in target region for remaining quantum after offsetting MTOA
Amendment to Regulation 11 of
Principal Regulations
Injection PoC and Demand PoC charges for STOA to
identified beneficiaries
Thank You