Overview
• Define Master Production Schedule
• Explain MPS
• Discuss How MPS Works
• Example From “Real Life”
• Brainstorm: How Can MPS Help Your
Firm?
• Practice MPS Logic
What is MPS?
• Master Production Schedule –
States the requirements for
individual end items by date and
quantity. -APICS
MPS Explained
• Marketing communicates
demand through customer
orders and forecasts
• Operations communicates
capacity through inventory
levels and constraints
Resource Availability
Control
• Production shortfalls will be
known ahead of time and
alternative plans can be made.
Customer Service
• Proactively control ability to
deliver goods to customers
Inventory Control
• Proactive approach to inventory
control
– Items are scheduled to arrive when
needed
– Safety stock has less importance
Planning Organization
S a le s a n d O p e r a tio n s P la n R e s o u r c e P la n n in g
M a s t e r P r o d u c t i o n S c h e d u le R o u g h C u t C a p a c ity P la n n in g
M a t e r ia ls R e s o u r c e p la n n in g C a p a c it y R e q u ir e m e n t s P la n
S h o p F lo o r C o n t r o l In p u t/O u tp u t
How MPS Works
• Information needed for MPS
logic
– Lot Size
– Lead Time
– Product Demand
– Starting Inventory
How MPS Works Cont.
2
W Inc. MPS for Widgets
Lot Size = 25 units
Lead Time = 0 periods
Period 1 2 3 4 5
Demand 30 30 30 30 30
Available 20 15 10 5 0
MPS 50 25 25 25 25
Jet Spray Corp. Example
Period 1 2 3 4 5 6 7
Demand 25 25 25 0 15 35 25
Available
MPS 50
Summary
• MPS breaks the Sales &
Operations plan into product
families
• Maintains Desired Level of
Customer Service
• Allows proactive control of
inventory
Bibliography
• Sources:
• Cox III, James F., and Blackstone Jr., John H.,
eds. APICS Dictionary. 1998