REDSIP Hydropower Projects

Procurement of Plant, Design, Supply and Install of Marala


Hydropower Project (ICB # PB-001)
Procurement of Plant, Design, Supply and Install of Chianwali
Hydropower Project (ICB # PB-002)
Procurement of Plant, Design, Supply and Install of Deg Outfall
Hydropower Project (ICB # PB-003)
Procurement of Plant, Design, Supply and Install of Pakpattan
Hydropower Project (ICB # PB-005)

DECEMEBR 23,
23 2015

7.64 MW
5.38 MW
4.04 MW

4.16 MW

2.82 MW

GENERAL INFORMATIONS
MARALA
Location

UCC RD
3+350

CHIANWALI
UCC RD
131+117

DEG
OUTFALL
UCC RD
282+735

PAKPATTAN
Pakpattan
Canal RD
114+800

Design
Discharge
(cumec)

420

150

120

80

Rated Head
(m)

2.16

4.20

4.00

4.20

Power
Potential
(MW)

7.64

5.38

4.04

2.82

Annual
Energy
(GWh)

43.47

28.22

26.46

20.86

Plant Factor
(%)

65.56

59.88

74.52

84.38

Amount of

Pak Rs

Pak Rs

Pak Rs

Pak Rs

Procurement of Plant, Design, Supply and Install of

Chianwali Hydropower Project


(ICB # PB-002)

Chianwali Hydropower Project

PROJECT
LAYOUT

POWERHOUSE AT RD 131+250

(ICB # PB-002)

Chianwali Hydropower Project


Old
RDs

New
RDs

Last
Design

Proposed
Design

BL

BL

FSL

FSL

(FPS)

Last Design
Q

FSD

Proposed Design
S

FSD

128+0
723. 734. 723.9
10225
0.0001 10225 246.0
0.0001

734.41
246.00 10.50 1.15
10.50 1.15
00
91
41
1
.0
5
.0
0
5
128+0
718. 729. 723.9
9569.
0.0001 9569. 237.0
0.0001

734.41
237.00 10.40 1.15
10.50 1.15
00
80
20
1
0
5
0
0
5
129+2 129+20 718.6 729.0 723.6
734.19
237 ~
00
0
2
2
9
9569.
0.0001 9569.
0.0001
237.00 10.40 1.15
294.3 10.50 1.15
0
5
0
5
131+10 718.3 728.7 723.4
6

733.90
0
4
4
0

Powerhouse

Powerhouse

131+37 718.2 728.6 712.9


723.39
294.3
5
9
9
6
9569.
0.0001 9569.
0.0001
237.00 10.40 1.15
6 ~ 10.40 1.15
0
5
0
5
133+14 718.0 728.4 712.7
237

723.12
1
3
3
2
133+0
718.0 728.4

17
5
5
134+0
717.9 728.3 712.5

722.97
00
0
0
7
9569.
0.0001 9569. 237.0
0.0001
237.00 10.40 1.15
10.40 1.15
0
5
0
0
5
164+0
713.3 723.7 708.0

718.47
00
5
5
7
164+4
713. 723. 708.0

718.41
00
29
69
1
164+4
708. 718. 708.0

718.41
00
09
29
1
9014.
0.0001 9014. 230.0
0.0001
230.00 10.20 1.10
10.20 1.10
0
5
0
0
5
165+0
708.0 718.2 708.0

718.20
00
0
0
0

Government of the Punjab

CHP Combined Powerhouse & Spillway


Plan

Government of the Punjab

CHP Powerhouse Longitudinal Section

Government of the Punjab

CHP Spillway Plan

CHP : Energy Computations in Detailed Design

Procurement of Plant, Design, Supply and Install of

Deg Outfall Hydropower Project


(ICB # PB-003)

PROJECT LAYOUT (Deg Outfall)

POWERHOUSE RD 282+100

Deg Outfall Hydropower Project (FPS)


Old
RDs

New Last Design


RDs
BL
FSL

266+0

00
266+0
00

267+00
0

280+00
0

280+88
9

280+8
89

282+
611

282+
968

283+0
00

283+1
00
283+1
00
284+6

42

Proposed
Design
BL

FSL

671.3 681.1 671.3


681.10
0
0
0
669.3 679.1 671.3
681.10
0
0
0
669.1
671.1
678.95
680.95
5
5
667.2
669.2
677.00
679.00
0
0
667.0
669.0
676.87
678.87
7
7
667.0
669.0
676.87
678.87
7
7
666.8
668.8 678.6
676.61
1
1
1

Powerhouse
666.7
657.5 667.3
676.55
5
2
2
666.7
657.5
676.55
667.32
5
2
666.7 676.5 657.5
667.30
4
4
0
657.5 667.3 657.5
667.30
0
0
0
657.2

667.07
7

Last Design
Q

FSD

Proposed Design
S

FSD

8145.
0.0001 8145.
0.0001
224.00 9.80 1.10
224.00 9.80 1.10
0
5
0
5

8145.
0.0001 8145.
0.0001
224.00 9.80 1.10
224.00 9.80 1.10
0
5
0
5

8145.
0.0001 8145. 224 ~
0.0001
224.00 9.80 1.10
9.80 1.10
0
5
0 291.40
5

8145.
0.0001 8145.
224.00 9.80 1.10
0
5
0

Powerhouse

291.40
0.0001
~
9.80 1.10
5
224

Government of the Punjab

DHP Combined Powerhouse & Spillway


Plan

14

Government of the Punjab

DHP Powerhouse Longitudinal Section

15

Government of the Punjab

DHP Spillway Plan

16

DHP: Energy Computations in Detailed Design

Procurement of Plant, Design, Supply and Install of

Marala Hydropower Project


(ICB # PB-001)

Marala Hydropower Project

(ICB # PB-001)

PROJECT LAYOUT
MR
UC
C

LI

NK

CA
NA
L

SPILLWAY RD 3+155
HEADRACE CHANNEL

POWERHOUSE RD 3+350
TAILRACE CHANNEL

COLONY

Marala Hydropower Project

(ICB # PB-001)

Marala Hydropower Project (FPS)


Proposed
Design

New Last Design


RDs
BL
FSL
BL
FSL
803.1
810.0
0+000
791.16
798.00
6
0

Old
RDs

1+000

791.01 803.01 797.85 809.85

2+000

790.86 802.86 797.70 809.70

2+116

790.84 802.84 797.68 809.68

2+116

797.68 809.68

3+000

797.55 809.55

3+21
8

797.5 809.5
2
2

FSD

16850 320.00 12.00

3+66
5

790.6 801.8
4
0

4+000

790.59 801.75

4+460 4+661
4+460
5+000

Proposed Design
S

FSD

0.0001
0.0001
16850 320.00 12.00
5
5

14832 293.64 12.00

Powerhous
e

Last Design

0.0001
5

Powerhouse

14832 328.74 11.16

0.0001
5

790.49 801.65

790.49 802.49 790.49 802.49


790.41 802.41 790.41 802.41

16850 320.00 12.00

0.0001
0.0001
16850 320.00 12.00
5
5

Government of the Punjab

MHP Powerhouse Plan

MHP Powerhouse Section

Government of the Punjab

Karrif
level
Rabi
level

MHP: Energy Computations in Detailed Design

Procurement of Plant, Design, Supply and Install of

Pakpattan Hydropower Project


(ICB # PB-005)

PROJECT LAYOUT - PHP

26

Pakpattan Hydropower Project (FPS)


Last Design
OLD
RDs

NEW
RDs
BL

FSL

Proposed
Design
BL

FSL

Proposed
Design

Last Design
Q

FSD

112+35
0

542.09 551.59 542.09 551.59 6309 186.00 9.50 0.000120 6309 186.00

0.00012
0

113+00
0

532.55 541.05 542.67 551.17 3976 150.00 8.50 0.000125 3976 177.00

0.00012
5

113+11 113+1
0.00012
532.53 541.03 542.65 551.15 3976 150.00 8.50 0.000125 3976 177.00
4
14
5

114+6
0.00012
532.34 540.84 542.46 550.96 3976 150.00 8.50 0.000125 3976 177.00
90
5

532.32 540.82

Powerhouse 3976 150.00 8.50 0.000125

Powerhouse

114+9
150.0 0.00012
532.30 540.80 529.80 538.30 3976 150.00 8.50 0.000125 3976
68
0
5

116+33 116+4
0.00012
532.13 540.63 529.62 538.12 3976 150.00 8.50 0.000125 3976 150.00
8
67
5
124+95
0

531.06 539.56 528.54 537.04 3976 150.00 8.50 0.000125 3976 150.00

0.00012
5

124+95
0

528.54 537.04 528.54 537.04 3958 150.00 8.50 0.000095 3958 150.00

0.00009
5

Government of the Punjab

PHP - POWER HOUSE

PHP: Energy Computations in Detailed Design

Progress of REDSIP Projects

MARALA HYDROPOWER PROJECT


WORK SCHEDULE & PROGRESS

MARALA HYDROPOWER PROJECT


PROJECT NAME
Contract Cost Rs. 3050 Million
Sr.
No.

Project Components

Financial Contrac
Weightag
t
Planned Achieved Planned Achieved
e w.r.t
Cost
Physical Physical Financial Financial
Project
(M
Progress Progress Progress Progress
Cost
PKR)

OVERALL PROJECT

100%

3050

96.12%

80.12%

96.12%

74.99%

DESIGN SERVICES FOR CIVIL WORKS

3.54%

108

100.00%

98.50%

100.00%

98.19%

DESIGN SERVICES FOR PLANT(E&M)

1.54%

47

100.00%

95.00%

100.00%

81.42%

PROCUREMENT OF E&M EQUIPMENT

37.02%

1132

100.00%

87.12%

100.00%

63.86%

CONSTRUCTION OF EMPLOYER'S FIELD FACILITIES

3.73%

114

100.00%

52.28%

100.00%

47.27%

1.74%

53

100.00%

66.68%

100.00%

48.23%

8.74%

267

100.00%

98.64%

100.00%

94.86%

38.65%

1179

100.00%

92.61%

100.00%

89.93%

5
6

CONSTRUCTION OF POWER CANAL INCLUDING


HEAD & TAIL RACE
CONSTRUCTION OF SPILLWAY INCLUDING
DIVERSION CHANNEL

CONSTRUCTION OF POWER HOUSE(Civil)

RAISING OF BANK OF UCC

1.01%

31

100.00%

49.33%

100.00%

17.40%

ACCESS ROAD

0.06%

100.00%

0.00%

100.00%

0.00%

10

E&M ELCTROMECHNICAL INSTALLATIONS

3.82%

117

95.00%

34.26%

95.00%

21.57%

11

INTERCONNECTION STUDY AND TRANSMISSION


LINE

0.15%

100.00%

10.00%

0.00%

0.00%

Plan % will be revised according to EOT-2 submitted.

PAKPATTAN HYDROPOWER PROJECT


WORK SCHEDULE & PROGRESS
PAKPATTAN HYDROPOWER PROJECT
PROJECT NAME
Contract Cost Rs. 1048 Million

Sr.
No.

Project Components

Financial
Contract
Weightage
Planned Achieved
w.r.t
Physical
Physical
Cost
Project
Progress Progress
(M PKR)
Cost

Planned Achieved
Financial Financial
Progress Progress

OVERALL PROJECT

100%

DESIGN SERVICES FOR CIVIL WORKS

1.42%

15

100.00%

99.00%

100.00%

97.64%

DESIGN SERVICES FOR PLANT(E&M)

6.19%

65

100.00%

95.00%

100.00%

80.26%

PROCUREMENT OF E&M EQUIPMENT

37.65%

405

100.00%

88.12%

100.00%

52.17%

5.66%

59

100.00%

93.30%

100.00%

89.50%

4.53%

47

100.00%

100.00%

100.00%

100.00%

4
5

CONSTRUCTION OF EMPLOYER'S
FIELD FACILITIES
CONSTRUCTION OF POWER CANAL
INCLUDING HEAD & TAIL RACE

1048 100.00% 85.12% 100.00% 76.16%

CONSTRUCTION OF SPILLWAY (Civil)

12.75%

134

100.00%

100.00%

100.00%

100.00%

CONSTRUCTION OF POWER
HOUSE(Civil)

19.26%

202

100.00%

100.00%

100.00%

100.00%

CONSTRUCTION OF BRIDGES

3.97%

42

100.00%

100.00%

100.00%

99.10%

EXCAVATION OF PAKPATTAN CANAL

3.21%

34

100.00%

100.00%

100.00%

100.00%

ACCESS ROAD

0.47%

100.00%

0.00%

100.00%

0.00%

3.19%

33

100.00%

62.38%

100.00%

23.90%

1.70%

100.00%

10.00%

100.00%

0.00%

10
11
12

E&M ELCTROMECHNICAL
INSTALLATIONS
INTERCONNECTION STUDY AND
TRANSMISSION LINE

Plan % will be revised according to EOT-2 submitted.

DEG OUTFALL HYDROPOWER PROJECT


WORK SCHEDULE & PROGRESS
DEG OUTFALL HYDROPOWER PROJECT

PROJECT NAME

Sr.
No.

Project Components

OVERALL PROJECT

Design Services for Civil Works

Design Services for Plant

Procurement of E&M Equipment

Construction of Employer's Field Facilities

Construction of Power Canal (Head & Tail Race)

Construction of Spillway

Construction of Power House(Civil)

8
9
10
11

Raising of Bed and Bank of UCC


Dismantling and Removal of Fall Structure
Relocation of Feeder & Construction of New
Outlets
Construction of Bridges

12

Construction of Aquaduct & Distributry

13

Strengthening of Foundation of Road Bridges

14

Machine Hall

15

Control Building

16

Access Road

17

E&M ELCTROMECHNICAL INSTALLATIONS

18

INTERCONNECTION STUDY AND TRANSMISSION


LINE

Plan % will be revised according to EOT submitted.

Contract Cost Rs. 1668 Million

Financial Contract
Planned
Weightage
Physical
w.r.t Project Cost
Progress
Cost
(M PKR)

100%

Achieved
Physical
Progress

Planned Achieved
Financial Financial
Progress Progress

1668 78.45% 63.60% 78.45% 52.34%

3.86%
4.83%
28.03%
7.26%
5.74%
9.78%
25.57%
1.34%
0.30%

64
81
485
121
96
163
427
22
5

98.00%
98.00%
100.00%
100.00%
76.12%
90.00%
100.00%
100.00%
0.00%

96.80%
90.00%
66.74%
84.90%
59.70%
70.70%
96.70%
0.00%
0.00%

98.00%
98.00%
100.00%
100.00%
76.12%
90.00%
100.00%
100.00%
0.00%

94.56%
75.44%
18.40%
81.20%
58.89%
53.31%
95.65%
0.00%
0.00%

1.54%

26

100.00%

18.20%

100.00% 12.05%

0.52%
1.16%
0.40%
3.23%
1.94%
0.06%

9
19
7
54
32
1

100.00%
100.00%
0.00%
100.00%
100.00%
85.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

100.00%
100.00%
0.00%
100.00%
100.00%
85.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

2.94%

49

52.00%

25.00%

24.61%

24.61%

1.5%

80.00%

15.00%

0.00%

0.00%

CHIANWALI HYDROPOWER PROJECT


WORK SCHEDULE & PROGRESS
CHIANWALI HYDROPOWER PROJECT

PROJECT NAME

Sr.
No.

Project Components

Contract Cost Rs. 2160 Million

Financial
Weightag Contract Planned Achieved Planned Achieved
e w.r.t
Cost
Physical Physical Financial Financial
Project (M PKR) Progress Progress Progress Progress
Cost

OVERALL PROJECT

100%

2160

DESIGN SERVICES FOR CIVIL WORKS

4.24%

92

92.00%

88.32%

92.00%

87.22%

DESIGN SERVICES FOR PLANT

2.77%

60

92.00%

90.00%

92.00%

75.37%

PROCUREMENT OF E&M EQUIPMENT

24.09%

552

100.00%

65.34%

100.00%

19.00%

5.83%

126

100.00%

34.00%

100.00%

33.26%

3.78%

82

82.20%

39.30%

82.20%

38.86%

4
5

CONSTRUCTION OF EMPLOYER'S FIELD


FACILITIES
CONSTRUCTION OF POWER CANAL
INCLUDING HEAD & TAIL RACE

73.84% 44.80% 73.84% 35.38%

CONSTRUCTION OF SPILLWAY

11.78%

254

87.20%

23.70%

87.20%

14.12%

CONSTRUCTION OF POWER HOUSE(civil)

21.33%

461

100.00%

87.50%

100.00%

86.77%

CONSTRUCTION OF BRIDGES

6.05%

131

70.00%

16.20%

70.00%

10.11%

CONSTRUCTION OF FEEDING CHANNEL

9.18%

198

88.10%

0.00%

88.10%

0.0%

10

EXCAVATION OF UCC

6.56%

142

0.00%

0.00%

0.00%

0.0%

11

ACCESS ROAD

0.10%

75.00%

0.00%

75.00%

0.0%

12

E&M ELCTROMECHNICAL INSTALLATIONS

2.29%

49

48.00%

32.00%

31.97%

31.97%

12

INTERCONNECTION STUDY AND


TRANSMISSION LINE

2.00%

11

87.20%

15.00%

0.00%

0.00%

SNAPS

Marala Hydropower Project

MARALA HYDROPOWER PROJECT

SEPTEMBER 2014

MARALA HYDROPOWER PROJECT

JANUARY 2015

MARALA HYDROPOWER PROJECT

APRIL 2015

MARALA HYDROPOWER PROJECT

JULY 2015

MARALA HYDROPOWER PROJECT

DEC 2015

41

MARALA HYDROPOWER PROJECT

DEC 2015

42

MARALA HYDROPOWER PROJECT

DEC 2015

43

MARALA HYDROPOWER PROJECT

DEC 2015

44

MARALA HYDROPOWER PROJECT

DEC 2015

45

MARALA HYDROPOWER PROJECT

DEC 2015

46

MARALA HYDROPOWER PROJECT

DEC 2015

47

Pakpattan Hydropower Project

PAKPATTAN HYDROPOWER PROJECT

JANUARY 2014

49

PAKPATTAN HYDROPOWER PROJECT

SEPTEMBER 2014

50

PAKPATTAN HYDROPOWER PROJECT

APRIL 2015

51

PAKPATTAN HYDROPOWER PROJECT

JULY 2015

PAKPATTAN HYDROPOWER PROJECT

DEC 2015

53

PAKPATTAN HYDROPOWER PROJECT

DEC 2015

54

PAKPATTAN HYDROPOWER PROJECT

DEC 2015

55

PAKPATTAN HYDROPOWER PROJECT

DEC 2015

56

PAKPATTAN HYDROPOWER PROJECT

DEC 2015

57

PAKPATTAN HYDROPOWER PROJECT

DEC 2015

58

PAKPATTAN HYDROPOWER PROJECT

DEC 2015

59

PAKPATTAN HYDROPOWER PROJECT

DEC 2015

60

PAKPATTAN HYDROPOWER PROJECT

DEC 2015

61

PAKPATTAN HYDROPOWER PROJECT

DEC 2015

62

Deg Outfall Hydropower Project

DEG OUTFALL HYDROPOWER PROJECT

JANUARY 2015

64

DEG OUTFALL HYDROPOWER PROJECT

APRIL 2015

65

DEG OUTFALL HYDROPOWER PROJECT

JULY 2015

DEG OUTFALL HYDROPOWER PROJECT

DEC 2015

DEG OUTFALL HYDROPOWER PROJECT

DEC 2015

DEG OUTFALL HYDROPOWER PROJECT

DEC 2015

DEG OUTFALL HYDROPOWER PROJECT

DEC 2015

DEG OUTFALL HYDROPOWER PROJECT

DEC 2015

Chianwali Hydropower Project

CHIANWALI HYDROPOWER PROJECT

JANUARY 2015

73

CHIANWALI HYDROPOWER PROJECT

APRIL 2015

74

CHIANWALI HYDROPOWER PROJECT

JULY 2015

CHIANWALI HYDROPOWER PROJECT

DEC 2015

76

CHIANWALI HYDROPOWER PROJECT

DEC 2015

77

CHIANWALI HYDROPOWER PROJECT

DEC 2015

78

SECURITY MEASURES

SECURITY ARRANGEMENTS FOR THE CHINESE WORKING


AT HYDRO POWER PROJECTS IN PUNJAB
Name of Project
Chinese State
Police Guards (SPU)
Elite Guards
Private Security Guards
Name of Security Company
Employees, labour and staff
CCTV Cameras
Search Lights
Metal Detector
Vehicle Scanner
Walki Taltkie Sets
Escort Register
Visitors Register
Employees Card
Escort Chinese
Boundary Wall
Barriers
Watch Tower
Focal Person

Chianwali Hydropower Project (CHP)


Twenty One (21)
3x HC & 42 x Constables (45)
2x HC & 8 x Constables (10)
2x Supervisors & 9 x Guards (11)
GB Security (Pvt) Ltd.
One Hundred Six (106)
Seven (7)
Twenty (20)
One (1)
One (1)
Four (4)
Being Maintained
Being Maintained
Issued
Being ensured
Exists
Two (2)
Four (4)
Lt Col Ejaz
80

SECURITY ARRANGEMENTS FOR THE CHINESE WORKING


AT HYDRO POWER PROJECTS IN PUNJAB
Name of Project
Chinese State
Police Guards
Elite Guards
Private Security Guards
Name of Security Company
CCTV Cameras
Search Lights
Metal Detector
Vehicle Scanner
Entry Barriers
Exit Barriers
Employees
Visitors Register
Employees Card
Escort Chinese
Focal Person

Marala Hydropower Project (MHP)


Twenty Four (24)
2x SI & 31x Constables (33)
1x SI & 15x Elite Guards (16)
2x Supervisors & 12x Guards (14)
GB Security (Pvt) Ltd.
Ten (10)
Sixteen (16)
Three (3)
One (1)
Two (2)
Two (2)
Two Hundred and Fifteen (215)
Being Maintained
Issued
Being ensured
Maj Zafar

Remarks: Security Situation is being regularly discussed with Chinese


81

SECURITY ARRANGEMENTS FOR THE CHINESE WORKING


AT HYDRO POWER PROJECTS IN PUNJAB
Name of Project
Chinese State
Police Guards
Elite Guards
Special Protection Unit Guard
Private Security Guards
Name of Security Company
CCTV Cameras
Search Lights
Metal Detector
Vehicle Scanner
Entry Barriers
Exit Barriers
Employees, staff and labour
Boundary Wall
Visitors Register
Employees Card
Escort Chinese
Focal Person

Pakpatan Hydropower Project (PHP)


Sixteen (16)
1x ASI, 3 x Constables (4)
1x ASI & 3x Constables (4)
1x SI, 4x HC, 47 x Guards (52)
2x Supervisors & 8x Guards (10)
GB Security (Pvt) Ltd.
Six (6)
Ten (10)
One (1)
One (1)
One (1)
One (1)
Nighty (90)
Exists
Being Maintained
Issued
Being provided
Mr. Zulfiqar

Remarks: Security situation is regularly discussed with Chinese

82

SECURITY ARRANGEMENTS FOR THE CHINESE WORKING


AT HYDRO POWER PROJECTS IN PUNJAB
Name of Project
Chinese
Police Guards
Elite Guards
Private Security Guards
Name of Security Company
CCTV Cameras
Search Lights
Metal Detector
Vehicle Scanner
Employees, labour, staff
Boundary Wall
Barbed Wire
Observation Post
Visitors Register
Escort Register
Employees Card
Escort Chinese
Focal Person

Deg Outfall Hydropower Project (DHP)


Twenty Five (25)
1x HC & 7 x Constables (8)
1x HC & 4 x Constables (5)
2x Supervisors & 8 x Guards (10)
GB Security (Pvt) Ltd.
Eight (8)
Fourteen (14)
One (1)
One (1)
Thirty Five (35)
Exist around Chinese residence
Exist over boundary wall
One (1)
Being Maintained
Being Maintained
Issued
Being ensured
Nil

Remarks: Security update is being regularly shared with Chinese


83

SECURITY ARRANGEMENTS FOR THE CHINESE WORKING


AT HYDRO POWER PROJECTS IN PUNJAB
Name of Project
Chinese
Police Guards
Private Security Guards
Name of Security Company
CCTV Cameras
Search Lights
Metal Detector
Vehicle Scanner
Alarm System
Entry Point
Exit Point
Employees
Visitors Register
Employees Card
Escort Chinese
Chief Coordinator
Remarks

Sinotec Co., Ltd, Lahore


Six (6)
1x HC & 3 x Constables (4)
Two (2)
GB Security (Pvt.) Ltd.
Four (4)
Four (4)
One (1)
One (1)
Installed
One (1)
One (1)
Forty (40)
Being Maintained
Issued
Being ensured
Col Sajid Hameed
Chinese living in 4 FCC Muratab Ali
Road and 33-A, Block G, Gulberg III, Lahore
84

THANKS

REDSIP PROJECTS
Description

Unit

MHP
43%

PHP
5.89

15.00

E & M Cost per MW

Million USD

1.96

Civil Work Cost

Million USD

19.79

Civil Works Cost per MW Million USD

2.59

2.15

3.13

2.89

2.73

Project EPC Cost

Million USD

34.78

11.95

24.53

18.80

90.06

Project Installed
Capacity

MW

7.64

2.82

5.37

4.04

19.87

Project EPC Cost per


MW

Million USD

4.55

4.24

4.57

4.65

4.53

6.06

1.44

32%

7.10

38%

Overall

Million USD

57%

7.75

DHP

E & M Cost

2.09

49%

CHP

1.76

51% 16.79 68% 11.69

35.73

40%

1.80
62%

54.33

60%

86