You are on page 1of 33

CTCI and Partners

Co. Ltd.
Introduction to
CTCI and Partners
Co. Ltd.
February, 2010
Al-Khobar
-- 1 --
Contents

 Who we are

 What we serve

 How we serve

 Our achievements

 Our vision

-- 2 --
Who we are

-- 3 --
CTCI and Partners Company Limited is
established in JV form to echo Aramco’s IK
Initiative program. His mother companies
include:
1. CTCI Corporation, based in Taiwan,
ROC
2. Al-Rabiah Consulting and Engineering
Services, based in Al-Khobar
3. PI-Consult, based in Al-Khobar

-- 4 --
CTCI Introduction
• Establishment since 1959
• A public company listed in Taiwan Stock Exchange (TSE)
since 1993
• Integrated service provider specialized in oil, gas, petroleum
refining, petrochemical, chemical, power, infrastructure and
environmental industries
• ISO 9001 / 14001 and OHSAS 18001 certificates
• Hundreds proven track record worldwide, including Taiwan,
China, Thailand, Singapore, Malaysia, Vietnam, Philippines,
Indonesia, KSA, Qatar and USA
• CTCI’s CSR report (1st Issuance) was published in June 2008.
• CTCI’s CSR report was rewarded by BSI (British Standard
Institution) on Oct. 29, 2008

-- 5 --
CTCI Corporate Overview & Shareholders
Paid-up Capital : 199 MUSD
Shareholder’s Total Equity (2007) : 314 MUSD
FY 2006 New Orders : 2.2 BUSD
Turnover : 1.0 BUSD
FY 2007 New Orders : 809 MUSD
Turnover : 1.3 BUSD
FY 2008 New Orders : 2.3 BUSD
Turnover : 1.2 BUSD (as of Oct 31, 2008)
Backlog : 2.9 BUSD

Domestic Morgan
Individuals, Stanley,
24.55% 19.57%

Domestic Other Foreign


Financial Investors,
Institutes, 20.83%
Domestic
11.72%
Legal Entities,
23.33% (as of Oct 2008)

-- 6 --
CTCI Worldwide Network

Jingding, PRC

Shangding, PRC
CTCI Taipei HQ
CTCI Kaohsiung

CINDA, CIPEC, the Philippines


India
CIMAS, Vietnam
CTCI,
Abu Dhabi
CTCI & Partners, KSA
CTCI Arabia, KSA
CTCI, Qatar CTCI, Thailand
CTCI, Malaysia

-- 7 --
• Alrabiah and Partners Co. ‘Consulting Engineers’ formed in
1988.

• 51 Design Engineers & Support Personnel.

• 72 Engineers for Project Management & Site Supervision

• Serving Several Major Clients in Saudi Arabia.

• ISO 9001:2000 Certified since 2007.

• Consulting and Design Experience in Infrastructure, Roads,


Traffic and Transportation.

• Experience in Structural Damage Assessment

-- 8 --
ALRABIAH & PARTNER CO.
OFFICES IN SAUDI ARABIA

Main Offices
Satellite Offices /
Projects
9
-- 9 --
• Petro-Infrastructure Engineering Consultants Company
was formed in 1988 and has over 40 years of combined
experience.

• Present strength of 160 Design Engineers & Support


Personnel.

• Executed Sizable Projects for Major clients in the


Kingdom.

• ISO 9001:2000 Certified since 1998.

• Versatile and wide range of Consulting Experience in


various fields, Including Design, Construction Support -- 10 --
What We Serve
Welcome to visit us at
www.ctci.com.tw
www.alrabiah.com.sa
www.pi-con.com

-- 11 --
Our Core Business Line
A. Oil & Gas
Refinery Petrochemical Strategic
HDS EO / EG Ethylene Plant
Hydrocracker PTA LNG Terminal
FCC / RFCC PP LLDPE / HDPE
Reformer Aromatics LDPE
Alkylation Styrenics PDH
Isomerization Cumene/Phenol/BPA Methanol
OCT

B. General Industry and Infrastructure


Building, Road, Marine Structure, Airports,
Telecommunication, etc.

-- 12 --
How We Serve

-- 13 --
One Team One Spirit One Goal
Passions for Customer!

Attitude

-- 14 --
Project Control Plan (1/2)
 Evaluated the planning work and the planning resources
mobilization to achieve the schedule and cost baseline
 Monitoring actual and forecast schedules, cost and
progress by comparing them to the plan so that
problem areas can be identified
 Taking corrective action against the causes of actual or
anticipated problems so that the impact on the final
schedule or cost targets is minimized

-- 15 --
Project Control Plan (2/2)

 Presentation of timely and accurate reporting and


forecasting of cost and schedule information the
project team to permit decision-making and, if
necessary, intervention, in a timely manner that
will enable project goals to be achieved
 Coordinating other project discipline groups to
adopt and follow the process of scope, cost and
time management

-- 16 --
Schedule Overall Conceptual
Schedule Philosophy
Reporting
Plot Plan
Planning Summary Schedule
Stage & Progress Stage Management
Equipment List Master Schedule Level
& Progress
Project
E/P/C Execution Plan Level III
Level III && Project
Project CPM
CPM
Level
Pre- comm System
E/P/C Schedule
Schedule
Contract Requirement Heavy Equipment Erection Plan
Quantity Take Off ERS/SPF PRS CRS
Control
Level

WBS & Scope Defined

P3 & P3 E/C &IN-HOUSE SYSTEM

Proposal Master Detail Control Weekly


Schedule Monthly
Schedule Schedule
Report

Pre-Comm. Quantity
90-day Project CPM E/P/C Schedule Integration Productivity
Schedule Schedule PM / PEM / PIM / PCM / PSM / LE
Schedule
Report

-- 17 --
Our Achievements

-- 18 --
CTCI Major Reference in China
1 ICI – PU System House 19 TSRC – SBR EPC LSTK

2 Rohm & Haas – IER 20 CIBA – Additive ENG’G

3 Fujian Huaxing – LPG Terminal 21 LCY – PMMA CONSTR. MGT

4 Montell-TPP China – PPAM 22 LCY – PFA On-going Project

5 ZGPC – SAN II 23 SPC – Ethylene Plant Expansion


6 Rohm & Haas – Ag Chemical 24 FPC – PVC
7 Xiang Lu – PTA 25 FCFC – PTA
8 ZGPC – ABS II 26 FCFC – ABS
9 CPPE – West-East Natural Gas 27 Qilu Petrochemical – PVC
31 
Pipeline 28 BASF/Huntsman – IIP (EPsCm) 18 Beijing
35
10 Secco – SAR 29 Oriental – PTA (EPsCm)
27
11 BASF-YPC – LDPE 30 ZGPC – ABS III
11 12 9 16 6 19 32 33
12 BASF-YPC – C1 31 PetroChina – EB/SM
28 15 10 20
13 CNOOC-Shell – EO/EG 32 TSRC – BR 5 30 8 Shanghai
22 21 29 2 1 23 17
14 Mitsubishi Rayon – AF 33 TSRC – SEBS
14 24 25 26
15 Lucite – MMA 34 PetroChina – FCC (BD)
3
16 Nantong SKT – PVDC 35 DuPont – TiO2 (EPsCm)
7
17 CNOOC Shanghai – LNG 13
34
18 (Confidential) – Polysilicon 19 Guangzhou
4

-- 19 --
CTCI Major Reference in Thailand
: On-going Project

1 Bangchak – Gas Oil HDS


2 MPKC – ABS/SAN
3 Tuntex – PTA
4 Vinythai – VCM
5 TPC OXY – PVC Paste Resin
6 HMC – PP II
7 TOC – C2 and C3 Recovery Expansion
8 TIG – ASU
9 Rohm & Haas – PAA
Bangkok 10 Bayer – BPA & PC II Expansion
1 14  11 Thai MMA – TBA - II
Sriracha 
12 Diapolyacrylic – PMMA
20  Rayong
2-13 18 19 13 HMC – PP I Upgrading / PP II Upgrading
15-17 21 22 14 Bangchak – Hydrocracker
15 PPCL – Phenol
16 HMC – PDH
17 PTTAC – AN/MMA
18 Amata – CCPP
19 Maxxis – Rubber Tire
20 Thai Oil – Co Generation
21 PTTUT – Co Generation
22 IRPC – Co Generation

-- 20 --
CTCI Major Reference in Singapore
: On-going Project

1 SRC –Visbreaker & Catalytic Reforming


2 Esso – Power System Expansion
3 Esso – Propane Recovery from CVS
Seletar  7-9 4 SRC – HCU II
5 Esso – Long Term Engineer Service
 6 SRC – RCC Expansion
Changi 7 Chevron – Lube Oil Additive
8 PUB – Senoko Power Station Fuel Oil
 Jurong Tank Facility
1-6 10 9 PUB – Senoko Power Station
Electrochlorination System
10 PUB – Gas Turbine Power Plant

-- 21 --
CTCI Major Reference in Middle East
: On-going Project
KSA
1 Petromin - Riyadh Refinery Expansion
2 Petromin - Yanbu Domestic Refinery
3 SWCC - Riyadh Water Transmission System
Pumping Station
4 SAMREF - Yanbu Export Fuel Refinery
5 Jeddah Oil Refinery - Hypo-Chlorination
6 YANPET - EG & Polymer
Tehran
15 7 SHARQ - EG & LLDPE
16 8 Petrokemya - Ethylene
IRAN 9 Luberef - Yanbu Luberef II
10 SAMAD - Urea Quality Improvement
Jubail QATAR 11 Saudi Kayan - EO/EG
Yanbu
7 8 10 UAE
2 4 KSA 11 Qatar
12 13 14
9 6
12 Qatargas - LNG
Riyadh
13 QAFAC - Methanol & MTBE
1
5 14 QAPCO - Ethylene Expansion II
3
Iran
15 GBPC - ABS/SAN

Jordan
16 Jordan Fertilizer Ind. - Aqaba Fertilizer

-- 22 --
CTCI Major Reference in Vietnam
: On-going Project

Hanoi 5 1 PV – Phu My Go Dau Pipeline


8 2 PV – Condensate Processing Plant
3 PV – Dung Quat Refinery Building
4 PV & ZNSM – Vietross Refinery Package II & III
5 Na Doung – Power Plant
6 Phu My – Power Plant III
7 Ca Mau – Power Plant I & II
8 PHI – Hai Duong Phase 1 & 2 (Building EPC)

3 4

Hochiminh  1 2 6

-- 23 --
BUILDINGS

Prince Faisal Stadium, Riyadh King Faisal University, Al-Hassa, KSA

-- 24 --
MARINE
STRUCTURES

Jetty, Shoaiba, KSA Saudi Bahrain Causeway

-- 25 --
AIRPORTS

King Abdulaziz International Airport, Jeddah Aramco Airport Runway, Shaybah, KSA

-- 26 --
Major Achievements of PI-Consult
Client: ROYAL COMMISSION FOR JUBAIL AND YANBU
Project Location: JUBAIL
Project Title: FEED FOR THE NEW INDUSTRIAL PARK WEST /JUBIAL 2 CONTRACT NO.
202-TO3
Description: Front End Engineering & Design (FEED) include the following:
Staged site development and drainage of entire site Roads and utilities
crossing at the KRT (3.0 KM Wide) High Ways, Main roads and high ways rail road
system. Sea water cooling supply and distribution. Potable water supply
distribution. Industrial Wastewater collection and treatment system.
Sanitary wastewater collection and treatment system. Material Handling, pipe
and utility corridors. Feedstock supply and fuel gas system supply and
distribution. Electrical Power and telecommunication transmission. Value Engineering
and Optimization.
Value in SAR: 35 Million (For FEED)
Design Duration: 2003-2008

Client: SAUDI ARAMCO


Project Location: K.S.A
Project Title: INSTALL & UPGRADE IDAS SYSTEM AT 18 COMPANY FACILITIES
Description: Provide Conceptual / project Proposal for the Following:
All IDAS field devices will be located within respective perimeter site
fences. The IDAS system equipment which will be located at respective
Control Center with relevant communications transport for each site.
Also, the system shall provide local monitoring for the gate of each.
Value in SAR: 7,232,963

Design Duration: 2007-2008

-- 27 --
Major Achievements of PI-Consult
Client: SAUDI ARAMCO
Project Location: KHURSANIA
Project Title: DETAILED ENGINEERING FOR ABU HADRIYAH / FADHILI NEW OIL DRILL
SITES & DETAILED ENGINEERING FOR ABU HADRIYAH / FADHILI T/L, INTERFACE
MANIFOLDS & UPGRADING EXISTING WELLS
Description: Provide detail engineering of crude oil upstream facilities at
Abu-Hadriyah and Fadhili fields consisting of Drill-sites development
including the connecting pipelines from wellheads to interface manifolds.
Each Drill-sites, consisting of single-well to multi-wells system, is equipped
with multi-phase flow-meters and testing facility, corrosion inhibitor chemical
injection system, corrosion monitoring system, remote terminal unit, switch-
rack, signal
Value in SAR: 5,000,000 muti-plexing unit (mux).

Design Duration: 2005-2006

Client: PUBLIC HOUSING EST. DAMASCUS, SYRIA


Project Location: DAMASCUS, SYRIA
Project Title: DIPLOMATIC QUARTERS PROJECT - DAMASCUS
Description: The project is located in the suburbs of Damascus city with a
total area of 600 Hectare. The project includes diplomatic
area (225 Hect), General Services Area (125 Hect), open uncovered
area (50 Hect.), Landscaped Area (150 Hect), Roads and Access passage and
walk ways (50 Hect). Pi-Consult consortium grouped with Arch Center Riyadh, and
SPC
Value in SAR: 5 Million Damascus were awarded the design on Jan 19, 2006.

Design Duration: 2006-2007


-- 28 --
Major Achievements of PI-Consult

Client: NESMA TRADING COMPANY LTD.


Project Location: VARIOUS
Project Title: IDAS, LR DAS INFRASTRUCTURE PROJECT

Description: The project shall provide a detail engineering design package


for IDAS at 18 Company facilitates with a dedicated Alarm
Management System (AMS) per site to monitor, detect, assess, trace and
video record potential intrusion for 18 Company facilities. And to provide
Long Range Detection and Assessment System (LRDAS) with the required infrastructure at
twenty five (25) company’s vital sites as specified henceforth in this
Value in SAR:
document. 5,000,000

Design Duration: 2009-2010 On going

-- 29 --
Our Vision

-- 30 --
Our Vision – Partnership with Clients
High Value /
Localization Leading EPC Company in KSA,
Patnership with Mr. Clients
A
S Intergration Capability / Esteem Stage
K
in
lue
a Introduce Corporate Social Responsibility
V
a te Advanced On-Line Support
re Stretch Local Capablity
C ISO 9001 Certificate
Full Spectrum Coach / Self-Dependent Stage

Comprehensive Training
Common 3D Work Platform
Recruit KSA Engineers
On-Line Support
Core Team from CTCI Group
Setting Up Operation Mechanism / Implant Stage
2009 2014 Time

-- 31 --
-- 32 --
-- 33 --

You might also like