HYDRAULICS DESIGN PLANS/REPORT REVIEW CHECKLIST

BOD Ref.
No.
Project Description:

Location:

DOTS Ref.
No.

Reviewer:
Designer:
(Office or
Consultant)

Approved by:

Type of Structure:
Type Documents (Plans, Report Analysis, CO, VO, Etc)

N/A

Item

1.

Is the cover sheet included and correctly


done?

2.

Is the index of drawings indicated?

3.

4.

Is the location vicinity/map reflected in


the plan?
Are
the
general
Notes/Legends,
Abbreviations & Symbols, and Technical
Specifications indicated?

5.

Is
the
geotechnical
provided?

6.

8.

9.

Are
the
technical
specifications
presented?
Are the general plan, elevation sections
and details of flood control/drainage and
other related structures indicated?
Are the following analysis/calculations
undertaken?
a. Hydrologic/Hydraulic

10.

b.

Comments

(boring

Water Surface Profile

log)

N/A

Item

#
a.
32.

33.

34.

35.

36.

36.

37.

37.

38.

Dimensions of the cutoff wall at the bottom


of revetment in profile, cross section and
typical section
a. Width of the top of revetment in typical
section
a. Location, size, type and spacing of
weepholes as well as the type and
dimensions of filter pockets at the proposed
revetment in typical section
a. Type of fill for void or eroded portions behind
the proposed revetment (if boulder fill, verify
sizes)
Are the following requirements for sheet piles
detail presented?
a. Details of pile cap
a. Details of sheet piles (steel or reinforced
concrete)
a. Location and orientation, size, type and
spacing of anchor rod or beam in typical
section
d. Location, orientation, size and type of anchor
pile in typical section
is the size of stones for foot protection works
indicated?

Comments

39
.

40
.

41
.

42
.

43
.

43
.

45

Are the size and slope of drainage, pipes,


dimensions of catch basins, type and
dimensions of gate flap (if provided) in
the plan and elevations of drainage
scheme indicated?
Are the dimensions in the plan and
elevations of stairway indicated?
Is the detail of connection of the
revetment
with
existing
structures
presented?
Is the maximum and ordinary water level
in typical section and cross sections
indicated?
Is the location, spacing and orientation
with reference to bank/shore line (for all
types of training works) presented?
Is the top elevation, length and
longitudinal slope in typical section and
cross sections (for all types of training
works) indicated?
Is the side slope, top width, and
description and sizes of stones in detail

11
.

a. Seepage and Settlement

12
.

b.

Slope Stability

13
.

c.

Overall Stability

14
.

d.

Scour

15
.

e.
Is there any detailed
quantitycalculations?

16
.

f.

Is the table of contents indicated?

17.

18.

19.

Are the quantities of structure for flood control,


drainage,
slope
and
scour
protections
presented/ indicated?
Are the tabulation of old and new quantities
presented? (revised quantities separately
indicated in case of revised plans or AsStaked plans

Is the soil profile correctly presented in the


drawing?
Is the location of proposed bridge, flood
control, dam, shore protection works and other
related structure with respect to existing road,
road section, towns, etc indicated?

20.

21.

Are the contours with elevation correctly


presented?

22.

Is the location of boreholes properly indicated?

23.

Is the direction of stream flow indicated?

24.

25.

Are
the
following
survey
requirements
indicated?
a. Benchmarks
used
in
the
surveys
(reference elevation)
a. Azimuth for alignment of revetment (flow
control structure) longitudinal axis

26
.
27
.
28
.
29
.

a. Directional
(northing)

Location of private and public


structure/ utilities that may be
affected by the proposed project

c.

Location of existing bridge and other


structures, if any

Are the following requirements in the


typical section of revetment indicated?
a.
Elevation of the proposed top of
revetment
in
plan/profile,
cross
sections and typical sections
b.

30
.

31
.

sign

b.

sign/informatory

Elevation at the top of cutoff wall at


the foot of revetment in plan/profile,
cross sections and typical section

c. Side slope/s of the proposed revetment


in plan/profile, cross section and
typical section

#
47
.

N/
A

48
.

49
.

50
.

51
.

Item
Is the detail of anchorage of retards
and pile hurdles to the bank indicated?
Are the following requirements for the
dike details indicated?
a. Elevation at the proposed top of
dike in plan/profile, cross section
and typical section indicated?
a. Elevation at proposed berm of dike
in plan/profile, cross sections and
typical section indicated?
a. Side slopes, top width of dike in
cross sections and typical section
presented?
d.
Description
and
degree
of
compaction of embankment material
in typical section indicated?

Comments

2. The minimum spacing of drainage manholes/inlets shall be


20 meters.
3. The minimum size of drainage pipes shall be 910 millimeters
in diameter.
4. The provision of underground detention tanks as part of
storm water
management system, particularly in flood prone urban areas to
temporarily
store flood water shall be a consideration in the design of the
drainage system.
The Bureau of Design shall integrate the above-mentioned
guidelines in the
updating of the DPWH Design Guidelines, Criteria and
Standards.
For strict compliance.

ROGELIO L. SINGSON
Secretary

End of
Presentation
Thank You
Prepared by Engr. P.L. Zaplan
Chief, Hydraulics Division

You might also like