Effort Estimation

Software Effort Estimation

Effort Estimation
Estimating

The process of forecasting or approximating the time


and cost of completing project deliverables.
The task of balancing the expectations of stakeholders
and the need for control while the project is implemented

Types

of Estimates

Top-down (macro) estimates: analogy, group consensus,


or mathematical relationships
Bottom-up (micro) estimates: estimates of elements of
the work breakdown structure

Which view is correct?

Rough order of magnitude is good enough. Spending


time on detailed estimating wastes money
Time is everything; our survival depends on getting there
first! Time and cost accuracy is not an issue.
The project is internal. We dont need to worry about cost.
The uncertainty is so great, spending time and money on
estimates is a waste.
The project is so small, we dont need to bother with
estimates. Just do it.
They used an internal estimate for strategic decisions
and then we had to live with it.
We were burned once. I want a detailed estimate of every
task by the people responsible.

Macro versus Micro Estimating


Conditions for Preferring Top-Down or Bottom-up
Time and Cost Estimates
Condition
Strategic decision making
Cost and time important
High uncertainty
Internal, small project
Fixed-price contract
Customer wants details
Unstable scope

Macro Estimates
X

Micro Estimates
X

X
X
X
X
X

Estimating Projects: Preferred


Approach
Make

rough top-down estimates.

Develop
Make

the WBS/OBS.

bottom-up estimates.

Develop

schedules and budgets.

Reconcile

differences between top-down and


bottom-up estimates

Estimating Guidelines for Times,


Costs, and Resources
1.

Have people familiar with the tasks make the estimate.

2.

Use several people to make estimates.

3.

Base estimates on normal conditions, efficient


methods, and a normal level of resources.

4.

Use consistent time units in estimating task times.

5.

Treat each task as independent, dont aggregate.

6.

Dont make allowances for contingencies.

7.

Adding a risk assessment helps avoid surprises to


stakeholders.

Refining Estimates
Reasons

Interaction costs are hidden in estimates.


Normal conditions do not apply.
Things go wrong on projects.
Changes in project scope and plans.

Adjusting

for Adjusting Estimates

Estimates

Time and cost estimates of specific activities are


adjusted as the risks, resources, and situation
particulars become more clearly defined.

Refining Estimates (contd)


Contingency

Are created independently to offset uncertainty.


Reduce the likelihood of cost and completion time
overruns for a project.
Can be added to the overall project or to specific
activities or work packages.
Can be determined from previous similar projects.

Changing

Funds and Time Buffers

Baseline Schedule and Budget

Unforeseen events may dictate a reformulation of the


budget and schedule.

Why Refine an Estimate?

Methods for Estimating Project


Times and Costs
Macro

(Top-down) Approaches

Consensus methods

Ratio methods

Apportion method

Function point methods for


software and system projects

Learning curves

Project Estimate
Times
Costs

Apportion Method of Allocating Project


Costs Using the Work Breakdown Structure

Methods for Estimating Project


Times and Costs (contd)
Micro

(Bottom-up)
Approaches

Template method

Parametric Procedures Applied


to Specific Tasks

Detailed Estimates for the


WBS Work Packages

Phase Estimating: A Hybrid

Duration vs. Effort vs. Productive Time


Duration

is the elapsed time in business


working days
Work effort is the labor required to complete
an activity. Work effort is typically the amount
of focused and uninterrupted labor time
required to complete an activity.
Productive time considers the percentage of
the work day that can be devoted to project
activity work. Estimates in IT range from 6675%, recent estimates of about 50-65%
(same client base). This doesnt include
unexpected interruptions!

Elapsed time vs. work time

Software Cost Estimation


What is the Problem?
100 - 200% cost overruns are not uncommon
15%of large projects never deliver anything
31% of new IS projects cancelled before completion ($81 billion)
What are the consequences?
Economic
Technical
Managerial
What is gained through effective software cost-estimation?
schedule/staffing estimates
better understanding of a particular project

Why are we bad at software


estimation?
Complexity
Infrequency
Uniqueness
Underestimation bias
Goals not estimates

Basic Steps in Software Estimation

Identify project objectives and requirements


Plan the activities
Estimate product size and complexity
Estimate effort, cost and resources
Develop projected schedule
Compare and iterate estimates
Follow up

Software Cost-Estimation Methods

algorithmic
expert judgement
similar, completed projects
equate to available resources
Price-to-win
Top-down (global estimate)
Bottom-up (each component separately estimated)

Algorithmic
Models
COCOMO
ESTIMACS
ESTIPLAN
FAST
FUNCTION
POINTS
MAINSTAY
PRICE
SLIM
SOFTCOST-R
SPQR

TRW (Boehm)
Computer Associates (Rubin)
AGS Management Systems
Freiman Parametric Systems (Freiman)
IBM (Albrecht)
Mainstay Software Corporation
RCA
QSM (Putnam)
Reifer Consultants (Tausworthe)
Software Productivity Research (Jones)

Basic Algorithmic Form


Effort = constant + coefficient*(size metric) +
coefficient*(cost driver 1) +
coefficient*(cost driver 2) +
coefficient*(cost driver 3) +
..
size metric

lines of code
new versus old lines of code
function points

SLOC as an Estimation Tool

Why used?
early systems emphasis on coding

Criticisms
cross-language inconsistencies
within language counting variations
change in program structure can affect count
stimulates programmers to write lots of code
system-oriented, not user-oriented

How many Lines of Code in this program?


#define LOWER 0 /* lower limit of table */
#define UPPER 300 /* upper limit */
#define STEP 20
/* step size */
main ()

/* print a Fahrenheit-Celsius conversion


table */

{
int fahr;
for (fahr=LOWER; fahr <= UPPER; fahr=fahr+STEP)
printf(%4d %6.1f\n, fahr, (5.0/9.0)*(fahr-32));
}

COCOMO Cost Drivers

Required software reliability


data base size
product complexity
computer execution time constraint
computer storage constraint
computer turnaround time
analyst capability
programmer capability
application experience
hardware/software experience
programming language experience
use of modern programming practices
use of software tools
required development schedule

Algorithmic Model Conclusions

Algorithmic Models can do a good job in estimating


required effort

Good project data must be collected and analyzed in


order to derive useful algorithms

Calibration is essential as the specific environment


is critically important

Effort estimates do have other uses


Productivity evaluation of project teams or software
development technologies
Objective negotiating tool with users in changes in
scope and impact on budget/schedule

Function Count Systems View:


Functionality Types
Interface
Files

Inputs

Internal
Files

Queries

Outputs

Function
Points
History
Non-code oriented size measure
Developed by IBM (A. Albrecht) in 1979, 1983
Now in use by more than 500 organizations
world-wide
What are they?
5 weighted functionality types
14 complexity factors

Functionality Types
EXTERNAL USER
input
type

output
type

inquiry
type

Internal
Logical File

External
Interface File

input type
output type
inquiry type
Application Boundary

Other Applications

Processing Complexity Adjustment

1)
2)
3)
4)
5)
6)
7)
8)
9)
10)
11)
12)
13)
14)

data communications
distributed functions
performance
heavily used configuration
transaction rate
on-line data entry
end user efficiency
on-line update
complex processing
reusability
installation ease
operational ease
multiple sites
facilitates change

Each rated on scales equivalent


to the following:
Not present
Incidental Influence
Moderate Influence
Average Influence
Significant Influence
Strong Influence

=0
=1
=2
=3
=4
=5

Function Point
Calculation
5

Function Counts = FC x w j
i

i 1 j 1

14
Function Points =FP FC .65 .01 ck
k 1

where
xi
wj
ck

= function i
= weight j
= complexity factor

Need to track employees and their work


- Add, change, delete, queries, and reports
- Two types of employees, salaried and hourly

Employees can have more than one job assignment

Standard job descriptions are retained by system

Employees can have more than one location and


locations can have more than one employee
- Another system stores the location data

Detailed Function Point Counting Rules

(1) Internal Logical Files (ILFs) Rules:


Each major logical group of user data or control
information
Data is generated, used and maintained by the
application
In Practice:
Count at logical (external design) level
In DB environment generally a relational table = a logical
file (before extensive normalization)
Ignore multiple views

Detailed Function Point Counting Rules


(2) External Interface Files (EIFs) Rules:
Files passed or shared between
applications
Reference data only (not transactions)
In Practice:
Look for read only usage
Count special database extracts

Example - ILFs and EIFs


Employee - entity type
- Employee name
- SSN
- Number of dependents
- Type (salary or hourly)
- Location name (foreign key)
Salaried employee - entity subtype
- Supervisory level
Hourly employee - entity subtype
- Standard Hourly rate
- Collective Bargaining Unit Number

Example - ILFs and EIFs


Job

- entity type
- Job name
- Job number
- Pay grade
Job Assignment - entity type
- Effective Date
- Salary
- Performance Rating
- Job Number (foreign key)
- Employee SSN (foreign key)
Job Description
- Job Number (foreign key)
- Line number (not known to users)
- Description line

Example - ILFs and EIFs

Location - entity --maintained in another system


-

Location Name
Address
Employee SSN (foreign key)

COUNTING STEPS:
-

Count number of ILFs and EIFs


Assign them a complexity weighting

Counting ILFs and EIFs

Three ILFs:
- Employee
- Job
- Job Assignment
- not Job Description (logically part of Job)
- not Location (an EIF)
- not Salaried Employee (a Record Element Type)
- not Hourly Employee (a Record Element Type)

One EIF:
- Location

Counting ILFs/EIFs - Complexity

Record
Element
RecordTypes
Element
(RETs)
Types

Data Element
Data Types (DETs)

Element
Types
1-19 (DETs)
20-50
51+
(RETs)
51+
<2 1-19 Low 20-50
Low
Average
<2
Low
2-5 LowLow
Average Average
High
2-5
Low
Average
High
>5 Average
Average High
High
High
>5
High

Three ILFs:
Employee - 8 DETs and 2 RETs
Job - 4 DETs and 1 RET
Job Assignment - 5 DETs and 1 RET
One EIF: Location - 3 DETs and 1 RET

ILF and EIF Unadjusted FPs

Low
External
Input
External
Output
Logical
Internal
File
External
Interface
File
External
Inquiry

Average

High

x3

x4

x6

x4

x5

x7

3 x7

x10

x15

1 x5

x7

x10

x3

x4

x6

Detailed Function Point Counting Rules

(3) External Inputs (EIs) Rules:


Each unique user data/control type that enters
application
Adds/Changes/Deletes data in Internal logical file
Each transaction type is an external input
In Practice:
Not necessarily equal to screens
Dont confuse with inquiries (no change to data)

Counting EIs - Raw Data

Employee

Add,

Maintenance

change, delete Employee


Employee Inquiry; Employee Report
Job Maintenance
Add, change, delete Job
Job Inquiry; Job Report
Job Assignment Maintenance
Assign Employee to Job
Job Assignment Inquiry; Job Assignment Report
Transfer Employee
Evaluate Employee
Delete Assignment
Location Reporting
Location Inquiry; Location Report

Counting EIs - Complexity

File Types
File Types
Referenced
Referenced
(FTRs)
(FTRs)
<2
2
>2

<2
2
>2

DataTypes (DETs)
Data Element
Element
Types
1-4
5-15
+15
(DETs)
Low
Low
Average
1-4
5-15
15+
Low
Average
High
Low
Low
Average
Average Average
High
High
Low
High
Average
High
High

Example EIs (3 of 10):


Create Employee- 10 DETs, 2FTRs (Employee
and Location) => Average
Delete Employee- 3 DETs and 1 FTR=> Low
Assign Employee to Job - 6 DETs and 3 FTRs
(Employee, Job and Job Assignment)=> High

External Input (EI) Unadjusted FPs

External
Input
External
Output
Logical
Internal
File
External
Interface
File
External
Inquiry

Low

Average

High

6 x3

2 x4

2 x6

x4

x5

x7

x7

x10

x15

x5

x7

x10

x3

x4

x6

Detailed Function Point Counting Rules


(4) External Outputs (EOs) Rules:
Each unique user data/control type that exits
application
Unique means different format or processing logic
Can be sent directly to users as reports/messages, or
to other applications as a file
In Practice:
Processing must be involved (dont count output
response to an inquiry)
Detail and summary outputs count separately

Counting EOs - Raw Data


Employee

Add,

Maintenance

change, delete Employee


Employee Inquiry; Employee Report - 6-19 DETs
Job Maintenance
Add, change, delete Job
Job Inquiry; Job Report- 5 DETs
Job Assignment Maintenance
Assign Employee to Job
Job Assignment Inquiry; Job Assignment Report
Transfer Employee
Evaluate Employee
Delete Assignment
Location Reporting
Location Inquiry; Location Report- 6-19DETs

Counting EOs - Complexity


File Types
File Types
Data
Referenced
Element
Referenced
Delta Element
Types (DETs)
File
Types
(FTRs)
Types Data
(FTRs)
Referenced
Element 20+
1-5 (DETs)
6-19
(FTRs)
Types Average
1-5 Low
6-19
20+
<2
Low
(DETs)
<2 2-3
LowLow
Low
Average
Average
High
1-4 Average
5-15 High
2-3 >3
Low
Average
High
High 15+
<2 Average Low High Low HighAverage
>3
2
Low
Average
High
>2
Average
High
High
Example EOs :
Employee Report- 6-19 DETs, 2FTRs (Employee
and Location) => Average
Job Report-5 DETs and 1 FTR=> Low
Job Assignment Report - 6-19 DETs, 3 FTRs
(Employee, Job and Job Assignment)=> Average

External Output Unadjusted FPs


Low
External
Input
External
Output
Logical
Internal
File
External
Interface
File
External
Inquiry

Average

High

x3

x4

x6

1 x4

3 x5

x7

x7

x10

x15

x5

x7

x10

x3

x4

x6

Detailed Function Point Counting Rules

(5) External Inquiry (EQ) Rules:


Each unique input/output combination where an input
causes and generates an immediate output
Unique means different format or processing logic
In Practice:
No processing involved. If result is calculated or derived
field, then it is an input and an output
Help systems typically counted as external inquiry
Rate complexity as the higher of the input/output value

Counting EQs - Medium Cooked Data


Employee

Maintenance
Employee Inquiry- 2 FTRs and 9 DETs (output)
Job Maintenance
Job Inquiry - 1 FTR and 4 DETs (output)
Job Assignment Maintenance
Job Assignment Inquiry- 1 FTR and 5 DETs (output)
Location Reporting
Location Inquiry - 2 FTRs and 5 DETs (output)

RESULT - Use EI and EO matrices => 3 low complexity and


1 average (employee)

EQ Unadjusted FPs
Low
External
Input
External
Output
Logical
Internal
File
External
Interface
File
External
Inquiry

Average

High

x3

x4

x6

x4

x5

x7

x7

x10

x15

x5

x7

x10

3 x3

1 x4

x6

Total Unadjusted Function Points


External
Input
External
Output
Logical
Internal
File
External
Interface
File
External
Inquiry

Low

Average High

6 x3

2 x4

2 x6

1 x4

3 x5

x7

3 x7

x10

x15

1 x5

x7

x10

3 x3

1 x4

x6

Total = 96 Unadjusted FPs

Are Function Points a Silver Bullet?

The function-point metric, like LOC, is relatively


controversial...Opponents claim that the method requires
some sleight of hand in that computation is based on
subjective, rather than objective, data...
R. Pressman Software Engineering p. 94
"Variants in FP counting methodologies can result in
variances of up to +/- 50%."
Capers Jones Selecting a FP Counting Method
Within organizations the variation in function point
counts about the mean appears to be within 30%...
G. Low and D.R. Jeffery IEEE TSE Jan. 1990

Software Estimating Rules of


Thumb

Rule 1: One function point = 100 logical source code


statements (procedural languages)

300 for assembly languages, < 20 for some OO languages

Rule 2: Raising the number of function points to the


1.15 power predicts the approximate page counts
for paper documents associated with software
projects
Rule 3: Creeping user requirements will grow at an
average rate of 1% per months over the
development schedule

For a 2 year project, functionality at delivery will be 24%


larger then when requirements were collected.

Software Estimating Rules of


Thumb (continued)

Rule 4: Raising the number of function points to 1.2


power predicts the approximate number of test
cases created.

Assume each test case will be executed about 4 times

Rule 5: Raising the number of function points to the


1.25 power predicts the approximate defect potential
for new software projects

Defect potential is sum of bugs (errors) in requirements,


design, coding, user-documentation + bad fixes or
secondary errors introduced fixes prior errors.
For enhancements: raise to 1.27 power

Software Estimating Rules of


Thumb (continued)
Rule

6: Each software review, inspection, or


test step will find and remove 30% of the
bugs that are present

Implies 6-12 consecutive defect-removal


operations to achieve high-quality software

Rule

7: Raising the number of function points


to the .4 power predicts the approximate
development schedule in calendar months.

Longer for military projects; for enhancements


applies to size of enhancement (not base product)

Software Estimating Rules of


Thumb (continued)
Rule

8: Dividing the number of function points


by 150 predicts the approximate number of
personnel for the application

Includes software developers, QA, testers,


technical writers, DBAs, project managers

Rule

9: Dividing the number of function points


by 500 predicts the approximate number of
maintenance personnel

Raising function point to .25 power predicts


approximate number of years the application will
stay in use

Software Estimating Rules of


Thumb (continued)
Rule

10: Multiply software development


schedules by number of personnel to predict
the approximate number of staff months of
effort.

1000 function points raised to .4 = 16 calendar


months
1000 function points / 150 = 6.6 full time staff
16 * 6.6 = 106 staff months to build project

Software Estimating Rules of


Thumb (continued)
Staff

month: 22 working days with 6


productive work hours each day
132 work hours per month
Capers-Jones

IEEE Computer March 1996:


notes limitations of these types of heuristics