The purpose of FAT test: The purpose of the FAT is to demonstrate total functions of the control system, proper function of the control communication, monitoring, logic systems, and the OWS. The FAT shall be done simultaneously for control system cabinets in order to check completely the hardware, software and communication system between terminal boards and CPUs. REQUIREMENT PRIOR TO FAT: Prior to the FAT the supplier shall provide all internal Test Reports previously executed: a) all hardware tests reports b) all calibration reports c) data sheets for all components installed e) CPU card certificate & I/O cards certificates/specifications to be available f) All tester tool calibration certificates to be available. Documents required for FAT test: 1)Detail Loop Diagram 2)Interconnection wiring diagram 3)P&IDs, Cause & Effect 4)Instrument Index, Cable schedule List 5)FAT procedure 6)Vendor drawings/documents as Cabinets General Arrangement, BOM, System Architecture, Logic diagram, I/O assignment 7)PO
Control System FAT Test
FAT Test main topics: 1- Hardware Testing Procedure: Overall system configuration Check Visual Inspection Check Electrical Checks Power Connection and Grounding Check Wiring Check 2- Software Testing Procedure Devices check Loop Check up to HMI Graphics Loop Function Test Cause & Effect Test Graphics / Faceplate Check Performance Test
Control System FAT Test
1) Hardware Testing Procedure 1.1) Overall system configuration Check OBJECTIVE: The purpose of this test is to verify that the following are in accordance with the reference drawings /documents. 1. Model No. and Serial No. of each component 2. Quantity of each component 3. Location and accessibility of each component. REFERENCE DOCUMENT/DRAWING: 1. Bill of Materials 2. Cabinet General Arrangement Drawing 3. FAT Procedure
Cabinet General Arrangement
Control System FAT Test
1.2)Visual Inspection Check OBJECTIVE: The purpose of this test is to ensure that all components and accessories are free from scratches, deformities and properly labelled for identification. REFERENCE DOCUMENT/DRAWING: 1) Cabinet General Arrangement Drawing Cabinet General 2) FAT Procedures Visual check FAT Arrangement procedure
1.3) Electrical Checks:
OBJECTIVE: The purpose of this test is to ensure that all electrical wires are of proper type, size and color. REFERENCE DOCUMENT/DRAWING: Electrical Check 3) Cabinet General Arrangement Drawing FAT procedure 4) FAT Procedures 5
Control System FAT Test
1.4) Power Connection and Grounding checks OBJECTIVE: The purpose of this test is to ensure proper power and earth connection as well as system voltage level prior to power on. REFERENCE DOCUMENT/DRAWING: 1) Cabinet General Arrangement Drawing
Cabinet General Arrangement
Power/Grounding/ Wiring FAT Procedure
1.5) Wiring Checks
OBJECTIVE: The purpose of this test is to ensure proper signal wiring connection prior to Loop checks. REFERENCE DOCUMENT/DRAWING: System Wiring 2) Wiring Diagram Diagram
Control System FAT Test
2) Software Testing Procedures 2.1) Devices checks: OBJECTIVE: The purpose of this test is to verify the proper operation of mouse, alpha-numeric keyboard and CD drives, LCD monitor and printer in line with Project specifications. 2.2) Loop Check up to HMI Graphics: OBJECTIVE: The purpose of this test is to ensure the I/O loops are complete with all design inputs information. The simulation panels have been wired up to the field TB in the DCS Marshalling Cabinets to allow all I/O points simulation during software testing without any delay. Open Loop REFERENCE DOCUMENT/DRAWING: 1. I/O Loop drawing 2. Wiring Diagram 3. FAT Procedure
FAT Loop Check
Control System FAT Test
2.3) Loop Function Test: OBJECTIVE: The purpose of this test is to ensure the closed loops and complex loop are implemented as per process control philosophy and narrative. REFERENCE DOCUMENT/DRAWING: 1. I/O Loop drawing 2. Control Narrative 3. FAT Procedure
Closed Loop
FAT Function loop test procedure
Control System FAT Test
2.4) Cause & Effect Test: OBJECTIVE: The purpose of this test is to verify that the logic is implemented and working as per design (C&E). The logic sequence will be tested exactly as per C&E and normal plant operating conditions, with each steps performed in sequence.
REFERENCE DOCUMENT/DRAWING: 1. 2. 3. 4.
Cause and effect
I/O wiring data base Loop diagram Logic Diagram
Cause & Effect
Pump 5901 Logic
Control System FAT Test
2.5) Graphics / Faceplate check: OBJECTIVE: The purpose of this section is to check the Static Displays against the P&ID, and that the graphic symbols developed in the graphics are as per the project specifications. REFERENCE DOCUMENT/DRAWING: 1. All Applicable P&ID Sheets
2.6) Performance Check
OBJECTIVE: The purpose of this section is to check and list the workstation and FCP loading and available free space in each hard disk drive of all the workstations and to check and list each FCP Scan time. 10
Control System FAT Test
Control System SAT test:
1)SAT test shall perform same as FAT test procedures but the difference shall be in INPUT /OUTPUT checks where 2 or 3 signals per module shall be tested as FAT test in order to ensure that the communications between systems & marshalling cabinets, HMI, and system network are established 2) SAT test results shall be recorded in Pre-commissioning check list. ESD check list