Professional Documents
Culture Documents
Project :
Combination of interrelated activities
which must be executed in a certain order
before the completion of entire task.
Project management :
Project planning
Manpower, financial, material etc
Project scheduling Start and finish time, allocation of
resources etc
Project controlling
measures
History
Developed in 1950s
CPM by DuPont for chemical plants
PERT by U.S. Navy for Polaris missile
CPM developed by Du Pont and the emphasis was on the tradeoff between the cost of the project and its overall completion
time (e.g. for certain activities it may be possible to decrease
their completion times by spending more money - how does this
affect the overall completion time of the project?)
PERT was developed by the US Navy for the planning and control of
the Polaris missile program and the emphasis was on completing the
program in the shortest possible time. In addition PERT had the
ability to cope with uncertain activity completion times (e.g. for a
particular activity the most likely completion time is 4 weeks but it
could be anywhere between 3 weeks and 8 weeks).
directionally
Indicate ACTIVITY, a time consuming effort that is
required to perform a part of the work.
Nodes
A completion of an
activity is represented by
a node
AON network diagrams
place the activities within
the nodes
Arrows are used to
indicate the sequence
requirements
An arrow represents a
task, while a node is the
completion of a task
Arrows represent order
of events
Activities
Represent project operations (task) to be conducted
An arrow is commonly used to represent an activity
with its head indicating the direction of progress in
the project
Types
Predecessor Activity Activities must be completed
before other activities start.
Successor Activity - Activities must starts immediately
after other activities are completed.
Dummy Activity Activities which doesnt consume
either any resource or time.
The main purpose of introducing
the DA is to establish logic relationship between networks
Errors in network
Looping (Cycling)
Drawing an endless
loop in a network
Dangling
Redundancy
dummy activity
Representation
1
A
3 days
Formative assessment 1
1. In the project network, activities and events are represented by
a)line and circle
b)circle and line
c)line and arrow
d)dotted line and arrow
3. The chain that connects the initial event to adjacent event is called
i)path
j)event
k)activity
l)node
Problem
Draw a network diagram for the following
set of activities and number the events
A < C, B
B < D, E
C<F
E<G
F < I, J
J<K
G<L
K,L < M
Problem
Draw a network for the simple project of creating a
steelwork for a shed. The various activities of the project
are as follows.
Activit
y
Job description
Preceeded by
Erect site
workshop
Fence site
Bend
reinforcement
Dig foundation
Fabricate
steelwork
Install concrete
pillars
Place
reinforcement
C,D
Concrete
G,F
Formative assessment 2
1. In the project network, > symbol indicates
a)left side activity is carried out first
b)right side activity is carried out first
c)left side activity is completed before starting the activity
given on right side
d)right side activity is completed before starting the activity
given on left side
History of CPM
1956 at the EI Pont Nemours and
Company, USA
Schedule their routine plant
overhaul, maintenance and
construction work
Applications
Production management - for the
jobs of repetitive in nature where the
activity time estimates can be
predicted with considerable certainty
due to the existence of past
experience.
Construction of building, Road &
Bridge
Physical verification of store
Yearly closing of accounts by
Critical Path
The path connecting the first initial node to the very
last terminal node of longest duration in any project network.
The series of tasks (or even a single task) that dictates
the calculated finish date of the project (i.e., when the last task
in the critical path is completed, the project is completed).
The "longest" path (in terms of time) to the completion
of a project. If shortened, it would shorten the time it takes to
complete the project. Activities of the critical path would not
affect completion time even if they were done more quickly.
18
Contd
Finding the critical path is a major part of controlling
a project.
The activities on the critical path represent tasks that
will delay the entire project if they are delayed.
Manager gain flexibility by identifying noncritical
activities and replanning, rescheduling, and
reallocating resources such as personnel and finances
Time calculations
Earliest Start Time : Time at which
the event is expected to occur at
earliest (EST)
Earliest Finish Time (EFT) : EST +
duration
Latest Finish Time : Time at which
the activity can be completed by
latest
without
affecting
the
completion of project (LFT)
Latest Start Time (LST) : LFT -
Late Start (LS) and Late Finish(LF) use the backward pass
technique.
MEMORY TRIGGER: if the float of the activity is zero, the
two starts (ES and LS) and the two finish (EF and LF) are the
same. Hence, If float of activity is zero, ES = LS and EF = LF.
21
Slack Time
The amount of time a task can be delayed before the
project finish date is delayed.
Total slack can be positive or negative.
If total slack is a positive it indicates the amount of time
that the task can be delayed without delaying the project
finish date. If negative, it indicates the amount of time that
must be saved so that the project finish date is not delayed.
Total Slack = Latest Start - Earliest Start.
By default and by definition, a task with 0 slack is
considered a critical task. If a critical task is delayed, the
project finish date is also delayed. (Also known as float
time)
22
Floats
Total
Free
Independent
Problem
Time
(days)
10
8
1-4
2-5
3-7
16
4-6
5-7
5-8
6-7
6-9
7-10
12
8-10
13
9-10
15
Problem
Time
(days)
6
3
1-4
2-5
2-8
3-6
4-6
4-7
5-8
6-8
6-9
7-9
8-10
9-10