WELCOME TO
39 th ORT
MEET
* * * 14 th Jan 2015 * * *
Agenda for 39
th
ORT
1. Presentation By H O team on
(A) All INDIA Performance .
(B) Mahagenco Stations Performance .
(C) O&M and other issues.
2. Presentation by SE(Operation-II ) on
Loadability constraints for Unit 5,6,7 not running the units
at rated capacity.
3. Presentation by SE (Operation I),
Unit 3 Major surprises & achievements and detail report
on unit performance after overhaul.
Many Many
Congratulations to
CHP
On 28-12-14
611 Wagons unloaded
maximum in last 10
years
DAHANU
500
1/1
97.51 / 100.47
TORANGALLU (JSW)
860
2/3
96.53 / 96.51
1000
3/4
96.37 / 96.34
KAKATIYA (Andhra)
500
4/5
95.00 / 94.75
BUDGE BUDGE
750
5/2
93.34 / 96.55
TALCHER (Old)
460
6/7
91.80 / 91.17
SOUTHERN Rep.
135
7/6
91.15 / 93.57
ROSA
1200
8/9
87.79 / 88.91
TALCHER (Kaniha)
3000
9 / 12
87.63 / 86.03
240
10 / 10
87.36 / 88.34
2600
11 / 13
87.28 / 85.89
400
12 / 8
86.86 / 89.48
OP JINDAL
TITAGARH
RAMAGUNDAM
TORRANT POWER
CAPACIT
Y
RANK
PLF (%)
KORBA
2600
14 / 15
85.63 / 85.24
UNCHAHAR
1050
15 / 16
84.98 / 84.65
SIMHADRI
2000
16 / 18
83.17 / 82.58
500
17 / 14
82.86 / 85.59
SIPAT
2980
18 / 23
82.68 / 81.36
1340
19 /
82.05 / 80.80
NEYVELI (Z)
250
20 / 21
81.85 / 82.26
SINGRAULI
2000
21 / 19
81.53 / 82.58
TUTICORIN
1050
22 / 22
81.36 / 81.63
KOTA ( Rajasthan)
1240
23 / 25
81.27 / 80.68
360
24 / 17
81.22 / 83.54
DSPM (Chhattisgarh)
JOJOBERA
178015 /
177052
56932 / 56333
3865 / 3865
CENTRAL SECTOR
53954 / 53591
SEBS
62263 / 63263
NTPC
37032 / 37032
MSPGCL*
7480 / 7480
65.09 /
65.07
62.74 /
62.90
68.14 /
69.54
73.39 /
73.24
59.77 /
59.62
79.42 /
79.16
56.97 /
56.29
BEST
POWER STATIONS
MAHAGENCO
DURING Dec 2014 (Nov 2014 )
STATION
CAPACI
TY
(MW)
KHAPERKH
1340
EDA
NASHIK
630
2nd / 2nd
PARAS
500
3rd / 1st
1420
4th / 5th
BHUSAWAL
RANK
PLF (%)
1st / 3rd
79.54 /
75.41
78.29 /
76.06
77.68 /
77.15
60.18 /
50.77
WATER
SHORT LOSS
%
LOSS
%
KHAPERKHE
DA
UNIT
4
210
1/3
89.48 /
81.26
3.09
5.02
KHAPERKHE
DA
UNIT
3
210
2/1
88.75 /
81.80
3.61
4.35
NASHIK
UNIT
3
210
3/2
87.77 /
81.62
0.35
4.96
PARALI
UNIT
6
250
4/6
86.88 /
77.88
10.52
2.33
NASHIK
UNIT
5
210
5 / 14
85.53 /
71.71
0.48
4.23
CHANDRAP
UR
UNIT
4
210
6/4
83.58 /
81.04
1.59
8.80
PARAS
UNIT
3
250
7/5
81.20 /
77.94
7.63
2.54
KORADI
UNIT
210
8 / 13
78.77 /
5.46
0.63
ON
PLF (%) Dec - 2014 (Nov
COAL /
LD
STATION
UNIT CAPACIT RANK
PLF (%)
WATER
LOSS
Y
-2014)
SHORTAGE
KHAPERKH
EDA
UNIT
5
500
15 /
15
74.54 /
71.54
2.44
5.97
PARAS
UNIT
4
250
16 / 8
74.17 /
76.37
4.81
1.53
CHANDRAP
UR
UNIT
6
500
17 /
17
72.40 /
69.32
5.16
3.98
PARALI
UNIT
5
210
18 /
16
70.59 /
70.82
14.41
0.91
KORADI
UNIT
6
210
19 /
21
65.13 /
62.28
5.14
0.40
CHANDRAP
UR
UNIT
2
210
20 /
19
64.50 /
64.06
2.45
0.02
CHANDRAP
UR
UNIT
7
500
21 /
20
63.86 /
63.41
8.45
3.35
NASHIK
UNIT
4
210
22 /
10
61.56 /
74.84
0.68
2.80
2014
(Nov
2014)
UNIT
CAPACIT RANK
LF (%)
SOC ml/kwh
Y
KHAPERKHEDA 4
210
1/3
89.48 / 81.26
0.093 / 0.01
KHAPERKHEDA 3
210
2/1
88.75 / 81.80
0.000 / 0.00
NASHIK - 3
210
3/2
87.77 / 81.62
0.124 / 0.22
PARALI - 6
250
4/9
86.88 / 78.67
0.291 / 0.43
NASHIK - 5
210
5/6
85.53 / 80.14
0.157 / 1.30
PARALI - 7
250
6/8
84.23 / 79.14
0.532 / 0.51
NASHIK - 4
210
7/7
83.91 / 79.55
1.726 / 0.86
CHANDRAPUR 4
210
8/4
83.58 / 81.04
0.031 / 0.30
KHAPERKHEDA
-5
500
9/5
83.51 / 80.55
1.200 / 0.62
PARAS - 3
250
10 / 10
81.20 / 77.94
0.131 / 0.18
BHUSAWAL - 4
500
11 / 18
80.47 / 69.85
0.199 / 0.56
500
15 / 14
76.58 / 71.98
0.320 / 0.04
KHAPERKHEDA 2
210
16 / 13
75.09 / 72.61
0.196 / 0.70
BHUSAWAL - 5
500
17 / 17
74.98 / 69.90
0.007 / 1.24
KORADI 6
210
18 / 21
74.91 / 68.23
1.746 / 2.02
CHANDRAPUR
7
500
19 / 22
73.57 / 66.91
0.267 / 1.14
CHANDRAPUR 6
500
20 / 19
72.40 / 69.32
0.150 / 0.18
BHUSAWAL - 3
210
21 / 23
71.28 / 66.85
2.167 / 0.69
PARALI - 5
210
22 / 16
70.59 / 70.82
0.000 / 0.17
CHANDRAPUR 2
210
23 / 20
65.32 / 68.35
0.784 / 0.92
CHANDRAPUR 3
210
24 / 24
64.83 / 65.47
25.96 / 0.64
MAHA
GENC
O NO
OF
UNITS
11
Units having LF
>80 %
11
Units having LF
between 70 & 80
%
11
13
UNIT 4
210
76.999
NASHIK
UNIT 5
210
76.884
KHAPERKHEDA
UNIT 4
210
75.132
NASHIK
UNIT 4
210
75.033
PARAS
UNIT 4
250
74.706
NASHIK
UNIT 3
210
70.361
UNIT 4
210
94.05
KHAPERKHEDA
UNIT 5
500
93.97
KORADI
UNIT 7
210
93.76
KHAPERKHEDA
UNIT 4
210
93.75
BHUSAWAL
UNIT 5
500
93.50
KHAPERKHEDA
UNIT 2
210
93.14
PARAS
UNIT 4
250
92.73
NASHIK
UNIT 5
210
91.69
CHANDRAPUR
UNIT 5
500
10
91.38
NASHIK
UNIT 4
210
11
90.12
UNIT 5
210
83.84
NASHIK
UNIT 4
210
83.25
NASHIK
UNIT 3
210
82.99
CHANDRAPUR
UNIT 4
210
81.80
PARAS
UNIT 4
250
80.56
KHAPERKHEDA
UNIT 4
210
80.13
PARALI
UNIT 6
250
79.41
KHAPERKHEDA
UNIT 3
210
79.07
PARALI
UNIT 7
250
78.08
CHANDRAPUR
UNIT 5
500
10
75.09
PARAS
UNIT 3
250
11
74.62
MAHAGENCO
THERMAL
POWER
STATIONS
MONTHLY
PERFORMANCE
Dec - 2014
V/S
Dec - 2013
Mu Dec -2014
GEN
MU
BTPS
CSTP
S
KHDT
PS
KTPS
NTPS
PRST
PS
PTPS MAHAG
ENCO
DEC
14
356.8
90
1025.7
85
793.01
0
224.83
2
366.95
2
288.9
82
410.9
00
3467.35
5
DEC 13
351.0
90
958.82
4
619.60
0
221.24
0
372.12
294.7
78
483.8
30
3301.48
6
PLF %
BTP
S
CSTP
S
KHDT
PS
KTPS
NTPS
PRST
PS
PTPS
MAHA
GENC
O
DEC
14
52.1
4
58.92
79.54
48.74
78.29
77.68
48.88
62.30
DEC 13
51.2
9
55.07
62.15
47.96
79.39
79.24
57.55
59.32
AVF %
BTPS
CST
PS
KHDT
PS
KTPS
NTPS
PRST
PS
PTPS
MAHA
GENC
O
DEC
14
66.31
76.6
1
95.99
63.32
91.12
96.68
60.33
77.82
DEC 13
81.36
73.6
0
87.29
70.11
94.44
94.05
79.89
80.79
LF %
BTPS
CSTP
S
KHDT
PS
KTPS
NTPS
PRST
PS
PTPS
MAHA
GENC
O
DEC 14
78.6
3
76.91
82.86
76.97
85.92
83.35
81.02
80.07
DEC -
63.0
74.82
71.20
68.41
84.06
84.25
72.04
73.43
SOC
ml/Kw
h
BTPS
CSTP
S
KHDT
PS
KTPS
NTPS
PRST
PS
PTPS
MAHA
GENC
O
DEC
14
0.56
0.61
0.53
0.86
0.56
0.25
0.29
0.53
DEC -
1.87
0.95
4.35
3.96
0.61
0.48
0.72
1.77
APC %
BTPS
CSTP
S
KHDT
PS
KTPS
NTPS
PRST
PS
PTPS
MAHA
GENC
O
DEC
14
7.69
8.41
7.99
12.21
10.96
10.74
10.92
9.25
DEC -
10.7
8.65
9.31
13.32
10.82
10.27
10.89
10.03
Station
BTPS
CSTPS KPKD
KTPS
NTPS PRSTP
S
PTPS
8.84
8.34
10.81
13.35
8.50
11.58
8.65
9.31
13.32
10.82
10.27
10.89
Deviatio - 2.55
n
Dec Normati 8.17
-14
ve
Actual
7.69
0.19
- 0.97
- 2.51
2.53
- 1.77
0.69
8.75
8.33
10.51
13.48
8.50
11.68
8.41
7.99
12.21
10.96
10.74
10.92
0.34
0.34
- 1.70
2.52
- 2.24
0.76
Deviatio
n
0.48
HR
Kcal/K
wh
BTP
S
CSTP
S
KHDT
PS
KTPS
NTPS
PRST
PS
PTPS
MAHA
GENC
O
DEC
14
2458
2647
2524
2777
2688
2454
2544
2584
DEC -
2619
2687
2566
2841
2687
2426
2745
2653
Station
BTPS
KTPS
NTPS PRSTP
S
PTPS
Dec Normati
-13
ve
2580
2686
2538
2835
2736
2450
2669
Actual
2619
2687
2566
2841
2687
2426
2745
Deviatio
n
- 39
-1
- 28
-6
49
24
- 76
2570
2680
2539
2814
2719
2450
2668
Actual
2458
2647
2524
2777
2688
2454
2544
Deviatio
n
112
33
15
37
31
-4
124
Dec Normati
-14
ve
CSTPS KPKD
FORCED
OUTAGE
%
BTP
S
CST
PS
KHDT
PS
KTPS
NTPS
PRST
PS
PTPS
MAHA
GENC
O
DEC 14
10.8
7
3.13
4.01
4.42
8.88
0.00
2.50
4.53
DEC - 13
18.6
4.34
12.71
18.51
5.56
5.95
1.94
8.62
PLANNE
D
OUTAGE
%
BTP
S
CST
PS
KHDT
PS
KTPS
NTPS
PRST
PS
PTPS
MAHA
GENC
O
DEC 14
22.8
3
11.0
7
0.00
0.00
0.00
0.00
0.00
6.27
PLF%
KPKD
(79.5
4)
NTPS
(78.29
)
PRTP
S
(77.6
8)
CSTPS
(58.92
)
BTPS
(52.14
)
PTPS
(48.88
)
KTPS
(48.74
)
Availabili
ty %
PARA
S
(96.6
8)
KPKD NTPS
(95.99
)
(91.1
2)
CSTPS
(76.61
)
BTPS
(66.31
)
KTPS
(63.32
)
PTPS
(60.33
)
Loading
Factor %
NTPS
(85.9
2)
KPKD
(82.86
)
PTPS
(81.0
2)
PRTPS
(80.35
)
BTPS
(78.63
)
KTPS
(76.97
)
CSTPS
(76.91
)
PARA PTPS
S
(0.30)
(0.25)
KPKD
NTPS
(0.56)
BTPS
(0.56)
CSTPS
(0.61)
KTPS
(0.86)
(0.53)
APC %
Deviatio
n
NTPS
(2.52)
PTPS
(0.76)
BTPS
(0.48)
KPKD
(0.34)
CSTPS KTPS
(0.34)
(1.70)
PRTPS
(2.24)
Heat
PTPS
BTPS
KTPS
CSTPS
NTPS
PRTPS
SOC
ml/Kwh
KPKD
CUMULATIVE
PERFORMANCE
MAHAGENCO
THERMAL
POWER
STATIONS
April to Dec (2014
15)
V/S
April to Dec (2013
14)
GEN
MU
BTPS
CSTPS
KHTPS
KTPS
NTPS
PRST
PS
PTPS
MAHAG
ENCO
2014 2686.0
60
2015
9247.8
28
5911.7
60
1735.3 3080.7
25
71
2271.8
22
3191.7
60
28125.32
6
2013 2969.1
10
7949.2
86
5028.0
00
1785.4 3115.0
81
93
2491.6
24
2045.2
40
25383.83
4
PLF
%
BTPS
CSTPS
KHTP
S
KTPS
NTPS
PRSTP
S
PTPS
MAHA
GENC
O
20142015
44.24
59.88
66.84
42.41
74.09
68.84
42.80
56.97
20132014
48.90
51.47
56.85
43.63
74.92
75.50
27.42
51.42
AVF
%
BTPS
CSTPS
KHTP
S
KTPS
NTPS
PRSTP
S
PTPS
MAHA
GENC
O
20142015
65.91
83.69
89.92
61.58
88.86
88.56
55.17
77.24
20132014
81.14
76.78
84.26
68.50
89.74
96.61
38.80
74.65
LF %
BTPS
CSTPS
KHTP
S
KTPS
NTPS
PRSTP
S
PTPS
MAHA
GENC
O
20142015
67.12
71.55
74.33
68.87
83.38
77.73
77.58
73.76
20132014
60.27
67.04
67.47
63.70
83.49
78.15
70.67
68.88
SOC
ml /
Kwh
BTP
S
CSTP
S
KHTP
S
KTPS
NTPS
PRSTP
S
PTPS
MAHA
GENC
O
20142015
1.7
1.52
1.33
3.22
1.16
1.23
0.95
1.47
20132014
7.43
3.62
8.25
9.85
1.02
1.37
2.54
4.79
APC %
BTPS
CST
PS
KHTP
S
KTPS
NTPS
PRST
PS
PTPS
MAHA
GENC
O
20142015
10.05
9.21
9.39
13.22
11.36
11.38
11.22
10.21
20132014
11.51
10.34
10.56
14.46
11.16
11.83
11.79
11.08
Station
BTPS
2013 Normati
ve
2014 Actual
8.19
CSTPS KPKD
8.84
8.34
KTPS
NTPS PRSTP
S
10.81 13.35
8.50
PTPS
11.58
n
2014 Normati
-2015
ve
Actual
8.17
8.75
8.33
10.51 13.48
8.50
11.68
HR
Kcal/k
wh
BTP
S
CSTPS
KHTP
S
KTPS
NTPS
PRSTP
S
PTPS
MAHA
GENC
O
20142015
256
3
2671
2547
2815
2691
2462
2552
2615
2013-
280
2711
2611
2877
2705
2464
2596
2680
Station
BTPS
CSTPS KPKD
KTPS
NTPS PRSTP
S
PTPS
2686
2538
2835
2736
2450
2669
2711
2611
2877
2705
2464
2596
- 25
- 73
- 42
31
- 14
73
2680
2539
2814
2719
2450
2668
Actual
2563
2671
2547
2815
2691
2462
2552
Deviatio
n
-8
-1
28
- 12
116
-225
FO %
BTP
S
CSTPS
KHTP
S
KTPS
NTPS
PRST
PS
PTPS
MAHA
GENC
O
20142015
15.1
9
6.66
4.20
7.68
6.88
5.59
1.40
6.51
20132014
15.5
8
4.95
7.41
18.28
4.71
3.36
4.02
7.54
PO %
BTP
S
CSTPS
KHTP
S
KTPS
NTPS
PRSTP
S
PTPS
MAHA
GENC
O
20142015
15.7
4
5.29
4.44
0.43
4.26
5.33
0.00
14.46
PLF%
NTPS
PARAS
Availabili
ty %
(74.0
9)
(68.84
)
KPKD CSTPS
(66.84
)
(59.88
)
BTPS
(44.24
)
PTPS
(42.80
)
KTPS
(42.41
)
KPKD
NTPS
PARAS CSTPS
(88.86
)
(88.56 (83.69
)
)
BTPS
(65.91
)
KTPS
(61.58
)
PTPS
(55.17
)
PARAS PTPS
KPKD CSTPS
(77.58 (74.33
(77.73
)
)
(71.55
)
)
KTPS
(68.87
)
BTPS
(67.12
)
KPKD NTPS
PARA
(1.101 (1.164
S
)
)
(1.225
)
BTPS
(1.299
)
CSTPS
(1.518
)
KTPS
(3.218
)
PTPS
(0.46)
BTPS
(-
KTPS
(-
PRTPS
(-
(89.9
2)
Loading
Factor %
NTPS
(83.3
8)
SOC
ml/Kwh
PTPS
(0.85
2)
APC %
NTPS
CSTPS KPKD
((-
PS
PS
GENCO
4
(3)
5 (7)
1
(15)
4
(10)
2
(3)
1 (2)
1
(2)
18
(42)
2
1 (3)
(1)
0 (0) 0 (0)
0 (0) 0 (0)
0 (1)
1
0
0 (1)
(1)
(2)
0 (0) 0 (0) 0 (0) 0 (0)
0 (0) 0 (1) 0 (0) 0 (0)
1
(0)
0 (0)
0 (0)
5 (9)
0 (1) 0 (0)
0 (1) 0 (0)
0 (0)
0 (0)
2 (2)
0 (9)
0 (0) 0 (0)
0 (0) 1 (0)
0 (0)
0 (0)
0 (1)
1 (0)
0 (0) 0 (0)
0 (0)
0 (0)
0 (0)
0 (1)
BFP PROBLEM
0 (0)
0 (0)
0 (0)
VACUUM LOW
0 (0)
0 (0)
CONDENSER
TUBE LKG
1 (0)
HYDROGEN
LEAKAGE
PS
ENCO
0 (0) 0 (0)
0 (0)
0 (0)
0 (0)
0 (0)
0 (0) 0 (0)
0 (0)
0 (0)
0 (0)
0 (0)
0 (0)
0 (0) 0 (0)
0 (0)
0 (0)
1 (0)
0 (0)
0 (0)
0 (0)
0 (0) 0 (0)
0 (0)
0 (0)
0 (0)
ELECTRICAL
PROBLEMS
0 (0)
1 (1)
0 (2)
1 (4) 0 (1)
0 (0)
0 (0)
2 (8)
TIC PROBLEMS
0 (0)
1 (1)
0 (0)
1 (2) 0 (0)
0 (0)
0 (0)
2 (3)
CHP PROBLEM
0 (0)
0 (0)
0 (0)
0 (0) 0 (0)
0 (0)
0 (0)
0 (0)
START UP /
WITHDRAWL
0 (0)
0 (0)
0 (0)
0 (0) 0 (0)
0 (0)
0 (0)
0 (0)
ANY OTHER
PROBLEM
1 (0) *1 (2)
1 (5)
5 (9)
* U#5
GTR B
Jumper
Switch
Yard
* Switch
Yard
problem
CSTP
S
KHDT
PS
KTPS
NTPS
PRST
PS
PTPS
MAHAGENC
O
TRIPPINGS
60
(86)
72
(69)
40
(90)
38
(68)
30
(35)
24
(18)
24
(25)
288 (391)
BTL
22
(5)
26
(27)
13
(13)
9
(15)
13
(8)
6 (6)
3 (0)
92 (74)
PR PART
LEAKAGE
0 (0)
5 (2)
0 (0)
0 (0)
1 (0)
0 (2)
0 (0)
6 (4)
COAL
CYCLE
PROBLEM
0 (0)
0 (0)
0 (1)
0 (1)
0 (0)
0 (0)
0 (0)
0 (2)
ID/FD/PA
FAN
6
(13)
4 (1)
3 (1)
12
(17)
8 (1)
1 (0)
1 (0)
35 (33)
FLAME
FAILURE /
FUENACE
DRAFT
7
(35)
1 (8)
11
(42)
9 (9)
0 (2)
5 (7)
6 (2)
39 (105)
DRUM
LEVEL
2 (5)
1 (2)
1 (4)
0 (0)
0 (0)
1 (0)
2 (3)
7 (14)
GOVERNIN
G PROBLEM
1 (1)
3 (0)
1 (1)
0 (0)
0 (0)
0 (0)
3 (1)
8 (3)
CSTP KHDT
S
PS
KTPS NTP
S
PRSTP
S
PTPS
MAHAGEN
CO
BFP
PROBLEMS
0 (0)
0 (0)
0 (0)
0 (1)
0 (0)
0 (0)
0 (0)
0 (1)
VACUUM
LOW
3 (1)
2 (0)
0 (1)
0 (0)
1 (0)
0 (1)
0 (1)
6 (4)
CONDENSE
R T/L
1 (1)
0 (0)
0 (0)
0 (1)
0 (0)
0 (0)
0 (1)
1 (3)
HYDROGEN
LEAKAGE
0 (0)
0 (0)
0 (0)
0 (0)
0 (0)
0 (0)
0 (0)
0 (0)
ELECTRICA
L
PROBLEMS
9 (6)
11
(6)
6 (5)
1 (5)
2 (4)
2 (0)
6 (4)
37 (30)
TIC
PROBLEMS
4 (1)
5 (3)
2 (5)
2 (5)
4 (1)
1 (0)
1 (0)
19 (15)
CHP
PROBLEM
0 (1)
0 (1)
0 (1)
1 (5)
0 (0)
2 (1)
0 (3)
3 (12)
START UP /
WITHDRAW
AL
0 (0)
0 (0)
0 (0)
0 (0)
0 (0)
0 (0)
0 (0)
0 (0)
ANY OTHER
12
3 (16)
3 (9)
6 (1)
2 (10)
31 (85)
provisional
Deemed AVF / PLF considered as provided by Works
section
% Aux. Consumption
85.00%
80.00%
80.00%
80.00%
72.00%
80.00%
85.00%
80.00%
80.00%
80.00%
72.00%
80.00%
85.00%
80.00%
80.00%
80.00%
72.00%
80.00%
9.77%
10.80%
11.80%
11.32%
10.81%
8.91%
9.74%
10.79%
13.35%
14.02%
10.81%
8.84%
80.00%
85.00%
85.00%
85.00%
9.00%
8.5%
8.5%
8.5%
80.00%
85.00%
85.00%
85.00%
9.00%
8.5%
8.5%
8.5%
80.00%
80.00%
85.00%
85.00%
85.00%
85.00%
85.00%
85.00%
7.50%
7.50%
6.00%
6.00%
6.00%
6.00%
6.00%
6.00%
85.00%
85.00%
85.00%
6.00%
6.00%
6.00%
55.00%
55.00%
55.00%
3.00%
3.00%
3.00%
BSL-5
Gas Thermal 55.00%
2.40%
9.71% 9.70%
10.75% 9.94%
13.48% 13.41%
14.21% 14.57%
10.51% 9.91%
8.75% 8.71%
50
SHR kcal/kWh
Station
Khaperkheda
2613
2606
2607
2607
2594
2588
2589
2589
Bhusawal
2788
2764
2743
2739
2772
2746
2725
2721
Nasik
2757
2736
2719
2715
2728
2709
2692
2688
Parli
2868
2842
2841
2850
2849
2824
2823
2832
Koradi
2826
2835
2814
2761
2799
2810
2788
2735
Chandrapur
2698
2686
2680
2684
2680
2668
2662
2666
2500
2450
2450
2450
2481
2441
2441
2441
2500
2450
2450
2450
2481
2441
2441
2441
2450
2425
2425
2425
2431
2416
2416
2416
2450
2425
2425
2425
2432
2416
2416
2416
2425
2425
2425
2416
2416
2416
2017
2021
2025
Paras-3
Paras-4
Parli-6
Parli-7
KPKD-5
BSL-4
BSL-5
Gas Thermal
1980
51
% Transit Loss
Khaperkheda
0.80%
0.80%
0.80%
0.80%
Bhusawal
0.80%
0.80%
0.80%
0.80%
Nasik
0.80%
0.80%
0.80%
0.80%
Parli
0.80%
0.80%
0.80%
0.80%
Koradi
2.81
2.81
2.81
2.81
0.80%
0.80%
0.80%
0.80%
Chandrapur
0.80%
0.80%
0.80%
0.80%
0.80%
0.80%
0.80%
0.80%
0.80%
0.80%
0.80%
0.80%
KPKD-5
0.80%
0.80%
0.80%
0.80%
BSL-4
0.80%
0.80%
0.80%
0.80%
0.80%
0.80%
0.80%
0.80%
Paras-3
Paras-4
Parli-6
Parli-7
BSL-5
52
AHP Unit 3,4 : New & used material are mixed up and
lying around pumps. Segregation will be done after Unit 3
overhaul.
AHP Stage I : Air compressor in AHP not in service since
long , but new compressor procured available at site and
not commissioned
Unit 7 : Spare Coal mill motor not available.
CHP A & B
Multi core control cable is not in stock may lead to
emergency situation Red indent sent to HO ,some
material received.
Average wagon unloading to be increased particularly in
CHP A. Corrective action taken for improved unloading.
Vibrating feeder replaced 2 nos. for fast evacuation -4
feeders replaced, remaining 2 will be replaced in FY-201516. Order under process expected upto Dec-14.
CHP A & B
UNIT 6
% LOSS
APH
9.34
ID /FD/PA
6.76
4.43
Duct lkg/modification
2.24
Electrical Problem
1.52
Coal mill
0.96
UNIT 2
UNIT 2
Fineness of coal mill + 5o mesh : 2B and 2F both is 2.5%
as per November -14 report.
H2 Consumption 166 cylinders in November- 14.
Frequent BTL near Burner Bend. CPRI findings to be
discussed.
IPT Top /Bottom temperatures are 470/429 deg c.
Steam temperature difference between SH outlet and
Turbine inlet is around 30 deg c.
Turbine speed and eccentricity not showing on chart & DCS.
% LOSS
---
Air Heater
----
Vacuum
-----
Governing
1.28
Coal mill
---
UNIT 3
UNIT-3
% LOSS
8.80
2.13
1.59
Coal mill
0.23
UNIT 4
HP CV no 1 : Stem broken since 2-9-14. Presently valve is
kept open, will be attended in opportunity shutdown.
Air Heater leakage - 41.73/36.35 %
CW PUMP No 5 : N/A due to vibration, Impeller repairing
work order to be placed.
Availability of soot blowers poor, 36 available out of 56.
Now availability is increased upto 45.
% LOSS
8.21
4.10
Air Heater
1.91
Vacuum
0.98
Electrical Problem
0.29
UNIT 5
Primary
APH
air
outlet
temperature
is
running
% LOSS
5.15
Vacuum
4.04
3.98
Air Heater
3.00
Duct lkg
1.98
UNIT 6
High energy drain valve Passing, Before ESV-3 (202 DEG),
MAL -14 (149 DEG ) -S/D JOB
Turbine
Bearing
no
4-
Velocity
component
is
9.--
APH
air
outlet
temperature
is
running
UNIT 6
Estimated CW Flow is 32659 T/hr against that of Unit 5
(56317) and Unit 7 (45193)
Condenser vacuum very poor- 8180 mmHg @ 390 MW.
Condenser Cleanliness factor is 35% against design of
89%. COH JOB.
Both TDBFP steam consumption is high.COH JOB
UNIT 6
Primary APH : Dry flue gas losses are
166.58
kcal/kwh
Primary Air heater leakages are 27.4/26.2 %
Secondary Air heater leakages are 41.9/42.6 %
TG
Bearing
no.
side(90micron).
1
AOH,
vibration
on
Minimum
higher
10
days
shutdown needed.
Around 400 MW load , 2 TD BFPs and 1 MD BFP
is to be operated.
8.45
3.35
Coal Mills
3.07
Electrical Problem
0.08
TIC Problem
0.12
UNIT 7
UNIT - 7
UNIT - 7
WTP I and II
SITE VISIT ISSUES
WTP 1
Spent
brine injection system is not in service leading to
extra requirement of salt. Spent brine process building is
about to collapse "FOR ST-I T-1382-Repair of spent brine
tank & pump house for ST-II T-1306 -Proposal for new
construction -order to be placed" CIVIL Pending .
WTP2
Regeneration system of DM Plant is not Healthy -Temporary
arrangements are made for permanent arrangement work
is being carried out by project. PO for AMT is placed.
Pipeline replacement work is to be carried out by project.
Tender not yet finalized.
Chlorination system is kept in service in general shift only.
Chlorine dioxide treatment is in service from 25/06/2014
along with chlorination at CW system.
DM Storage tank Inlet & Outlet valve passing
shall be taken up during Unit# 6 COH.
PRESENTATION BY
SE (Operation)-II
PRESENTATION BY SE
(Operation-I)
PRESENTATION BY MPD