DMRC PHASE -III

Project Site:- Munirka,Metro Station.


L&T SUCG JV
DMRC CC-27

Submitted by:
Ayush srivastava
1324000024

Construction Method
Top down Method:
Munirka station is made by the top down method due to lack of construction area.
After the construction of D-wall, Excavation took place and roof slab was prepared
and then similarly after executing excavation concourse slab and base slab was
accomplished respectively and at last platform slab was prepared.
Procedures:

PROJECT INFORMATION DMRC CONTRACT NO. CC 27


DESIGN AND CONSTRUCTION OF TUNNEL FROM END OF
UNDERGROUND RAMP ( NEAR SHANKAR VIHAR METRO
STATION)
TO
HAUZ
KHAS
METRO
STATION
AND
UNDERGROUND RAMP NEAR SHANKAR VIHAR METRO
STATION AND UNDER GROUND METRO STATIONS AT VASANT
VIHAR , MUNIRKA, R.K.PURAM, IIT AND HAUZ KHAS ON
JANAKPURI WEST - BOTANICAL GARDEN CORRIDOR OF
DELHI MRTS PROJECT OF PHASE - III (CONTRACT NO. CC-27UG 2)

PROJECT DETAILS
Client

M/s Delhi Metro Rail Corporation Limited

Nature of Contract
:

Lumsum - Design and Build Contract (Civil &


Architectural)

Contractor

L&T-SUCG JV

Letter Of
Acceptance

DMRC/20/III-057/2012 dated: 1st Nov 2012


:

Contract Price
Contract Period
:
Completion Date
:
DLP Period
:

INR 1252.6 Cr.


42 Months
December 2016
52 Weeks after Taking Over Certificate

Project features
Total Length
=

6.82 KM

No of Stations
=

5 No.( Hauz Khas, IIT, R.K Puram, Munirka and Vasant


Vihar)

No. of Cross
Passages =

18

Station Length
=

1326 Mtr

Station Width
=

21.57 Mtr.

Entry Exit
=

11 Nos

Total TBM Tunnel


=

4.307 Km

C&C Tunnel
=

0.270 Km

NATM/TBM
=

0.756 Km

Length of Ramp

0.160 Km

MUNIRKA STATION

MUNIRKA INSERTIONS LEVEL

SALIENT FEATURES
Length of station
:
Shaft

268 Metre
Towards RKP launching shaft and towards VV
Retrieval shaft

Length of Guide
wall
:

588 Rmt.

Number of D-wall
panels:

121 nos. ( LS 14 nos., RS 13 nos., Station box 94


nos. )

Panel features
:

Length Avg. 5 meter, width 800 mm , depth 21


24 Metre

Entry / exit

3 nos.

Method of
construction

Top down construction

Box pushing

Length 42 meter

Progress pics :-

GUIDE WALL

Guide wall

Construction of Guide Wall

G-Wall Process
Surveyor Works

Excavation of Guide Walls

Reinforcement

Shuttering

Concreting and De-shuttering

Building Diaphragm Wall


This Presentation Describes about the methodology used for building
diaphragm wall.
Diaphragm Wall
Diaphragm wall basically used for following purpose: To create permanent foundations and temporary earth retention wall for deep
basements.
Use in Earth retention schemes for highway or tunnel projects.
Structural support for construction of basement with underground parking.
Also plays the role of retaining Walls.
Stability to landslide ,highway cuts and deep building excavation.

i apphhr raaggmm WWaal ll l AAnni m


i maat ti o
i onn
DDi a

Guide wall

Top Slab
D wall
Concour
se Slab

Base
Slab

Plunge
Column

DIAPHRAGM WALL PANEL


SEQUENCE

Primary Panel

Secondary panel

Closing panel

Panel with
two stopends.

Panel
with
one
stopends

Panel with no
stop-ends