The suspended steel-arch-type FoBs are the first-of-its-kind of


structures built in the country. The bridge, to be used by athletes
during the event, connects the main Jawaharlal Nehru Stadium to a
nearby parking lot.
However, there was a slip in one of the clips that
supported the structure which was attached to the end
of the suspenders dangling

from an arch. The structure


fell while concrete
Engineers
proposed to broadly retain

poured original
into one of the
the was
foot being
over bridge's
decks.
rainbow
design that had a
prefabricated steel walking slab
hung from 26 steel wires called
suspenders

COLLPASED FOOTOVER BRIDGE

The bridges were rebuilt using alternate


suspender system of Freyssinet Suspenders
which are manufactured using specific
industrial processes including heat treatment
(quench and tempered) that ensures
increased mechanical characteristics.
Quenched and tempered steel is
characterized by high strength and good
Quenching and tempering
ductility.
consists of a two-stage
heat-treatment process.

Stage 1 includes
hardening, in which the
plate is austenitized to
approximately 900C and
then quickly cooled. The
material is water-quenched
in a quench unit
Stage 2 consists of
tempering the material to
obtain
the desiredGIVEN
material
HEAT TREATMENT
TO
properties.
STEEL TO
OBTAIN DESIRED
PROPERTIES

FREYSSINET
SUSPENDERS

Its a beautiful structure spanning 95


metres.
All the steel used were procured from
SAIL and TATA.

STEEL SUSPENDER JOINERY TO THE


BEAM

STAIRCASE : CARRIAGEWAY BEAM


STRUCTURE USED WITH STEEL SHEETS

TREAD = 300MM
RISER = 150 MM
HEIGHT OF RAILING
= 1.2M

CARRIAGE

The framework, made of iron


grills serving as support for the
floor and the railings

IRON GRILLS- SUPPORT FOR


FLOOR
DEEP DECKING SHEETS PLACED
DIRECTLY OVER THE BEAM.
FINAL FINISH OF CHEQUERED
TILES

TURN OF HANDRAIL AT THE LANDING


LEVEL
CONNECTION OF BALLUSTER TO TREAD

The new structure, made of portable steel sheets and iron


angles with roadbed width of 12 feet, has been erected on
concrete pillars on either side of the elevated Barapullah
Nallah, on which the earlier structure rested, near Lodhi
Road

They added
three piers to
make the
bridge more
safe.

CONCRETE PILLAR

DETAIL AT A
BOLT

A
BOX SECTION STEEL COLUMNS
RESTING ON RCC PEDESTALS
STRUCTURAL SUPPORT MEMBER

BEAM-COLUMN JOINERY

Expansion joint

EVERY STEP ON WHICH THE


BALUSTER WAS FIXED, WAS
PROTRUDING OUTWARD, AS
SHOWN ON THE LEFT

LANDING WAS ALSO


PROTRUDING

The PWD appointed P&R group to construct two


steel suspended arch bridges weighing 600
metric tonnes and built-up SAW welded steel
box sections.
SAW welding, i.e, submerged arc welding
NOTE:
1t=1000kg

Submerged-arc welding (SAW)


involves the formation of an arc
between a continuously fed
electrode and the workpiece. A
blanket of powdered flux, which
generates a protective gas shield and
a slag, protects the weld zone. A
shielding gas is not required. The arc
is submerged beneath the flux
blanket and is not normally visible
during welding.