Professional Documents
Culture Documents
PIPEWORK FABRICATION
SCOPE
MATERIALS
PROJECT SPECIFICATION:
WELD DESIGN
BUTT WELDS:
Spool pieces shall have excess 100 mm plain end length on one
component of the joint.
RADIAL MISALIGNMENT:
FLANGES:
The distance from the flange face to the pipe end = the pipe wall thickness
+ 3 mm
DIMENSIONAL TOLERANCES:
Up to and
including(mm)
Nom pipe
size(inches)
(+/-)
Tolerances(mm)
250
10
3.2
900
36
4.8
1200
48
5.6
1500
60
6.4
1800
72
WELDING
WELDING PROCEDURE SPECIFICATION (WPS):
All WPS shall be submitted for review by IOCL in accordance with PDRP
8840 SP 0009
WELDING PROCESSES:
Acceptable Welding Processes
PROHIBITIONS:
JOINT DETAILS:
FULL PENETRATION WELDS:
SMAW electrode diameter for the root pass in 3 NPS shall not exceed 2.5
mm.(For carbon and low alloy steels with up to 2% Cr )
GTAW shall be used for root pass in less than 3 NPS.
PROHIBITIONS:
WELDING CONSUMABLES:
Inert gas shall contain not more than 2% oxygen for GTAW or GMAW of
Austenitic stainless steel.
Shielding and purging gases for GTAW welding of Ni alloys shall be in high
purity (99.99%) argon or helium.
Inter pass temperature should not fall below the specified preheat temperature
until the completion of not less than 30% of final weld depth.
Piping shall not be moved until at least 50% of final weld depth is complete.
PWHT:
Carbon Steel
Thickness
(mm)
Min Holding
Temperature
(C)
Time at Holding
Temperatures(Min)
Per mm
Minimum
Up to 19(a)
Over 19(a)
595
595
2.5
2.5
60
60
1 Cr 0.5 Mo
Or
1.25 Cr 0.5 Mo
All (b)
704
2.5
120
2.25 Cr Mo
All (b)
704
2.5
120
5 Cr 0.5 Mo
Or
9 Cr 1 Mo
All (b)
730
2.5
120
Notes:
Except where specifically required by the governing code, or called for in the piping class for process
or other reason, PWHT is not generally required for carbon steel up to an including 19 mm thick.
Where specifically agreed in writing with IOCL, PWHT is not required for small bore(1.5 NS and
below)
EXAMINATION CLASS:
Materials
Class II
Class III
Class IV
Carbon
Steel
900
2500
150
600
150 (b)
Low alloy
steel
150
2500
Cement
lined C.S
All
Austenitic
S.S
900
2500
150
600
Cupro
Nickel
150
2500
Titanium
150
2500
Duplex
S.S
150
2500
Nickel
alloy
150
2500
EXTEND OF NDE
Examination
Class
Examination
methods
Visual
Radiography
(note a)
Mag Particle
Dye
Penetrant
II
Visual
Radiography
(note a)
Mag particle
Dye
Penetrant
Applicable Butt
materials welds
Branch
welds
Fillet/Sock
et welds
Attachment
welds
All
All
100
100
100
-
100
(note b)
100
NR
CS,LAS
Aus S.S
Duplex S.S
& Non
ferrous
100(h
)
100
100(g, h)
100(g)
100
100
100
100
All
All
100
10
100
-
100
10(note b)
100
NR
CS,Aus
S.S
S.S & Non
ferrous
10
10
10(g)
10(g)
10
10
10
10
III(note c)
Visual
Mag particle
CS
CS
100
NA
100
NA
100
100
100
100
IV (note d)
Visual
Mag particle
All
All (note e)
100
100
100
100
NOTES:
a)As per 11.4.2 ultrasonic examination may be utilized when radiography is
inappropriate.
b)Radiography may be used to verify correct gap for socket welding.
c)Examination Class III is applicable to carbon steel concrete lined pipe.
d)Examination Class IV will not normally be used on pressure containing pipe work.
e)Fire water Services: 10% Radiography
Amine Services: 100% Radiography
Concrete lined site joints: Random radiography
f)Including seal welds of threaded joints
g)For branch welds, the required DPI/MPI shall apply to the root pass and final
pass.
h)For butt welds in carbon steel and any low alloy steel piping classes designated
for NACE MR 0103 duty, the MPI shall be:
a.The DC prod method permitted only for non-impact tested carbon steel piping
that is not subject to PWHT. Any arc strikes resulting from this method shall be dressed out.
b.All other material/service combinations shall use the electormagnetic AC yoke method.
c.MPI of welds shall include a minimum of 25 mm of base material either side of the weld
centerline.
If the extent indicated is 10%, this is defined as 100% examination of 1 in 10 of
)those welds indicated
)The first five production welds by each welder should be examined shall cover
)each pipe size
Production macro hardness values shall not exceed 200 BHN for carbon
steel welds or 225 BHN for alloy steel welds.
PRESSURE TESTING:
The chloride content of the hydro test water for austenitic stainless steels
shall not exceed 30 ppm and the hydro test temperature shall not exceed
50C
Austenitic stainless steel weld subject to stress relief or service over 500 C,
shall be subjected to a minimum of 3 ferrite checks per weld.
With minimum of 1 ferrite check per 200 mm length of manual welds.
Ferrite levels shall be in the range of 3% to 10%.
Checking shall be performed before PWHT by using ``Ferritescope or
``Permascope.
REPAIRS
Repairs or not permitted for use on 300 series stainless steels or non
ferrous alloys.
Unacceptable flaws found during NDE shall be repaired in accordance with
an approved repair procedure.
Material
Max no of permitted
repair attempts per weld
CS 300#
CS > 300#
KCS
Austenitic S.S
3.5 % Ni steel
Others
RECORDS
TABLES
Carbon steel
Austenitic S.S:
Type 304(a)
Type 306(a)
Type 321 or 347(a)
SFA-5.28 ER80S-B2
SFA-5.28 ER90S-B3
SFA-5.9 ER502
SFA-5.9 ER505
(wires also for SAW)
SFA-5.9 ER308(a)
SFA-5.9 ER316(a)
SFA-5.9 ER347(a)
SFA-5.11 ENi-1
SFA-5.11 ENiCu-7
SFA-5.11 ENiCrFe-1 or 3
SFA-5.11 ENiCrMo-3
SFA-5.11 ENiCrMo-2
SFA-5.11 ENiCrMo-3
SFA-5.14 ERNiCrMo-3
SFA-5.14 ErNiFeCr-1
Sandvik 22.8.3L
Metrode ER329N
Metrode ER225Cu
Notes:
a.
b.
c.
Where specifically agreed in writing with IOCL, small bore(1.5 NS and below)
socket/fillet
welds, which will not be subject to PWHT, may be performed using SFA-5.11
ENiCrFe-2 or 3 or SFA-5.14 ERNiCr-3 consumables.
Second base
material
GTAW or
GMAW wire
Carbon
Or
low alloy
or
Ferritic S.S
Ferritic S.S
or
Austenitic S.S(e)
Or
Nickel alloys(e)
SFA-5.9
ER309 (a) (b)
Or
SFA-5.14
ERNiCr-3(c)
Carbon steel
SFA-5.11 ENiCu-7
Or
SFA-5.11 ENiCrFe-2
Or
SFA-5.11 ENiCrFe-3
SFA-5.11
ERNiCu-7
Or
SFA-5.14
ERNiCr-3
Consumable to be selected
as per table 1 for carbon
steel
90/10 Cupro-Nickel
SFA-5.11
ENiCrFe-2
Or
SFA-5.11
ENiCrFe-3
SFA-5.14
ERNiCr-3
NOTES:
a)Type E310 or ER310 consumables are specifically prohibited.
b)Type E309 or ER309 consumables shall not be used on nickel alloys, neither shall they be used
for design temperatures exceeding 315 oC where the second base material is ferritic stainless steel.
c)When welds can be exposed to high temperature, sulphur bearing, reducing process conditions
these high nickel alloys shall not be used
d) Where dissimilar base materials have dissimilar PWHT requirements, the detail design, welding and
PWHT sequence shall be subject to agreement with IOCL. Specific requirements apply per (e) and
(f)below.
e) Welding austenitic stainless steels or nickel alloys to low alloy or carbon steels requiring
PWHT:"Butter low alloy or carbon steel with nominal 3mm weld metal before PWHT of low alloy or
carbon steel part(s).Complete weld to austenitic stainless steel or nickel alloy without further PWHT.
f) Welding carbon steels to low alloy steels:- "Butter" low alloy with nominal 3mm weld metal before
PWHT of low alloy part(s). Complete weld to carbon steel without further PWHT unless required for
carbon
steel.
Nominal
thickness at
weld(mm)
Minimum
preheat
temperature(
C)
T 13
13 < T 25
25 < T 50
T >50
10
75
100
150
C-Mo,Mn-Mo,Mn-Mo-Ni,
Mn-Mo-V
T 13
13 < T 25
25 < T 50
T>5
10
75
100
150
1Cr-Mo, 1 Cr- Mo
All
150
315
5A
5B
All
200
315
6&7
All
Per code
Austenitic S.S
All
10
175
9A
2Ni, 3Ni
All
125
250
Carbon steel
Maximum
interpass
temperature(
C)
315
315
Material type
Nominal
thickness at
weld(mm)
Minimum
preheat
temperature
(C)
Maximum inter
pass
temperature(
C)
11A
&
11B
Ni-Cr-Mo,Mn-Mo-Ni,
Ni-Cr-Mo-V
T 13
13 < T 25
T > 25
125
150
175
315
3435
Cu-base alloys
All
10
175
4145
Ni-base alloys
All
10
175
Notes:
1. Preheat temperatures are based on 8ml H2/100g weld metal hydrogen levels. Alternative preheat
temperatures may be calculated in accordance with EN 1011-2, in which case, the WPS and PQR shall show
all limiting factors such as combined thickness, CE value, weld metal hydrogen content and heat input or
run-out-length, upon which the preheat level is based.
2. Preheat requirements are based on conventional carbon steel with CE 0.45 and S > 0.01%.
Low sulphur steels (S 0.01%) may be at higher risk of HAZ hydrogen cold cracking than conventional
carbon steels and fabricator shall review the necessity of increasing the preheat temperature or lowering the
specified CE value for these steels based on fabricators experience.
3. Not required other than to remove moisture prior to welding.
4. Preheat temperature for martensitic type steels shall be 200C minimum but shall not exceed the martensite
finish (Mf) temperature to ensure no untransformed austenite is present during PWHT. The maximum
interpass temperature shall not exceed the preheat temperature by more than 100C.
200C
250C
300C
Up to 10
See note 1
Up to 20
Up to 30
Over 30
10
NOTES:
1.For thicknesses below 10mm the cooling from preheating to
ambient temperature shall be under an insulated cover.
5% < e <
10%
10% < e
<20%
e > 20%
Non- impact
tested(Sour service not
specified)
No heat treatment
required
No heat
treatment
required
SR
Non-impact tested
(Sour service not
specified)
No heat treatment
required
SR
SR
Impact tested(All
services)
No heat treatment
required
SR
Notes:
SR Stress relieve in accordance with Table 5 of this Standard.
N Normalize.
NOTE: a. 'e' shall be calculated by: e=t/2r : r=bend radius t=pipe O.D.
APPENDIX
APPENDIX A - FABRICATION
SPECIFICATION FOR DUPLEX STAINLESS
STEEL
GENERAL:
WELDING:
PREPARATION:
ESSENTIAL VARIABLES:
Any increase in heat input greater than 20% of the maximum reached during the
qualification.
Any change in backing gas conditions including gas composition, flow rate,
damming method or oxygen levels in backing gas enclosure outside those reached
during the qualification test
All welds in duplex stainless steel shall additionally be 100% examined by dye
penetrant method
ACCEPTANCE CRITERIA:
The following features are unacceptable
Any cracks
Any lack of fusion or lack of penetration at the bore surface
Surface breaking porosity.
REPAIR:
One repair per weld is permitted.
If the repair contains unacceptable defects the complete weld shall be cut out
PIPE SUPPORTS:
Internal gas purging shall be required to prevent oxidation/discolouration while
welding directly on to the pressure retaining components of thin wall
Forming and bending of nickel alloys during fabrication shall be carried out at
or below 190C.
Grinding wheels or discs shall be iron free and shall not be organic resin
bonded.
Nickel alloys shall be heat treated to remove the effects of any cold working in
excess of 5% fiber strain, prior to welding.
WELDING:
HEAT CONTROL:
Preheat shall not be used
Temperature of the joint surfaces shall not be less than 20 C before
commencement of welding
The inter pass temperature shall be 150C maximum(except NO8825 120 C)
PWHT shall not be used.
SHIELDING AND BACKING GAS:
The flow rate shall be minimum 15 liters per minute.
INSPECTION:
Welded joints shall be 100% visually examined and 100% liquid penetrant
inspected.
Lack of root penetration in excess of 1.6 mm is not permitted.
SHIELDING/PURGING GASES:
Shielding and purge gases shall comply with EN439 with respect to mixture
tolerances, purity and dew point.
Preheat and interpass temperature:
Minimum preheat temperature 200C
Maximum interpass temperature 300C
For 9 Cr 1 Mo V :
On completion the welds shall be maintained at 200 C 400 C for 2 hrs
after welding.
Joint shall be allowed to cool below 100C prior to receiving PWHT.
PWHT immediately after welding without this intermediate heat treatment
cycle is not permitted.
PQR TESTING REQUIREMENTS:
Test welds shall be subject to 10Kg Vickers hardness survey of the weld.
The maximum hardness shall not exceed 270 HV10.
For impact testing the test temperature shall not exceed 0 C and the
energy
shall be 40J average and 34J average.