Schedule updating
Schedule updating is just one part of the project
control process.
Schedule updating must reflect
Actual work , and
involves change orders (CO) .
9/11/16
What is an updated
schedule?
9/11/16
Frequency of updating
Construction schedules may be
updated monthly , biweekly, weekly, or
according to another time interval .
Project managers must achieve a
delicate balance between updates is
too long and one is too short
9/11/16
9/11/16
For example :
Deleting activity AS520 in the partial network shown in figure will
remove any link between activities in each side.
AS210
TL160
AS250
AS245
9/11/16
AS260
Nabil Dmaidi Najah University
9/11/16
9/11/16
10
Example 1: No Cost
9/11/16
11
9/11/16
12
9/11/16
13
9/11/16
14
Myths/Misconceptions About
Schedule Updating
We always produce a complete schedule
before the commencement of construction.
We just dont update it, We trust our field
staff and subcontractors to follow it.
We update projects only when there is a
need for the update
Everything is going well. There is no need
for an update
9/11/16
15
Quiz 6
True or False:
1. Updating is needed for projects that have
duration of at least one year or a minimum
budget of QAR 10 million
2. Data date is the date all information was entered
in the computer
3. In updating schedules, we must enter not only
actual work progress but also any future changes
4. Negative float is an indication that the schedule
is not meeting its expected completion date or an
interim imposed date
9/11/16
16
Project Control
9/11/16
17
Project Control
Project control is the continuous practice of
1. monitoring work progress,
2. comparing it to baseline budget and schedule,
3. detecting any deviations and their causes, and
4. taking a corrective action wherever and
whenever necessary
18
19
What is a baseline
schedule?
A baseline schedule is a schedule
prepared by the contractor ,usually
before the start of the project ,and used
for performance comparison.
Baseline Budget: The projects original
approved budget including any
approved changes
9/11/16
20
Percent Complete
Percent Complete (PC or PCT): is an estimate,
expressed as a percent, of the amount of
work that has been completed on an activity
or a work breakdown structure component.
(PMBOK 2008)
Percent complete may be used to estimate:
Activity
Project
9/11/16
21
Most importantly:
Know exactly what each percent complete
means
Pick one or two parameters to use and then be
9/11/16 consistent
Nabil Dmaidi Najah University
22
9/11/16
23
Level of Control
Small projects - low cost - short duration
Detailed network
Reporting mechanism
Middle-sized projects (300 activities)
Detailed network
Summary network
Area and craft network
9/11/16
24
3.
25
9/11/16
26
9/11/16
27
9/11/16
28
9/11/16
29
Cost
Total
Duratio
Rate
Cost
($)
Activity n (Days) ($/Day)
A
2
500
1,000
B
17
200
3,400
C
3
300
900
D
5
100
500
E
6
2,000 12,000
F
2
500
1,000
G
1
1,000
1,000
9/11/16
30
9/11/16
31
9/11/16
32
Target Network
9/11/16
33
Project S-Curve
9/11/16
34
9/11/16
35
9/11/16
36
37
38
9/11/16
39
EVA Terminology
BCWS Budgeted Cost of Work Scheduled
Planned cost of the total amount of work scheduled to
be performed by the milestone date. (a.k.a. your
original plan)
40
9/11/16
41
42
CV BCWP ACWP
BCWP
CPI
ACWP
9/11/16
CPI = 1, on budget
CPI < 1, over budget
CPI > 1, under budget
43
SV BCWP BCWS
BCWP
SPI
BCWS
9/11/16
SPI = 1, on schedule
SPI < 1, behind schedule
SPI > 1, ahead of schedule
44
(budgeted)
(earned)
(actual)
9/11/16
Nabil Dmaidi
45
45
Example
A simple problem will help to illustrate the
application of the principles of earned value . A
project has been defined that consist of 12
activities for which the estimated cost and
duration have been defined see figure .
After three and a half month , the activates
1,2,4,5,7 are completed and (6) is one half
complete and(8) is three fourth complete and
(3) is half complete. The incurred cost to date are
152000$ . What is the status of this project in
terms of the schedule and the budget?
Solution
9/11/16
46
Activity
cost
$22000
$10000
$18000
$30000
$50000
$40000
$6000
$16000
$13000
10
$4000
11
$34000
12
9/11/16
$14000
m1
m2
m3
m4
m5
m6
47
Solution
ACWP =152000$
BCWS=22000+30000+50000+10000+18000+0.5(40000+
6000+16000)=161000$
BCWP=22000+30000+50000+10000+6000+0,5(40000)
+0.75(16000)+0.5(18000)= 159000$
SV= BCWP-BCWS= -2000$
CV=BCWP-ACWP= 7000$
EAC=ACWP+(BAC-BCWP)=152000+(257000-159000)
= 250000$
9/11/16
48
II
+
Time
III
IV
9/11/16
49
9/11/16
50
Quiz 7
True or false:
1. Project control is to be practiced by both contractor and
owner
2. Project monitoring is part of project control
3. For assistance in calculating progress payments, percent
4. complete for the project is more important than percent
complete of individual activities
5. It is possible that different parties compute the project
percent complete and come up with different estimates,
yet none of them is wrong!
9/11/16
51