Professional Documents
Culture Documents
Surveys
(Chapter 10)
PROF TERY JOHNSON
Construction Survey
Marking on the ground (using wood stakes, iron
bars, aluminium and concrete monuments, nails,
spikes, etc) features as illustrated or calculated on a
designed plan for engineering projects.
For example, establishing the corners of new house
footings from the property limits or some other
control point.
Construction Project
Process
1)
Construction Project
Process
2) Design Phase:
Design of the feature to be constructed is done inhouse using data collected during the preliminary
phase.
A Design Plan is created using software such as
AutoCAD, MicroSurvey, etc. using the data collected
in the preliminary survey, traverse, level loop and/or
topographic survey.
Construction Project
Process
3) Layout Phase:
(Control, Topographic and Property Surveys may be used
to layout in field what was created in the design phase)
Construction Control
Prior to the start of construction:
Construction Survey used to check/re-establish
horizontal and vertical control points to ensure
the layout is accurate and precise. Preliminary
surveys (control surveys) may have been done
months or years before construction begins.
Control points are established or verified
throughout the construction site to regulate the
line and grade for all points in the project.
Municipal
road
construction
Municipal Road
Construction
Plan and profile or Line and Grade:
Designed feature(s) must be built/laidout so they
meet the horizontal and vertical specifications
accurately and precisely.
In other words:
The blueprint (Design Plan/Layout Plan) shows the
vertical and horizontal details of the features that
must be constructed.
Top-Of-Curb (T-o-C)
CUT and FILL
calculation
BC 0+ 14.5
0+20
0+40
-0.8%
0+45
+1.0%
0+60
0+80
1+00
+1.0%
1+20
C/L Road
Elevations
Stake
elevation
(given)
180.270
- 0.116
180.154
- 0.044
180.110
-0.160
179.950
-0.040
179.910
+0.150
180.060
180.570
0.300
180.325
0.171
180.315
0.205
180.225
0.275
180.110
0.200
180.060
On
grade
+0.200
180.260
+0.200
180.460
+0.200
180.660
Cut
Fill
----------
180.200
0.060
180.445
0.015
180.610
0.050
2%
C/L
0.150m
9m
ROAD CROSS SECTION
0+00
BC 0+ 14.5
0+20
0+40
0+45
0+60
0+80
1+00
1+20
1+43
C/L Road
Elevations
PROPOSED
Top-of-Curb
Elevations
(Add
0.060m)
Stake
elevations
Cut
Fill
180.270
- 0.116
180.154
- 0.044
180.110
-0.160
179.950
-0.040
179.910
+0.150
180.060
+0.200
180.260
+0.200
180.460
+0.200
180.660
+0.230
180.890
180.330
180.570
0.240
180.214
180.325
0.111
180.170
180.315
0.145
180.010
180.225
0.215
179.970
180.110
0.140
180.120
180.060
0.060
180.320
180.200
0.120
180.520
180.445
0.075
180.720
180.610
0.110
180.950
180.914
0.036
Calculating gradient
How to calculate gradient
: RISE or
DISTANCE
RUN
ELEVATION
Sewer
Construction
Sewer Construction
Sewer are described
as:
Sanitary
Storm
http://www.gic-edu.com/805/Distance--Sanitary-Sewer-Stormwater-Drainage-Systems-Design-Workshop-12-PDHs
Sanitary Sewers
Collect industrial, commercial liquid waste and sewage to
treatment plant usually deeper under roadway;
Gradient +/- 2% from basement to sewer main connection;
Between +/- 2.5 - 3.0m below road grade depending on
traffic load and frost penetration in soil and located 1.5m on
either side of C/L road;
Minimum slope 0.67% to achieve a self cleaning velocity of
0.8 to 0.9 m/s to avoid maintenance cost.
NOTE:
In Design Phase elevations of basement floor govern sanitary
sewer depth
Storm Sewers
Collect runoff (rain and snow) and transport this water to
the near natural water body (creeks, rivers, and lakes);
The runoff is collected at catchbasins at curb side or in
ditches along the way and about 2.0 to 2.5m below grade;
Slope less than sanitary sewer, minimum 0.5% along
centerline gradient to achieve a self cleaning velocity of
0.8 to 0.9 m/s to avoid maintenance cost;
Drain gradient based on principle that gravity needed to
transport material suspended in the water. Therefore to
avoid flloding/pooling grades must be calculated
accurately !
Important Terms
Maintenance holes:
(MHs) are located at 100 to 400
m intervals max, or at each
change in direction, slope or pipe
size.
http://www.lgam.info/sewer-maintenance-shaft
Important terms
Catch Basins (CB):
Usually about 100 -150m apart,
closer in areas with steeper
gradients (WHY?) along the
drain
Batter Board (BB):
Horizontal board (usually
wood), attached to a vertical
stake, used in construction
layout to establish a proposed
elevation.
(contd)
STEP 3:
Calculate Grade Rod length and Stake to BB heights:
Selecting a proper Grade Rod length =
Mean CUT Offset Stake height + Height of Inspector
Use 1.7m, if height of inspector is unknown.
For example: 2.3 0.3 + 1.7 = 3.7m
Grade Rod length is made to the nearest 0.1m. In this case
use 3.7 or 4m
MH 3 0+00
0+20
0+40
0+60
0+80
MH 4 1+00
Invert
elevation
Stake
elevation
(given)
Cut
420.86
(+ 0.24)
421.10
422.96
2.10
Stake to
Batter
Board
Rod = 4m
1.90
423.37
2.27
1.73
421.34
423.67
2.33
1.67
421.58
423.82
2.24
1.76
421.82
424.17
2.35
1.65
422.06
424.45
2.39
1.61
Highway
construction
General comments
Highways like municipal roads are classified local,
collectors, arterials and freeways think of Hwy #7
going east, #27 North the old roads to Ottawa and
Barrie
Most highways are arterials joining towns and cities
Unlike municipal roads, highways do not have curbs,
storm sewers, instead ditches on sides.
General comments
Before construction begin establish C/L of construction from
limits of R-O-W of highway;
Stationing is also reestablished based on the original
preliminary survey, usually every 10 m or 20m or 25m apart;
Additional stations are required at changes in horizontal
alignment (BC, EC), vertical direction (BVC, EVC)
Full stations at are 100 m intervals (0+00, 3+00, 6+000, etc)
CUT SECTION
Finished Grade
Slope stake
FILL SECTION
R-O-W
Slope stake
C/L
Profile/Grade elevation
C/L ditch
3:1
Original Ground
2:1
7.45m
@ 3% (d1)
Slope stake
1.5m (d2)
Min 0.5m
(d3)
Granular A = 0.15m
Granular B = 0.30m
total 0.45m