Professional Documents
Culture Documents
COURSE OUTCOMES :
3.1 Understand Bar Chart and
Gantt Chart
3.1.1 Discuss the usage of the
bar chart and Gantt chart.
3.1.2 Identify the
characteristics of bar
chart and Gantt chart.
RELATIONSHIP:
1.START T0 START RELATIONSHIP
Digging
trench for
cable 5 km
Lag 1 day
Laying of
cable 5km
Lag 1 day
Filling of trench
5 km
Lag 2 days
Testing
a finish-to-start
relationship.
However, there may be instances when the
succeeding activity
cannot be started immediately when the
preceding activity is
completed.
For instance, the activities in casting a roof
may be erecting
formwork, pouring concrete, removing
formwork and so on.
Removin
Lag 2 weeks
Erecting
Pouring
While the three activities mentioned follow one g
formwork
concrete
formwork
another
sequentially, formwork cannot be removed for
at least two
weeks after the concrete has been poured.
PREPARED BY - ROSIDA BINTI
AHMAD - PSA
the finish of
another activity.
For example, the testing of a prototype of a new
car model cannot
be completed till the prototype is fully ready.
However this does not mean that testing cannot
be commence till
Lag 2 weeks
Assembling
the prototype model is ready.
prototype
Testing
DEVELOP A
PLAN TO GET
A NEW
PRODUCT TO
MARKET
USE THE DATA
PROVIDED IN
THIS CHART
TO CREAT A
GANTT CHART
ACTIVITY
DESCRIPTION
DURATION
PREDECESSORS
Decide to
Investigate New
Product
6 months
Market Analysis
2 months
Design Production
System
3 months
Assemble
Production System
3 months
Produce Initial
Samples
1.5 months
Product Testing
3 months
Develop Sales
Brochure
2 months
2,3
Detailed Cost
Analysis
1 month
10
2 months
3,8
11
Develop Final
Pricing
1 month
10,9
12
Corporate Project
Report
1 month
3,9,7
13
Initial Sales
Contacts
2 months
11,6,7
14
Orders
0 days
13
0 days
12
3. Understand Task
Relationships:
13
Task 1
Task 2
Task 4
Task 3
4.Effectively Allocate
Resources:
By being able to look ahead on the
Gantt chart, users can clearly
discern where resources need to be
anticipated, allocated or shared to
maximize the use of those
resources.
The more closely the chart is
followed, the better chance there is
of keeping project costs within
PREPARED BY : ROSIDA BINTI
budget while also
better assuring
AHMAD (PSA)
15
16
COURSE OUTCOME :
3.2.4 Construct
network diagram and
determine project
duration and identify
critical path using
Arrow Method.
PREPARED BY : ROSIDA BINTI
AHMAD (PSA)
26
CPM (NETWORK
ANALYSIS)
ACTIVITY ON ARROW
sta
rt
activity
finish
node
duration
arrow
dummy
TYPE OF NODES
EST
LST
EST
LST
EFT
LFT
EFT
LFT
or
or
EST LST
EST LST
2
EFT LFT
EFT LFT
RULES :
a)Activity arrows should be drawn
from left to right.
b)Crossing of an activity arrows
should be avoided.
c)Avoid use of unnecessary
dummies.
d)Activities are set in the order of
their execution.
e)Head event number should be
greater than tail event number.
f)There should be no loops. All
activities must be connected to
the finish event of the project.
PREPARED BY - ROSIDA BINTI
AHMAD - PSA
EXAMPLE
Early
Late
Tota
Activi Descripti Duratio
l
ty no
on
n
floa
Finis
Finis
t
Start h Start h
1-2
A
3
1-3
B
2
1-4
C
5
2-5
D
DUMMY
2-7
E
6
3-5
F
4
4-5
G
3
4-6
H
1
5-7
I
4
6-7
J
2
EXERCISE
Early
Durati
Activit
Description
on
y no
(week) Star Fini
t
sh
1-2 Drill well
4
1-4 Excavate
5
4-6 Foundation
4
Late
Tota
l
floa
Star Fini
t
t
sh
COURSE OUTCOME :
3.3 Discuss the advantages and
disadvantages of Gantt Chart and CPM
3.3.1 Identify the advantages and
disadvantages of Gantt Chart
3.3.2 Identify the advantages and
disadvantages of CPM
ADVANTAGES of CPM
Relationships between
all the
activities can be seen
clearly
Able to identify critical
activities
Progress of the overall
project can
be discovered and
monitored
PREPARED BY - ROSIDA BINTI
AHMAD - PSA
easily
DISADVANTAGES OF CPM
need the knowledge,
skills and
experience to prepare
take a long time to
complete
only suitable for large
and complex
projects
PREPARED BY - ROSIDA BINTI
AHMAD - PSA
COURSE OUTCOME
3.4 Understand the concept of
controlling
3.4.1 Define project control
3.4.2 Identify project control
system
a. Quality Management
System and its
perspectives
b. Quality Management
Process and
its concepts
ACTION
Correct
deviations
from plan
PLAN
Specifications
Project Schedule
Project budget
Resource plan
Vendor contracts
RE-PLAN as
necessary
COMPARE
Actual status
against plan
-Schedule
MONITOR
Record status
Report progress
Report cost
-Cost
PREPARED BY : ROSIDA BINTI AHMAD (JKA-PSA)
40
QUALITY MANAGEMENT
Quality management is an
internationally certifiable
process. International
standard (ISO 9000 to
9004) guide to establish,
administer, maintain and
improve our organizations
competitiveness through
our ability to provide a
quality product or service.
QUALITY SYSTEM
A quality system is the way an
organization formally controls the process
or activities that directly influence the
quality of the goods and services it
produces.
To manage and ensure quality
Help to increase quality, lower operating
costs, reduce inventory, improve system
design, improve the way it gathers and
uses information and increase its flexibility.
QUALITY MANAGEMENT
SYSTEM
1. PRODUCT QUALITY - The group of features
and characteristics of a saleable good which
determine its desirability and which can be
controlled by a manufacturer to meet certain
basic requirements.
2. SERVICE QUALITY - An assessment of how well
a delivered
service conforms to the client's expectations.
3. PROCESS QUALITY - Quality Process uses a
phased approach,
designed to support the entire product life
cycle from inception,
design and development, through rollout, to
updates and
1. QUALITY PLANNING
46
QA PRINCIPLES ;
1. FIT FOR PURPOSE the
product should be suitable
for
the intended purpose
2. RIGHT FIRST TIME mistake
should be eliminated
47
48
QA :
Provides a documented process by
which
quality commitment are met
Establishes a benchmark
A systematic and reproducible
Provides a mead of continuous
improvement
49
3. QUALITY CONTROL
To get an effective QC
program:
1.Decide which specific standards
the product or service must meet.
2.Then determined (for example,
the percentage of units to be
tested from each lot).
3.Next, real-world data must be
collected (for example, the
percentage of units that fail) and
the results reported to
management personnel.
PROJECT MONITORING
What do we mean by project
monitoring?
collecting, recording, and reporting
information
concerning project performance that
project
manager and others wish to know.
- it means to keep a careful check of
project
activities over a period of time.
PREPARED BY : ROSIDA BINTI AHMAD
(JKA-PSA)
54
55
What do we monitor?
Men (human
resources)
Machines
Materials
Money
Space
Time
Tasks
Quality/Technic
al Performance
56
When do we monitor?
57
Where do we monitor?
At head office?
At the site office?
On the spot?
Depends on situation
and the whats
58
How do we monitor
Through meetings with clients, parties
involved in project (Contractor, supplier,etc.)
For schedule Update CPA, PERT Charts,
Update Gantt Charts
Using Earned Value Analysis
Milestones
Reports
Tests and inspections
Delivery or staggered delivery
PMIS (Project Management Info Sys) Updating
59