Professional Documents
Culture Documents
Pre-Commissioning
After mechanical erection of plant/ project, precommissioning activity typically starts up to nine
months before the project execution phase.
It involves the assigning of responsibilities
between various parties, such as the engineers,
construction contractor, equipment vendors and
the organization commissioning the project.
Preparation of Punch lists is carried out as per
design requirements.
Pre-Commissioning Activities
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Cleaning of lines
Hydrostatic testing
Flushing of lines
Air blowing / drying
N2 purging
Acid cleaning of compressor lines
Breakingin pumps
Breakingin Compressors
Dryout and Boilout
Catalyst loading
Tightness test
Air purging and Gas blanketing of NonCatalytic sections
Catalytic Units Reactor Section Air purging and Gas
blanketing
14. Inhibitor / Chemical Injections
Cleaning of Lines
Internal Surface Finish Class
Class 1
a) Removal of all loose material and adherent material which could
become detached during operation of the plant.
Class 2
b) Removal of all loose material and adherent material which could
become detached during operation of the plant.
c) Removal of all oil, grease and protective coatings
Class 3
d) Removal of all loose material and adherent material that could be
detached during operation of the plant.
e) Removal of all oil, grease, and protective coatings.
f) Removal of adherent mill scale, rust and welding slag to achieve
bare metal.
g) Protection of cleaned surfaces to prevent rusting after cleaning
Hydrostatic Testing
Hydrostatic pressure testing of the Unit
shall be performed to prove strength of
the materials and weld integrity after
completion of the construction.
The tests shall be made on new or
repaired equipment and pipings.
Equipments / Pipelines are normally
pressure tested on the designed operating
pressure parameters.
This test is preferred over pneumatic test
due to safety reasons.
Hydrostatic test method is applied on the
newly manufactured pressure equipments,
after alterations, repairs and before
commissioning stage.
Flushing of Lines
As a pre-commissioning activity, flushing can be defined as the act of
pumping water, in sufficient quantity and velocity, through a given
section of pipe or piping, completely filling that section of pipe or
piping, such that the flow of water through the system will forcibly
remove any loose rust, mill scale or construction debris from the
system.
The flushing duration for an "open ended" system is such that for a
period of > 5 minutes "clear water" (no debris or other foreign
materials) must be discharged.
Guidelines
Detailed flushing plans shall be prepared for each system to be
flushed
Flushing shall be carried-out under the supervision of the
commissioning team
Flushing shall be performed through fully open flanges and/or open
pipe ends.
Flushing through smaller openings, such as drains or vents, is not
Air/ N2 Blowing
Air blowing is carried out after steam / water flushing to dry the
pipeline/ vessel.
Process lines if service for air, gas and steam shall be blown with air or
steam.
During this operation, all instruments shall be isolated, all orifice plates,
flow meter elements, control valves and safety valves shall be
removed.
All natural gas handling piping, vessels and equipments shall be dried
to a water dew point of -22 F (-30 C) and inerted with nitrogen.
What is Breaking-In?
Break-in or breaking in, also known as run-in or running
in, is the procedure of conditioning a new piece of equipment
by giving it an initial period of running, usually under light
load, but sometimes under heavy load or normal load.
It is generally a process of moving parts wearing against each
other to produce the last small bit of size and shape
adjustment that will settle them into a stable relationship for
the rest of their working life.
Breaking-In Pumps
New pumps should be given a preliminary run, with strainers
in their suction lines, in order to test mechanical performance
and reveal any defects before attempting to start up the Unit.
Breaking-In Compressor
Compressors and drivers of all types must be properly
installed and operated for "run-in" similarly to pumps to
assure their satisfactory service.
Catalyst Loading
Initial catalyst loading activities shall be performed according to the
Licensers and/or catalyst manufacturers procedures under
supervision of the Licensers representatives.
Tightness Test
During equipment cleaning, lines have been disconnected, orifice
plates and blinds removed and re-installed. As a consequence,
tightness tests shall be required to eliminate leakages due to gaskets
which have been damaged, flanges or drains which have been left
open.
Thightness test pressure will depend on the operating pressure of
the system under test. Normally shall be 1.2 times the normal
operating pressure provided that this does not exceed the set of the
PSV existing in the section.
Commissioning
Commissioning Procedure
Commissioning during the construction phase is intended to
achieve the following specific objectives according to the Contract
Documents:
a. Verify that applicable equipment and systems are installed
according to the manufacturers recommendations and to
industry accepted minimum standards and that they receive
adequate operational checkout by installing contractors.
b. Verify and document proper performance of equipment and
systems.
c. Verify that O&M documentation left on site is complete.
d. Verify that the Owners operating personnel are adequately
trained.
Adobe Acrobat
Document
Startup of Equipment /
Machineries
Objectives
Pre-Startup Checks
Before starting any item of equipment, prestart checks must be carried out to:
valves are lined up to ensure equipment does not run dry, or is not damaged on
startup due to high temperatures or pressures.
alarm systems
interlock systems
thermal insulation.
valves are lined up correctly, into and out of the equipment item
utility systems such as instrument air, steam, fuel, gas and water are in operational
condition
Equipment Start-up
all flow rates, fluid levels, pressures and temperatures are carefully monitored
equipment is brought up to operating parameters in the minimum allowable time
for safe operation
Types of Shutdowns
Level 1 Unit Shutdown (USD)
Unit Shutdown (USD) is the shutdown of individual process or utility system or
subsystem and intended to prevent equipment from operating outside process limits
that may cause damage to the equipment or adversely afect the process.
Level 2 Process Shutdown (PSD)
Process Shutdown (PSD) is shutdown of all process system. PSD is activated
automatically by various process sensors. PSD will shutdown and isolate all related
process equipment or systems, to limit the probability of an abnormal operating
condition leading to an emergency situation.
Level 3 Emergency Shutdown (ESD)
Emergency Shutdown (ESD) is shutdown to minimize the consequences during
emergency. ESD can be automatically initiated by load shedding functions or
manually by the operator through push button on the panel. ESD will shutdown and
isolate all designated process related equipment, including inlet and outlet ESD
valves.
Level 4 Emergency Depressurize Shutdown (EDP)
Emergency Depressurize Shutdown (EDP) will shutdown, isolate and depressurize all
equipments by opening the de-pressuring valves to flare. In this condition, main
power generation system will be shutdown and the emergency power generator will
start. EDP is manually activated by the operator through push button.
Monitoring of Equipment
Operation
Monitoring checks
Equipment isolation
Changeover of equipment
Equipment items such as heat exchangers, pumps and
filters are often installed in parallel where one equipment
item is on duty while the other is on standby.