Professional Documents
Culture Documents
Legal Basis
Example Contd
Example Contd
i.e. the scope of the companys validation programme did not extend to
the validation of cleaning procedures
10
11
Other Selected References to Risk & Risk Assessment, together with other examples
of where Risk Assessment can be used to determine the scope and extent of
validation, are presented for.
Chapter 5 Production
Annex 1 - Manufacture of Steriles
Annex 2 - Biologicals for Human Use
Annex 4 - Veterinary Products other then IVMPs
Annex 8 Sampling of Starting & Packaging Materials
Annex 9 - Liquids, Creams & Ointments
Annex 13 Investigational Medicinal Products
Annex 15 Qualification & Validation
Annex 17 Parametric Release
Proposed Annex 18 GMPs for APIs (ICH Q7A)
12
13
What is risk?
Many Definitions:
Key Considerations:
14
A Risk Definition
15
Comment
16
Detection Contd
17
18
20
21
22
Reasons:
Probability relates not to the effects of the failure, but to the probability of
occurrence of the failure mode itself or to its cause, and this can be difficult to
determine accurately
26
Quantify vs Qualify?
Word descriptors (e.g. high, medium, low) may be more valid than numerical
descriptors, and are preferable, because we will not then be tempted to multiply
categories
27
28
29
Whats in a Name?
Many of us do Risk Assessment & Risk Management
without calling it this
30
31
General Comments
Some of these techniques are complementary
FTA aids FMEA in Failure Mode Identification one is actually
the reverse of the other
HACCP aids FMECA in determining Critical Control Points
(or Critical Process Parameters)
Most tools were developed for non-pharma industries
Most do not address Qualification & Validation requirements
So some degree of modification can be required
32
What is FMECA?
Failure Mode, Effects & Criticality Analysis
FMECA
33
What is HACCP
Hazard Analysis and Critical Control Points
In HACCP
34
Frequent
Probable
Occasional
Remote
Note: These levels are arbitrary and for illustrative purposes only
35
Severity Levels
Severity
Critical
Major
Minor
Note: These levels are arbitrary and for illustrative purposes only
36
Failure Mode
Minor
Severity
Major
Severity
Critical
Severity
Frequent
Probable
Occasional
Remote
Note: These criteria are arbitrary and for illustrative purposes only
37
Failure Mode
Minor
Severity
Major
Severity
Critical
Severity
Frequent
Unacceptable Intolerable
Intolerable
Probable
Unacceptable Unacceptable
Intolerable
Occasional
Acceptable
Unacceptable
Unacceptable
Remote
Acceptable
Acceptable
Unacceptable
38
Red Means
The Risk is Intolerable. Eliminate the Hazard or build in systems/controls to ensure the effects of th
hazard are not realised (e.g. redundant systems)
Amber Means
The Risk is Unacceptable. The Risk must be Reduced or Controlled to an acceptable level
Green Means
The Risk is Acceptable. No Reduction or New Controls are Required
39
Detection Levels
Detection
This Means.
High
Medium
Low
None
Note: These levels are arbitrary and for illustrative purposes only
40
Risk Management
Risk Control
Risk Reduction or Risk Maintenance Controls Initiated
until Risk is Acceptable or Adequately Controlled
Periodic
Review
41
Inspectors may ask to see evidence of how Risk Assessment was used
when determining what qualification & validation work was carried out
on a certain process, piece of equipment, etc
Inspectors may ask to see evidence of how Risk Assessment was used
when designing qualification & validation protocols, and in Change
Controls
Inspectors will not require any specific Risk Assessment tool to have
been used
We will look for evidence that hazards were adequately identified and
that risks were adequately assessed & managed
42
Appendix 1
Case Study
43
FMECA
HACCP but with Critical Process Parameters
ISO 14971 (Risk Management for Medical Devices)
Qualification & Validation requirements are built in
44
Appendix 2
Other GMP Risk References & Examples
47
48
Example
A change control was approved for changing the status of a dryer from
being dedicated to drying one product to drying two products
The dried products were relatively potent materials, they were exposed
to the air in the room during manual handling, and the room was
serviced with HEPA filtered re-circulated air.
49
50
Comment
51
Example
Examples of some worst case conditions & interventions for
evaluation via Risk Assessment
Operator fatigue
Room temperature and humidity set-point extremes
Performing the media fill after completion of the last batch in a campaign
Using the maximum defined time between completion of equipment
sterilisation and starting the media fill
Highest allowed number of personnel working in the area during the
media fill
Filling the largest vial size at the slowest operating speed
Clearing broken ampoules from a fill/seal filling area
52
Annex 2
Manufacture of Biologicals for Human Use, 39
In virus inactivation or removal processes, measures should be
taken to avoid the risk of recontamination of treated products by
non-treated products
Annex 5 - Manufacture of Immunological Veterinary Medicinal
Products (Paragraph 5)
For Immunological products, the risk of contamination by
personnel is particularly important.
53
Example
Annex 4
Manufacture of Vet Medicinal Products, 4
Because of the large volume of dust generated during
processing bulk material for premixes, specific attention
should be given to the need to avoid cross contamination.
e.g. via sealed transport systems and dust extraction.. buffer
zone to minimise risk of contamination of other
manufacturing areas
55
56
Annex 8
Sampling of Starting & Packaging Materials
Comment
57
Example
One company was observed to be doing very limited identity and other
testing on a critical incoming material. (Identity and Particle size were
critical attributes.)
58
Example Contd
The drum labels contained critical identity & particle size info.
59
Risk of microbial proliferation discussed. Other risks are implied, such as risk
associated with the use of glass apparatus.
Comment
Risk assessment can help determine the extent of validation required for mixing
and filling processes.
Example
The application of a Risk Assessment and Risk Management tool to the mixing
& filling of a suspension for paediatric use is discussed elsewhere in this
presentation
60
Annex 13
Manufacture of Investigational Medicinal Products
Comment
This does not imply that no process validation is required! A Risk
assessment approach can help determine the extent of process
validation required.
61
62
Example
63
64
Appendix 3 - Bibliography
See
next page
65