PTW Issuing 07h30 (after morning meeting and supv tool box talk)
All Permits are signed. Corrective permits are written on the spot.
Isolation completed then and there
Work onsite commences after 08h00
Techs / Supv visit warehouse to get materials
The majority of permits are signed without site visits, gas tests or energy isolations
being in place
Many permits are signed but work does not start immediately no clear picture of
who is on site doing what for OPS
A large proportion of work executed is unscheduled i.e. this of work at ISG is risk
assessed that morning!
Not enough notice is given to ops or PTW co-ordinator of proposed work. More
time to review work means more time to reduce the risks and consider interactions.
Planning Process
Identify
Operator inspections
System generated
maintenance
inspections
System generated
PMs service
System generated
CM - predictive
methodologies
Component life
monitoring
Engaged workforce
Validate
Eliminates
duplication
Ensures quality work
orders with all required
fields populated
Ensures accurate
prioritisation
Validation of the
workforce
engagement
Plan
Ensures accurate
parts are ordered &
staged prior to work
execution
Ensures estimate
time to perform the
work are realistic
Ensures
documentation
required to perform
the work are available
Ensures special tools
or equipment are
available to perform
the work
Schedule
Coordination with
Ops / production for
scheduled equipment
downtime
Coordination of
multiple work order
execution
Coordination of labor
resources
Coordination of
special tools or
equipment
Execute
Accountability Oversight to ensure
quality repairs
(scheduled and
emergency work)
Validation of the
workforce efficiency
and effectiveness
Provide feedback to
person planning and
scheduling the work
Close
Accountability Recording findings of
work done
Recording actual
timing of tasks
Accountability
Returning unused
parts to the warehouse
WO Prioritisation Meeting
Prioritisation Criteria
Priority
5
4
3
Target Start
Target Completion
Conditions
Immediate
48 hours
7 days
30 days
2 days
7 days
1 month
3 months
3 months
12 months
ENCRS
6.1
OPEN
WO
PRETTRAV
3.3
Planning
available?
SCHEDULED
WORK ORDERS
PRETTRAV
+
SCHEDULE
DATE
PUBLISH
FROZEN
SCHEDULE
WMEX1
Work Order
Planner /
Scheduler
4.1
WEEKLY SCHEDULING
MEETING
AGREEMENT BASED ON
RESOURCES AVAILABILITY AND
ON-GOING ACTIVITIES
OF THE WORK TO BE SCHEDULED
FOR THE NEXT x WEEKS
Weekly scheduling
Pre meeting
schedulable work
orders list
Forms
Maintenance
Type / Start
Point
Process
Decision
Parallel Flow
Connector
Prepared by:Maximo Engineer
Reviewed by:Maintenance Spt / Systems TL
Approved by:Field Manager
Maintenance
Business Process
Mapping
Rev. 3
Maintenance
Tech /
Contractor
5.2
START WORK
COLLECT
MATERIAL /
EXECUTION
COLLECT
WORK PERMIT
WMEX2
WORK ORDER
Warehouse
5.1
Next Day
RESERVATION
PREPARATION
INVENTORY
4.1
PRETTRAV
+
SCHEDULE
DATE
Maintenance
Spv
Planner/
Scheduler
ENCRS
PUBLISH
Next Day
WO List
PRINT
Next day
WORK
PACKS
Issue APPROVED
Next Day Pick list
to warehouse
7.3
ASSIGN WORK
TO
TECHNICIAN
REQUEST
WORK PERMIT
3.3
Forms
Maintenance
Type / Start
Point
Process
Decision
Parallel Flow
Connector
Prepared by:Maximo Engineer
Reviewed by:Maintenance Spt / Systems TL
Approved by:Field Manager
Maintenance
Business Process
Mapping
Rev. 3
HSE
Ops update on plant status
Work Review (supervisors)
Update on progress of todays schedule
Define which work will continue next day and re-validate the
permit
ENCRS
WC.1
7.1
7.2
FINAL ACTUAL
HOURS
REPORTING
FAILURE
REPORTING
QUICK REPORTING
QUICK REPORTING
7.3
Review work
orders reporting
for completion
and exactitude
Rework
required?
WORK ORDER
Reporitng
Ok?
TERMI
Investigation
Required?
Maintenance
Engineer
Maintenance
Spv
Maintenance
Technician / Contractor
CALL FOR
INVESTIGATION
REQUEST
CLOSE WO
WMEX1
Forms
Maintenance
Type / Start
Point
Process
Decision
Parallel Flow
Connector
Prepared by:Maximo Engineer
Reviewed by:Maintenance Spt / Systems TL
Approved by:Field Manager
Maintenance
Business Process
Mapping
Rev. 3
Back Up
Permit Issuing
Weekly Meeting
Planning team create schedule for all CO and PM for the next
week based on available resources.
Schedule is discussed by HSE, exploitation and maintenance
week prior to work.
Any problems are highlighted (TRA requirements or issues with
scheduling for example) and in place prior to presenting the permit
for approval.
Schedule is agreed and finalised no surprises for anyone.