You are on page 1of 73

PT.

PERUSAHAAN LISTRIK NEGARA (Persero)


PENYALURAN DAN PUSAT PENGATUR BEBAN JAWA BALI

Afrizal N

PERENCANAAN WAKTU PROYEK

Afrizal N

The Project Management


Knowledge Areas

4. Project Integration
Management

5. Project Scope
Management

6. Project Time
Management

7. Project Cost
Management

8. Project Quality
9. Project Human
Resource Management
Management

10. Project Communications Management

11. Project Risk 12. Project ProcureManagement


ment Management
Afrizal N

PMBOK PMI ed 2004


Section 3:
Chapter 6 :

Project Time Management

6.1 Activity Definition


6.2
6.3
6.4
6.5
6.6

PMBOK p.
127-130
Activity Sequencing PMBOK p. 130135
PMBOK p. 135Activity Resource Estimating
138
Activity Duration Estimating
PMBOK p. 139143
Schedule Development
PMBOK p.
143-152
Schedule Control
PMBOK p.
152-156

Afrizal N

PMBOK p.
123

PROJECT TIME MANAGEMENT


6.1 Activity Definition
1 Inputs
.1. Enterprise environmental factors
.2. Organizational process assets
3. Project scope statement
4. WBS
.5. WBS dictionary
.6. Project Management plan
2 Tools and Technniques
.1. Decomposition
.2. Templates
.3. Rolling wave planning
.4. Expert judgment
.5. Planning component
3 Outputs
.1. Activity list
.2. Activity atributes
.3. Milestone list
.4. Requested changes

6.4 Activity Duration


Estimating
1 Inputs
.1. Enterprise environmental factors
.2. Organizational process assets
.3. Project scope statement
.4. Activity list
.5. Activity atributes
.6. Activity resource requirements
.7. Resource calendars
.8. Project management plan
. Risk register
. Activity cost estimates
2 Tools and Technniques
.1. Expert judgment
.2. Analogous estimating
.3. Parametric estimating
.4. Three-point estimates
.5. Reserve analysis
3 Outputs
.1. Activity duration estimates
.2. Activity atributes (updates)

(PMBOK Guide p. 125)

6.2 Activity Sequencing


1 Inputs
.1. Project scope statement
.2. Activity list
.3. Activity atributes
.4. Milestone list
.5. Approved change request
2 Tools and Technniques
1. Precedence diagramming method (PDM)
2. Arrow diagramming method (ADM)
3. Schedule network tamplates
4. Dependaency determination
5. Applying leads and lags
3 Outputs
1. Project schedule network diagrams
2. Activity list (updates)
3. Activity atributes (updates)
4. Requested changes

6.5 Schedule Development


1 Inputs
.1. Organizational process assets
2. Project scope statement
.3. Activity list
.4. Activity atributes
.5. Project schedule network diagrams
.6. Activity resource requirements
7. Resource calendars
.8. Activity duration estimates
.9. Project management plan
. Risk register
2 Tools and Technniques
3 Outputs
.1. Schedule network analysis
.1. Project schedule
.2. Critical path methode
.2. Schedule model data
.3. Schedule compression
.3. Schedule baseline
.4. What if-scenario analysis
.4. Resource requirement (updates)
.5. Resource leveling
.5. Activity atributes (updates)
.6. Critical chain method
.6. Project calendars (updates)
.7. Project management sofware .7. Requested changes
.8. Applying calendars
.8. Project management plan (updates)
.9. Adjusting leads and lags
. Schedule management plan (updates)
10. Schedule model

Afrizal N

Overview
6.3 Activity Resource
Estimating
1 Inputs
.1. Enterprise environmental factors
.2. Organizational process assets
.3. Activity list
.4. Activity atributes
.5. Resource availability
.6. Project management plan
2 Tools and Technniques
.1. Expert judgment
.2. Alternative analysis
.3. Published estimating data
.4. Project management sofware
.5. Bottom-up estimating
3 Outputs
.1. Activity resource requirements
.2. Activity atributes (updates)
.3. Resource breakdown structure
.4. Resource calendars (updates)
.5. Requested changes

6.6 Schedule Control


1 Inputs
.1. Schedule management plan
.2. Schedule baseline
.3. Performance reports
.4. Approved changes request
2 Tools and Technniques
.1. Progress reporting
.2. Schedule change control system
.3. Performance measurement
.4. Project management software
.5. Variance analysis
.6. Schedule comparison bar chart
3 Outputs
.1. Schedule model data (updates)
.2. Schedule baseline (updates)
.3. Performance measurements
.4. Request changes
.5. Recommended corrective actions
.6. Organizational process assets (updates)
.7. Activity list (updates)
.8. Activity atributes (updates)
.9. Project management plan (updates)

Scope Definition
5.2

(3.2.2.3)

Create WBS

Project Time Management Process Flow Diagram

5.3

(3.2.2.4)

Enterprise
Environmental
Factors
Organizational
Process Assets
Select Seller
5.2

Project Scope Statement


WBS
WBS
Dictionary

7.1

Organizational Policies
Historical Information
Project Calendar
Resource Availability

Resource Availability

Performance
Reporting
10.3

Activity
Sequencing
6.2 (3.2.2.6)

(3.2.3.1)

Close Project
4.7

(3.2.5.1)

Develop Project
Management Plan
4.3
(3.2.2.1)

Approved Changes Requests


Approved Corrective Actions

Requested Changes
Project Management Plan (updates)

Project Schedule Network Diagram

Activity
Resource
Estimating
6.3 (3.2.2.7)

Requested Changes
Activity Resource Requirements
RBS
Resource Calendar (updates)

Activity Duration
Estimating
6.4 (3.2.2.8)

Requested Changes

Risk Register
Activity Duration Estimates
Schedule
Development
6.5 (3.2.2.9)
Performance Reports

(3.2.4.9)

Direct & Manage


Project Execution
4.4

Activity Cost Estimates

(3.2.2.10)

Risk Management
Planning 11.211.5 (3.2.2.15)

Scope Management Plan

Activity List, Activity, Attributes.


Milestone List

(3.2.3.3)

Cost Estimating

Project Management Plan

Resource Availability

(3.2.2.3)

Acquire Project
Team 9..2

Activity
Definition
6.1 (3.2.2.5)

Work Performance Information

Schedule
Control
Afrizal
6.6 N
(3.2.4.5)
Organizational Process Assets (updates)

Project Management Plan (updates)


Requested Changes
Performance Measurements
Activity List (updates)
Activity Atributes (updates)
Project Management Plan (updates)
Schedule Baseline (updates)
Schedule Model data (updates)
Project Schedule
Requested Changes,
Recommended Corrective Actions

Project Schedule,
Sch.Model Data,
Sch.Baseline, Resource
Requirement (updates),
Project Calendar
(updates)

Integrated Change
Control
4.6

(3.2.4.2)

6. 1. ACTIVITY DEFINITION
INPUTS
Melibatkan pengidentifikasian dan dokumentasi pekerjaan yang telah
direncanakan untuk dilaksanakan. Prosesnya meng identifikasi
deliverables pada level paling bawah dalam WBS, juga disebut work
package.
Work package direncanakan kedalam komponen yang lebih kecil yang
disebut Jadwal kegiatan sebagai dasar estimating, scheduling, executing,
monitoring & controling pekerjaan proyek. Terkandung di dalam proses
ini adalah pentingnya menggambarkan suatu kegiatan seperti yang
dimaksud
bahwa
sasaran hasil proyek akan tercapai.Inputs
.1.
Enterprise
environmental
Inputs: :
.1.
factors
.1.Enterprise
Enterpriseenvironmental
environmental
factors
(6.1.1.1 p.127)
factors
.2.
Organizational
Pada (4.1.1.3) dapat disesuaikan
.2. Organizationalprocess
processassets
assets
3.
Project
scope
statement
termaksuk tersedianya project
3. Project scope statement
4.
management system dan scheduling
4.WBS
WBS
.5.
sofware tools
.5.WBS
WBSdictionary
dictionary
.2. Organizational process assets
.6.
Project
.6. ProjectManagement
Managementplan
plan
(6.1.1.2 p.127)
(4.1.1.4) berisi kebijakan, baik formal
maupun non formal, prosedur, panduan
untuk mengembangkan Activity
definitions.
Historical information dari proyek
sebelumnya dapat menetapkan
Afrizal N
7
schedule activities.

6. 1. ACTIVITY DEFINITION
INPUTS
3. Project scope statement
(6.1.1.3 p.127)
Deliverable proyek, constraint dan
assumsi yang ada pada project scope
statement (5.2.3.1) dapat disesuaikan
sepanjang
activity definitions.
4. WBS (6.1.1.4
p.128)
WBS (5.3.3.2) sebagai masukan
schedule activity definition.

Inputs
Inputs: :
.1.
.1.Enterprise
Enterpriseenvironmental
environmental
factors
factors
.2.
Organizational
.2. Organizationalprocess
processassets
assets
3.3.Project
scope
statement
Project scope statement
4.4.WBS
WBS
.5.
.5.WBS
WBSdictionary
dictionary
.6.
Project
.6. ProjectManagement
Managementplan
plan

5. WBS Dictionary (6.1.1.5 p.128)


WBS (5.3.3.3) sebagai masukan
schedule activity definition.
.6. Project Management Plan
(6.1.1.6 p.128)
Berisi Schedule management plan
(chapter 6) memandu mengembangkan
dan merencanakan Schedule activities
dan project scope management plan.

Afrizal N

Contoh

: WBS

(Basic Knowledge)

TOTAL PROGRAM

MANAGERIAL
LEVEL
PROJECT

TASK
TECHNICAL
LEVEL
WORK
PACKAGE

PROJECT

TASK

PROJECT

TASK

SUB TASK

SUB TASK

WORK
PACKAGE

WORK
PACKAGE

LEVEL OF
EFFORT

LEVEL OF
EFFORT

Afrizal N

LEVEL 1

PROJECT

LEVEL 2

LEVEL 3

SUB TASK

LEVEL 4

LEVEL 5

LEVEL OF
EFFORT

LEVEL 6

WORK PACKAGE
REPRESENTS UNITS OF WORK AT THE LEVEL WHERE THE WORK IS
PERFORMED
CLEARLY

DISTINGUISHES

ONE

WORK PACKAGE FROM ALL

OTHERS ASSIGNED TO A SINGLE FUNCTIONAL GROUP.


CONTAINS CLEARLY DEFINED START

END DATES THAT ARE

REPRESENTATIVE OF PHYSICAL ACCOMPLISHMENT


SPECIFIES A BUDGET IN TERMS OF DOLLARS, MANHOUR OR OTHER
MEASURABLE UNITS.
LIMITS THE WORK TO BE PERFORMED TO RELATIVELY

SHORT

PERIODS OF TIME TO MINIMIZE THE WORK-IN- PROCESS EFFORT.

Afrizal N

10

Contoh : WBS

Afrizal N

11

WBS - LEVEL

(Basic Knowledge)

Ifluenced by :
Level of Detail
Level of Risk
Level of Control
Estimate accuracy
Work package value
Work pcckage man-hour

Afrizal N

12

6. 1. ACTIVITY DEFINITION
TECHNIQUES
.1. Decomposition (6.1.2.1 p.128)
.2. Templates (6.1.2.2 p.128)
.3. Rolling Wave Planning (6.1.2.3
p.128)
.4. Expert Judgment (6.1.2.4
p.129)
.5. Planning Component (6.1.2.5
p.129)

Afrizal N

TOOLS &
Tools
Tools&&Techniques
Techniques
.1.
.1.Decomposition
Decomposition
.2.
.2.Templates
Templates
.3.
Rolling
.3. Rollingwave
waveplanning
planning
.4.
Expert
judgment
.4. Expert judgment
.5.
.5.Planning
Planningcomponent
component

13

WBS - Decomposition (Basic Knowledge)


Identify the major elements of the project
Subdividing the total effort into discrete and logical subelements
Decide if adequate cost and duration estimates can be
developed at the level of detail for each element.
Work package is a deliverable at the lowest level of the work
breakdown structure. A typical work package may be 200-300
hours or

approximately

two weeks

duration.

Check the proposed WBS satisfied both functional and project


requirement.

Afrizal N

14

WBS Numbering System


(Basic Knowledge)
Linked to project account, corporate account, client account.
Linked to the person responsible carrying out the work.
Use to roll-up project for utilization of hierarchical report in planning and
control purposes.
Can be alphabetical, numeric or alphanumeric (letters and numbers)

Afrizal N

15

Calendars
(Basic Knowledge)

Describe when time is available for work to be performed

Define time units, length of work week, non working period :


Day's of the week
Hours of the day
Holidays or non-working period

All activities must be assigned a calendar

A typical project requires several calendars to represent different work


patterns (time unit must be same)

Afrizal N

16

6. 1. ACTIVITY DEFINITION
OUTPUTS
.1. Activity List (6.1.3.1 p.129)
.2. Activity Attributes (6.1.3.2
p.130)
.3. Milestone List (6.1.3.3 p.130)

Outputs
Outputs
.1.
Activity
.1. Activitylist
list
.2.
Activity
attributes
.2. Activity attributes
.3.
.3.Milestone
Milestonelist
list
.4.
Requested
changes
.4. Requested changes

.4. Requested Changes (6.1.3.4


p.130)

Afrizal N

17

Activity List (Basic Knowledge)


BAR CHART

Afrizal N

18

6. 2. ACTIVITY SEQUENCING
INPUTS
Melibatkan pengidentifikasian dan dokumentasi hubungan antaraktivitas secara logic. Aktivitas harus dihubungkan dengan teliti
untuk mendukung pengembangan berikutnya/ yang akan datang
dari suatu jadwal yang realistis. Peruntutan dapat dilakukan
dengan bantuan dari suatu komputer.
.1. Project scope statement
(6.2.1.1 p.131)
.2. Activity list (6.2.1.2 p.131)

Inputs
Inputs: :
.1.
.1.Project
Projectscope
scopestatement
statement
.2.
Activity
list
.2. Activity list
.3.
.3.Activity
Activityattributes
attributes
.4.
Milestone
.4. Milestonelist
list
.5.
Approved
change
.5. Approved changerequest
request

.3. Activity atributes (6.2.1.3


p.131)
.4. Milestone list (6.2.1.4 p.131)
.5. Approved change request
(6.2.1.5 p.131)

Afrizal N

19

6. 2. ACTIVITY SEQUENCING
INPUTS
1. Precedence diagramming
method (PDM)
(6.2.2.1 p. 132)
2. Arrow diagramming method
(ADM)
(6.2.2.2 p. 133)
3. Schedule network templates
(6.2.2.3 p. 133)

Tools
Tools&&Techniques
Techniques
1.1.Precedence
diagramming
Precedence diagrammingmethod
method(PDM)
(PDM)
2.2.Arrow
diagramming
method
(ADM)
Arrow diagramming method (ADM)
3.3.Schedule
Schedulenetwork
networktemplates
templates
4.4.Dependency
determination
Dependency determination
5.5.Applying
Applyingleads
leadsand
andlags
lags

4. Dependency determination
(6.2.2.4 p. 133)
Mandatory dependencies
Discretionary dependencies
External dependencies
5. Applying leads and lags (6.2.2.5
p. 134)

Afrizal N

20

Method Activity Sequencing


Precedence diagramming method (PDM)
ES
ES

EF

EF

Activity Name

Activity Name

ES

EF

Duration
Activity Name

Duration
LS

LF

LS

LF

ES

EF

ES

Activity Name

Activity Name

Duration

Duration

LS

LF

LS

Duration

EF
LS

LF

LF

AON : Activity On Node

Arrow diagramming method (ADM)


B
Start

A
Finish
F

D
E

AOA : Activity On Arrow

Afrizal N

21

Method Activity Sequencing


Conditional diagramming method
GERT : System Dynamic Model
Allow : Loops or Conditional Branches

Network Templete
Artemis Int.S.Corp

: Artemis (7) Project management.

Primavera System Inc. : Primavera Project Planner (P3, 3.1)


Microsoft

: Microsoft Project (2002)

Afrizal N

22

Activity List : Daftar aktivitas meliputi semua aktivitas yang akan dilakukan untuk menye
lesaikan proyek. Harus dapat diorganisir dan sebagai pengembangan dari
WBS
untuk
memastikan bahwa aktivitas itu lengkap, dan tidak meliputi aktivitas yang tidak
diperlukan
dari lingkup proyek. Dengan WBS, daftar aktivitas meliputi uraian dari tiap
aktivitas untuk memastikan bahwa anggota tim proyek akan memahami bagaimana pekerjaan
lakukan.
Product Description : Dokumen uraian produk yang menunjukkan karakteristik produk atau
jasa layanan. Mempunyai sedikit detil pada tahap awal dan lebih datail di kemudian
dengan karakteristik produk yang semakin ditekuni. Karakteristik produk sering
mempengaruhi urutan. Dan uraian produk biasanya ditinjau ulang untuk memastikan
ketelitian.
Mandatory Dependencies : Ketergantungan Wajib yang tidak bisa dipisahkan dari wujud
pekerjaan yang telah dilakukan. Ketergantungan wajib adalah juga dinamakan
Hard Logic.
Descretionary Dependencies : Ketergantungan tidak wajib biasanya ditentukan oleh tim
proyek. Mempunyai kepedulian ( dan secara penuh di-dokumentasikan), Pada umumnya
digambarkan berdasar pada pengetahuan: Best practise, dan yang tidak umum, dan
biasanya dinamakan Prefered logic, Preferential logic, atau shoft logic.
External Dependencies : Ketergantungan eksternal yang melibatkan suatu hubungan antar
aktivitas proyek dan bukan aktivitas proyek..
Milestone : Peristiwa yang diperlukan untuk
bagian
dari urutan aktivitas, untuk
Afrizal
N
memastikan
bahwa kebutuhan dalam memenuhi milstone(s) dijumpai.

23

Activity Relationships
Types
Finish To Start

Activity A

Activity B
Activity A

Activity A

Start To Start

Start To Start

With Lag

Activity B

SS + 5

Activity B

Activity A

Activity A

Finish To Finish

Finish To Finish

Activity B

FF + 3

With Lag

Activity B
Activity A
Start To Finish

Start To Finish

Activity B
Finish To Start
With Lag

Activity A

With Lead = - Lag


FS + 7

Activity B

Afrizal N

Activity A
FF + 0

Activity B
24

6. 2. ACTIVITY SEQUENCING
OUTPUTS
1. Project schedule network
diagrams
(6.2.3.1 p. 135)
2. Activity list (updates)
(6.2.3.2 p. 135)

Outputs
Outputs
1.1.Project
Projectschedule
schedule
network
networkdiagrams
diagrams
2.2.Activity
list
Activity list
(updates)
(updates)
3.3.Activity
Activityattributes
attributes
(updates)
(updates)
4.4.Requested
Requestedchanges
changes

3. Activity attributes (updates)


(6.2.3.3 p. 135)
4. Requested changes
(6.2.3.4 p. 135)

PMBOK Guide page 130

Afrizal N

25

6. 3. ACTIVITY RESOURCE ESTIMATING


INPUTS
Estimate resources (persons, equipment, material) , Quantity,
when will be available untuk melaksanakan kegiatan proyek.
Dikoordinasikan dengan proses Cost Estimating (7.1)
.1. Enterprise environmental
factors
(6.3.1.1 p. 136)
.2. Organizational process assets
(6.3.1.2 p. 136)

Inputs
Inputs: :
.1.
.1.Enterprise
Enterpriseenvironmental
environmentalfactors
factors
.2.
Organizational
process
assets
.2. Organizational process assets
.3.
.3.Activity
Activitylist
list
.4.
Activity
attributes
.4. Activity attributes
.5.
.5.Resource
Resourceavailability
availability
.6.
Project
management
.6. Project managementplan
plan

.3. Activity list


(6.3.1.3 p. 136)
.4. Activity attributes
(6.3.1.4 p. 136)
.5. Resource availability
(6.3.1.5 p. 137)
.6. Project management plan
(6.3.1.6 p. 137)
Afrizal N

26

6. 3. ACTIVITY RESOURCE ESTIMATING TOOLS &


TECHNIQUES

Tools
Tools&&Techniques
Techniques
.1.
.1.Expert
Expertjudgment
judgment
.2.
.2.Alternative
Alternativeanalysis
analysis
.3.
Published
estimating
.3. Published estimatingdata
data
.4.
Project
management
sofware
.4. Project management sofware
.5.
.5.Bottom-up
Bottom-upestimating
estimating

.1. Expert judgment


(6.3.2.1 p. 137)
.2. Alternative analysis
(6.3.2.2 p. 137)
.3. Published estimating data
(6.3.2.3 p. 137)
.4. Project management sofware
(6.3.2.4 p. 137)
.5. Bottom-up estimating
(6.3.2.5 p. 137)

Afrizal N

27

6. 3. ACTIVITY RESOURCE ESTIMATING


PMBOK
OUTPUTS
.1. Activity resource requirements
(6.3.3.1 p. 138)
.2. Activity atributes (updates)
(6.3.3.2 p. 138)
.3. Resource breakdown structure
(6.3.3.3 p. 138)
.4. Resource calendars (updates)
(6.3.3.4 p. 138)

Guide page 136

Outputs
Outputs
.1.
Activity
.1. Activityresource
resource
requirements
requirements
.2.
Activity
.2. Activityatributes
atributes
(updates)
(updates)
.3.
Resource
.3. Resourcebreakdown
breakdown
structure
structure
.4.
Resource
.4. Resourcecalendars
calendars
(updates)
(updates)
.5.
Requested
.5. Requestedchanges
changes

.5. Requested changes


(6.3.3.5 p. 138)

Afrizal N

28

6. 4. ACTIVITY DURATION ESTIMATING


INPUTS
Adalah proses dari mendapatkan informasi pada lingkup proyek
dan sumber daya dan kemudian pengembangan jangka waktu
/durasi sebagai masukan terhadap jadwal/ schedule. Masukan
untuk perkiraan dari jangka waktu proyek secara khas didapat
dari seseorang atau group didalam tim proyek dimana telah
familiar / ahli terhadap sifat dari kegiatan khusus
tersebut..
Inputs
Inputs: :
.1. Enterprise environmental
factors
(6.4.1.1 p. 140)
.2. Organizational process assets
(6.4.1.2 p. 140)
.3. Project scope statement
(6.4.1.3 p. 140)

.1.
.1.Enterprise
Enterpriseenvironmental
environmentalfactors
factors
.2.
Organizational
process
assets
.2. Organizational process assets
.3.
.3.Project
Projectscope
scopestatement
statement
.4.
Activity
list
.4. Activity list
.5.
.5.Activity
Activityattributes
attributes
.6.
Activity
resource
.6. Activity resourcerequirements
requirements
.7.
Resource
calendars
.7. Resource calendars
.8.
.8.Project
Projectmanagement
managementplan
plan
. . Risk
register
Risk register
. . Activity
Activitycost
costestimates
estimates

.4. Activity list


(6.4.1.4 p. 140)
.5. Activity atributes
(6.4.1.5 p. 140)
Afrizal N

29

6. 4. ACTIVITY DURATION ESTIMATING


INPUTS
Adalah proses dari mendapatkan informasi pada lingkup proyek
dan sumber daya dan kemudian pengembangan jangka waktu
/durasi sebagai masukan terhadap jadwal/ schedule. Masukan
untuk perkiraan dari jangka waktu proyek secara khas didapat
dari seseorang atau group didalam tim proyek dimana telah
Inputs
::
familiar / ahli terhadap sifat dari kegiatan khusus
tersebut..
Inputs
.6. Activity resource requirements
(6.4.1.6 p. 140)
.7. Resource calendars
(6.4.1.7 p. 141)
.8. Project management plan
. Risk register
. Activity cost estimates
(6.4.1.8 p. 141)

Afrizal N

.1.
.1.Enterprise
Enterpriseenvironmental
environmentalfactors
factors
.2.
Organizational
process
assets
.2. Organizational process assets
.3.
.3.Project
Projectscope
scopestatement
statement
.4.
Activity
list
.4. Activity list
.5.
.5.Activity
Activityattributes
attributes
.6.
Activity
resource
.6. Activity resourcerequirements
requirements
.7.
Resource
calendars
.7. Resource calendars
.8.
.8.Project
Projectmanagement
managementplan
plan
. . Risk
register
Risk register
. . Activity
Activitycost
costestimates
estimates

30

6. 4. ACTIVITY DURATION ESTIMATING TOOLS &


TECHNIQUES
.1. Expert judgment(6.4.2.1 p. 141)

.2. Analogous estimating (6.4.2.2


p. 141)

Tools
Tools&&Techniques
Techniques
.1.
Expert
judgment
.1. Expert judgment
.2.
.2.Analogous
Analogousestimating
estimating
.3.
Parametric
estimating
.3. Parametric estimating
.4.
.4.Three-point
Three-pointestimates
estimates
.5.
Reserve
analysis
.5. Reserve analysis

.3. Parametric estimating (6.4.2.3


p. 142)
.4. Three-point estimates (6.4.2.4
p. 142)
.5. Reserve analysis (6.4.2.5 p.
142)

Afrizal N

31

Activity Duration Calculation


Activity
ID

Activity
Description

Time Estimated

Expected
Time

Variance

Std.Dev

(TE)

Successor

A0

Start

Kegiatan A

A1

Kegiatan A

13

Kegiatan B, C

A2

Kegiatan B

0.1

0.3

Kegiatan D,E,F

A3

Kegiatan C

11

13

11

0.4

0.7

Kegiatan H

A4

Kegiatan D

0.1

0.3

Kegiatan G

A5

Kegiatan E

10

13

10

A6

Kegiatan F

13

1.8

1.3

Kegiatan H

A7

Kegiatan G

0.1

0.3

Kegiatan I

A8

Kegiatan H

12

Kegiatan I

A9

Kegiatan I

0.1

0.3

A10

Finish

TE =

a + 4m + b
6
((b a)/6)2

a = most optimistic time


m = most likely time / waktu hampir
bisa dipastikan
Afrizal N
b = most pessimistic time

Duration =

Kegiatan G,H

Finish

Man-hours
Amount of worker
32

Probability Completion Time


Completion Time for the probability 25 % (appendix E table)
Z = -0.68

Z = D TE / 2CP

- 0.68 = D 36 / 3.2

D (Desire Project completion time ) = - 0.68 X 1.8 + 36 = 34.7


hari = 35 hari.

Completion Time for the probability 50 % (appendix E table) Z = 0


D (Desire Project completion time ) = 36 hari

Completion Time for the probability 75% (appendix E table) Z =


0.70
D (Desire Project completion time ) = 0.70 X 1.8 + 36 = 37 hari
Afrizal N

33

PERT Duration Calculation


For a single Activity (Tree-Point
Estimates)
Higher

Most Likely
(Used in original CPM calculation)

PERT Weighted Average =


Optimistic + 4 X Most Likely + Pessimistic

Probability of
Occurrence

6
Beta Distribution

Optimistic

Pessimistic

Lower
Shorter

Possible Durations
Afrizal N

Longer
34

Duration Probability Calculation


(Example)

Activity A has pessimistic (b) estimate of 36 days, a most likely (m) estimate of 21
days, and an optimistic (a) estimate of 6 days. What is the probability that actifity A
will be completed in 16 to 26 days ?
16 days

21 days

34.13%

26 days

34.13%

13.6%
0.14 %

13.6%

2.13 %

2.13 %

-5 days

0.14 %

+5 days

68.26 %
95.46 %
99.73 %

Mean = [6 + (4 X 21) + 36 ] / 6 = 21 days


SD

= (36 6) / 6 = 5 days

The probability that activity will be completed in 16 to 26 days = 68.26%

Afrizal N

35

6. 4. ACTIVITY DURATION ESTIMATING


INPUTS
Outputs
Outputs
.1.
Activity
.1. Activityduration
duration
estimates
estimates
.2.
Activity
.2. Activityattributes
attributes
(updates)
(updates)

.1. Activity duration estimates


(6.4.3.1 p. 142)
.2. Activity attributes (updates)
(6.4.3.2 p. 143)

Afrizal N

36

6. 5. SCHEDULE DEVELOPMENT
INPUTS
Proses berulang didalam menentukan tanggal start dan finish
dari suatu aktivitas/kegiatan proyek. Jika tanggal start dan finish
tidaklah realistis, maka proyek tidak mungkin akan selesai
sesuai jadwal yang diharapkan.
Didalam Schedule development, duration estimates dan
resource estimates selalu direview dan direvisi untuk
menciptakan approved project schedule yang Inputs
berguna
untuk
Inputs: :
.1. Organizational
process assets
mengontrol progress.
.1.
.1.Organizational
Organizationalprocess
processassets
assets
(6.5.1.1 p. 143)

2.2.Project
Projectscope
scopestatement
statement
.3.
Activity
list
.3. Activity list
.4.
.4.Activity
Activityattributes
attributes
.5.
Project
schedule
.5. Project schedulenetwork
networkdiagrams
diagrams
.6.
Activity
resource
requirements
.6. Activity resource requirements
7.7.Resource
Resourcecalendars
calendars
.8.
Activity
duration
.8. Activity durationestimates
estimates
.9.
Project
management
.9. Project managementplan
plan
. . Risk
register
Risk register

2. Project scope statement


(6.5.1.2 p. 143)
.3. Activity list
(6.5.1.3 p. 144)
.4. Activity attributes
(6.5.1.3 p. 144)

Afrizal N

37

6. 5. SCHEDULE DEVELOPMENT
INPUTS
.5. Project schedule network
diagrams
(6.5.1.5 p. 144)
.6. Activity resource requirements
(6.5.1.6 p. 144)
7. Resource calendars
(6.5.1.7 p. 144)
.8. Activity duration estimates
(6.5.1.8 p. 144)

Inputs
Inputs: :
.1.
.1.Organizational
Organizationalprocess
processassets
assets
2.2.Project
scope
statement
Project scope statement
.3.
Activity
.3. Activitylist
list
.4.
Activity
attributes
.4. Activity attributes
.5.
.5.Project
Projectschedule
schedulenetwork
networkdiagrams
diagrams
.6.
Activity
resource
requirements
.6. Activity resource requirements
7.7.Resource
Resourcecalendars
calendars
.8.
Activity
duration
.8. Activity durationestimates
estimates
.9.
Project
management
.9. Project managementplan
plan
. . Risk
register
Risk register

.9. Project management plan


(6.5.1.9 p. 144)
. Risk register

Afrizal N

38

Schedule Development
Compression (With No Impact)
Start

(Basic Knowledge)

Start Mfg

Design

Detail

Design

Detail

Check

Purchase
Material

Purchase
Material
Check
Compression

Tools : Duration Compression


1.

Crashing :

Doing anything to reduce the schedule completion of the project .

The rule in implementing Crashing are :


a. Crash on Critical Path
b. Crash Critical Activities whose have cheapest cost
2.

Fast Tracking

AfrizaltoNbe done with some overlap.


Activities that schedule sequence are scheduled
Hints : a. Leads, b. Logic relationship.

39

6. 5. SCHEDULE DEVELOPMENT
TECHNIQUES
.1. Schedule network analysis
(6.5.1.5 p. 144)
.2. Critical path methods
(6.5.1.6 p. 144)
.3. Schedule compression
(6.5.1.7 p. 144)
.4. What if-scenario analysis
(6.5.1.8 p. 144)
.5. Resource leveling (6.5.1.9 p.
144)
.6. Critical chain method (6.5.1.8
p. 144)
.7. Project management sofware
(6.5.1.9 p. 144)

TOOLS &
Tools
Tools&&Techniques
Techniques
.1.
Schedule
network
.1. Schedule networkanalysis
analysis
.2.
Critical
path
methods
.2. Critical path methods
.3.
.3.Schedule
Schedulecompression
compression
.4.
What
if-scenario
.4. What if-scenarioanalysis
analysis
.5.
Resource
leveling
.5. Resource leveling
.6.
.6.Critical
Criticalchain
chainmethod
method
.7.
Project
management
.7. Project management
sofware
sofware
.8.
.8.Applying
Applyingcalendars
calendars
.9.
Adjusting
leads
.9. Adjusting leadsand
andlags
lags
10.
Schedule
model
10. Schedule model

.8. Applying calendars (6.5.1.8 p.


144)
9. Adjusting leads and lags (6.5.1.9
p. 144)
10. Schedule model (6.5.1.9 p.
144)

Afrizal N

40

PMBOK Guide page 143

CPM

(Example)

Calculation Early dates, Late dates and Total Float


Identify Critical Path.

SS + 5

Activity D

Activity E

Duration= 8

Duration=2

Activity B
Activity A

Activity G

Duration=10

Duration=5

Duration= 5
Activity F
Duration=5
Activity C

FF + 2

Duration=15

Afrizal N

41

CPM

(Example)

Calculation Early dates


Forward Pass
11
SS + 5

5
Activity A

19

20

Activity D

Activity E

Duration= 8

Duration=2
23

6
1

18

15

27

Activity G

Activity B
Duration=5
Duration=10

21

Duration= 5

25
Activity F

20

Activity C

Duration=5

FF + 2

Duration=15

ES
EF

= Early Start
= Early Finish

= EF pred terbesar + 1
= ES + OD 1
Afrizal N

42

CPM

(Example)

Calculation Early dates, Late dates


Backward Pass
11
SS + 5

18

Activity E

Duration= 8

Duration=2

21

22

15

27

Activity G

Activity B

Duration=5
Duration=10

Duration= 5

20

23

Activity A

20

Activity D

13

19

21

20

20

Activity C

25

23

27

Activity F
Duration=5
21

25

FF + 2

Duration=15
6

LF
LS

= Late Finish
= Late Start

20

= ES suc 1
= LF OD + 1
Afrizal N

43

CPM

(Example)

Calculation Early dates, Late dates, Total Float


Foreword Pass
Backward Pass
11
SS + 5

18

Activity E

Duration= 8

Duration=2

TF

TF

1
0

22

23

27

Activity G
Duration=5

8
2

21

20
5

5
0

= Total Float

21

15

Duration=10

Duration= 5

20
2

Activity B

5
Activity A

20

Activity D

13
6

19

25
Activity F

20

Duration=5

Activity C

21

25

Duration=15

20

23
0

27
0

FF + 2

Critical Path

= ES suc EF pred 1 = Zero = Critical


= LS ES; LF EF
FF
= Free Float
= LF OD ES ; FF is defined as the amount of time
an activity can be delayed without delaying the early start of any
44
immediately following activities Afrizal N
Float
= Float or slack is a measure of scheduling flexibility.

Formulas
ES
EF
LF
LS
TF

= Early Start
= Early Finish
= Late Start
= Late Finish
= Total Float

= EF pred terbesar + 1
= ES + OD 1
= ES suc 1
= LF OD + 1
= ES suc EF pred 1 = Zero = Critical
= LS ES; LF EF
FF = Free Float
= LF OD ES ; FF is defined as the amount of time an activity
can be delayed without delaying the early start of any immediately following
activities
Float = Float or slack is a measure of scheduling flexibility.
OD = Original Duration
Pred = Predecessor
Suc = Successor
Bwpas = LF(1) akhir
LF(2)

= EF akhir
= LS suc terbesar 1

Bwpas = LF(1) require = EF akhir


LF(2)
= LS suc terbesar 1
CPM (Critical Path Method) : Determine the group of activities that cannot be delayed without delaying
the completion date for the entire project.
In order to find :
1.
Early Dates: By forward Pass Calculation
2.
Late Dates : By Backward Pass Calculation
3.
Total Float : By substract early dates from late dates
Afrizal N
4.
Total float is belong to entire string of activities Not to an individual activity

45

CPM

(Example)

Negative Float
Change on impose date : Impose finish date of work period 12 (Constrained)
1

3
Activity A
Duration= 3

-5
-6

TF

-3
-6

Activity B
Duration= 1
-2
-6

8
Activity C
Duration= 4

-2
-6

-1
-6

2
-6

18
Activity D

Duration= 10
3
-6

12
-6

Represents an Impossible situation so it must be eliminated


Solutions to eliminate Negative Float :
1.

Surrender; let the end dates slip

2.

Add resources ( Crashing)

3.

De-scope (best implement in the conceptual stage)

4.

Improve the work process; fast tracking and work smarter


Afrizal N

46

Compression (With Crashing)


(Basic Knowledge)
All Activity Crash

h
as
Cr

Program Cost ( $ / IDR )

Minimum Cost Total Crash

Increase cost

Normal Operation

Program completion Time, Weeks


Afrizal N

47

Project Finish Constraint

Required
Completion Date

Project Start Date


Projected Lateness
Negative Slack

(a)

(b)

ET1

ET1

ET2

ET3

ET4

ET5

ET2 ET3

ET4

ET5

ET6

ET6

ET7

ET7

ET8

Expected
Completion

ET8
Expected
Completion

(c)
ET1 ET2 ET3 ET4

ET5

ET6

ET7

ET8

Afrizal N

Expected
Completion
Contingency
Positive Slack

48

Resources Leveling Heuristic


Implement this method to the activities that has Slack/Positive Float
Resource Leveling generally extend the completion date of project.

Also called as
- Resource Based Method ; optimizing project team member or
Resources constrained scheduling where we have the constraint is
limitation on the quantity of resource available.

the

Reverse Resource Allocation Scheduling


Resource be scheduled in reverse from ending date

Critical Chain
A technique that modifies the project schedule to account for limited
resources.

Afrizal N

49

Resources Leveling Heuristic


SCHEDULE DEVELOPMENT
Simple Exercise :

Activity A

A required 10 man, B required 20 man, the


availability is 25 man, WP = 30

Duration= 5
11

What should you do?


a.

11

Activity C

Assign 10 to A and 15 to B
1

b.

Assign 5 to A and 20 to B

c.

Assign all to A and put them all to B

d.

Assign 12 to A and 13 to B
E

Activity B

10

10
Activity B

10

30

15

Aktivity A
11

25

Duration=15
11

CP is B-C
This is a sample of resource
leveling

Aktivity B
10

25

Aktivity C
15

Duration=10
1

16

The Answer is B,

Activity C
1

Duration=15

Duration=10

Duration= 5
L

10

5
Activity A

25

15

Afrizal N

50

Project Schedule

Basic Knowledge

Type of project schedule format :


1.

Project Network Diagram : PDM and ADM


Usually show both project logic and project Critical
Path

2.

Bart Charts

3.

Milestone Charts
Milestone : a significant event in the project, usually
completion of a major deliverables or activity with
zero duration

4.

Time Scale Networks Diagram


Usually show project logic, activity duration &
Schedule information.

Afrizal N

51

Activity Float
5

10

12

L=7

(Basic Knowledge)

21
25

8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Independence Float

X
L=7
X

Free Float

L=7
SPAi

SPLi

SPA5

SPL5

Total Float
Afrizal N

SPAj

SPLj

SPA9

SPL9

52

6. 5. SCHEDULE DEVELOPMENT
OUTPUTS
.1. Project schedule (6.5.3.1 p.
149)
Project schedule network diagrams
Bar charts
Milestone charts
.2. Schedule model data (6.5.3.2 p.
151)
.3. Schedule baseline (6.5.3.3 p.
151)
.4. Resource requirement
(updates)
(6.5.3.4 p. 151)
5. Activity attributes (updates)
(6.5.3.5 p. 151)

Outputs
Outputs
.1.
Project
schedule
.1. Project schedule
.2.
.2.Schedule
Schedulemodel
modeldata
data
.3.
Schedule
baseline
.3. Schedule baseline
.4.
.4.Resource
Resourcerequirement
requirement
(updates)
(updates)
.5.
Activity
.5. Activityattributes
attributes(updates)
(updates)
.6.
Project
calendars
(updates)
.6. Project calendars (updates)
.7.
.7.Requested
Requestedchanges
changes
.8.
Project
management
.8. Project managementplan
plan
(updates)
(updates)
. . Schedule
Schedulemanagement
managementplan
plan
(updates)
(updates)
PMBOK Guide page 143

.6. Project calendars (updates)


(6.5.3.6 p. 152)
.7. Requested changes
(6.5.3.7 p. 152)
8. Project management plan
(updates)
. Schedule management plan Afrizal N
(updates)

53

Bar Chart (Basic Knowledge)

Bar Chart = Gantt Charts


Show tasks relative to time (activity start and end dates), expected
duration, usually not show dependencies.
Relatively easy to read start/finish date and view progress
Most proper for the Management Afrizal N

54

PERT Chart

(Basic Knowledge)

Program Evaluation and Review Technique

Afrizal N

55

Milestone Charts
DATA
DATE

SCHEDULE DEVELOPMENT
EVENT

JAN

Basic Knowledge

FEB

MAR

APR

MAY

JUN

JUL

AUG

Contract Award
Specification Review
Design Review
Value Engineering
Site Preparation
Quality Planning

Afrizal N

56

Time Scale Network Diagram


= Blend of project network diagram and bar chart.
SCHEDULE DEVELOPMENT
A

10

10

11

12

11

13

12

14

Time

Afrizal N

57

Arrow Diagram

(Basic Knowledge)

D
2

13

13

10

23

23

23

23

F
C

23

23

32

32

36
36

11
Identified CPM (Critical Path Method)

Afrizal N

58

6. 6. SCHEDULE CONTROL
INPUTS
Perhatian
dengan :
Progress schedule.
Faktor yang mempengaruhi timbulnya
perubahan schedule.

Inputs
Inputs: :
.1.
.1.Schedule
Schedulemanagement
managementplan
plan
.2.
Schedule
baseline
.2. Schedule baseline
.3.
.3.Performance
Performancereports
reports
.4.
Approved
changes
.4. Approved changesrequest
request

Adanya perubahan pada schedule proyek


Mengelola perubahan yang terjadi saat ini.
.1. Schedule management plan
(6.6.1.1 p. 153)
.3. Performance reports (6.6.1.3 p.
(4.3) berisi Schedule management plan
153)
(Chapter 6 ) bagaimana project
(10.3.3.1) menyediakan informasi pada
schedule akan dikelola dan
kinerja schedule, kesesuaian terhadap
dikendalikan
.2. Schedule baseline (6.6.1.2 p.
rencana,
153)
(6.5.3.1) project schedule mengontrol
.4. Approved changes request
approved project schedule. (6.5.3.3)
(6.6.1.4 p. 153)
schedule baseline komponen project
Hanya approved change request
management plan (4.3).
(4.4.1.4) yang telah diproses
Menyediakan dasar pengukuran dan
sebelumnya melalui proses Integrated
laporan kinerja schedule sebagai
Change Control (4.6) digunakan untuk
bagian dari kinerja pengukuran
mengupdate project schedule
baseline.
baseline.
Afrizal N
59

6. 6. SCHEDULE CONTROL
TECHNIQUES
.1. Progress reporting (6.6.2.1 p.
153)

.2. Schedule change control system


(6.6.2.2 p. 153)
.3. Performance measurement
(6.6.2.3 p. 154)

TOOLS &
Tools
Tools&&Techniques
Techniques
.1.
Progress
reporting
.1. Progress reporting
.2.
.2.Schedule
Schedulechange
changecontrol
control
system
system
.3.
.3.Performance
Performancemeasurement
measurement
.4.
Project
management
.4. Project managementsoftware
software
.5.
Variance
analysis
.5. Variance analysis
.6.
.6.Schedule
Schedulecomparison
comparisonbar
bar
chart
chart

.4. Project management software


(6.6.2.4 p. 154)
.5. Variance analysis (6.6.2.5 p.
154)
.6. Schedule comparison bar chart
(6.6.2.6 p. 154)

Afrizal N

60

Variance Analysis (Basic Knowledge)

Variance
report

Delay ?

No

Forecasting

Yes

Corrective
Action

Afrizal N

61

Corrective Action
Any delay

(Basic Knowledge)

Propose
Alternatives
Determine
Corrective
Action To be
Taken
Issued Notice
of Corrective
Action to the
Parties
Involved
Afrizal N

Re planning

62

6. 6. SCHEDULE CONTROL
OUTPUTS
.1. Schedule model data (updates)
(6.6.3.1 p. 154)
Stakeholder terkait memberikan
catatan yang berarti didalam
mengupdate informasi pada project
schedule model .
.2. Schedule baseline (updates)
(6.6.3.2 p. 155)
Revisi perubahan schedule stat date
and finish date dalam approved
schedule baseline.
.3. Performance measurements
(6.6.3.3 p. 155)
Perhitungan (SV) dan (SPI) mempunyai
nilai terhadap komponen.WBS.
.4. Request changes (6.6.3.4 p.
155)
Schedule variance analysis, review
progress report, hasil pengukuran
kinerja, modifikasi project schedule
model dapat menghasilkan Requested
Afrizal N
changes. (4.4.3.2)

Outputs
Outputs
.1.
Schedule
.1. Schedulemodel
modeldata
data
(updates)
(updates)
.2.
Schedule
.2. Schedulebaseline
baseline(updates)
(updates)
.3.
Performance
measurements
.3. Performance measurements
.4.
.4.Request
Requestchanges
changes
.5.
Recommended
.5. Recommendedcorrective
corrective
actions
actions
.6.
Organizational
.6. Organizationalprocess
process
assets
(updates)
assets (updates)
.7.
Activity
.7. Activitylist
list(updates)
(updates)
.8.
Activity
attributes
.8. Activity attributes(updates)
(updates)
.9.
Project
management
.9. Project managementplan
plan
(updates)
(updates)

63

6. 6. SCHEDULE CONTROL
OUTPUTS
.5. Recommended corrective actions
(6.6.3.5 p. 155)
.6. Organizational process assets
(updates)
(6.6.3.6 p. 155)
.7. Activity list (updates)
(6.6.3.7 p. 156)
.8. Activity attributes (updates)
(6.6.3.8 p. 156)

Outputs
Outputs
.1.
Schedule
.1. Schedulemodel
modeldata
data
(updates)
(updates)
.2.
Schedule
.2. Schedulebaseline
baseline(updates)
(updates)
.3.
Performance
measurements
.3. Performance measurements
.4.
.4.Request
Requestchanges
changes
.5.
Recommended
.5. Recommendedcorrective
corrective
actions
actions
.6.
Organizational
.6. Organizationalprocess
process
assets
(updates)
assets (updates)
.7.
Activity
.7. Activitylist
list(updates)
(updates)
.8.
Activity
attributes
.8. Activity attributes(updates)
(updates)
.9.
Project
management
.9. Project managementplan
plan
(updates)
(updates)

.9. Project management plan


(updates)
(6.6.3.9 p. 156)

Afrizal N

64

Schedule Control Flow (Basic Knowledge)


Progress Monitoring
Schedule Assessment
Variance Analysis
Forecasting

Corective Action
Replanning

Afrizal N

65

Control Management Aspect

Plan the Future :


Technical implication
Control of consultant
Control of pre project activity
Performance appraisal
Implementation of control system

Understand and apply schedule control requirement :

Afrizal N

66

Schedule Control Requirement


1. Target dates & milestone
2. Scope control
3. Appraisal of schedule control capability
4. Baseline schedule
5. Manpower loading
6. Periodical review
7. Interface key dates
8. Report and analysis schedule status
9. Trend analysis (Rescheduling)

Afrizal N

67

Appraisal of Schedule Control Capability


Schedule Control Written Procedures
Organizing & Staffing
Use of specialist
Reference of experience
Methodology
Bar chart
CPM Network
Reporting Format and Procedures

Afrizal N

68

Schedule Assessment (Basic Knowledge)


Impact
Completion
Date

Update
Progress

Review Critical
& Next Critical
Activities

Variance
Analysis

Prepare Report

Schedule
Variance
report
Afrizal N

69

Progress Monitoring (Basic Knowledge)


Progress

Progress

Progress

Progress

Agregate
Progress

No

Approve

Afrizal N

Yes

Schedule
Assessment

70

How to Improve Progress (Basic Knowledge)


Increase Productivity
Increase Manpower
Work Overtime
Reduce the Scope of Work whenever possible
Subcontracting part of the work
Fast-Tracking

Afrizal N

71

Earned Value Analysis (Basic Knowledge)

Cost

JutaIDR

Projected Budget Completed

2000

100

1800

90

1600

80

1400

70

1200

60

1000

50

800

40

600

30

400

20

200

10

Cost Overrun
Actual Cost (AC)
(ACWP)
Projected Time Completed

Planned Cost (PV)


(BCWS)

Schedule Overrun

Work Performed (EV)


(BCWP)

3
1

6
2

12
3

25
4

35
5

52
6

75
7

Data Date

85
8

95
9

98
10

99
11

100
12

%
13

Month

Afrizal N
Earned Value
Analysis

72

PERENCANAAN WAKTU
PROYEK

Afrizal Nursin (0815 8611 3660)

Thank you
Afrizal N

73

You might also like